Area-based approach & grid congestion · Heerenveen · March 2026
IBF Heerenveen: area-based approach for 60+ companies.
The largest logistics business park in the northern Netherlands, with 60+ companies on 250 hectares, had an energy problem on every front: grid congestion, too little charging infrastructure and no coordination. Energyc introduced an area-based approach with Liander.
At IBF Heerenveen (250 hectares, 60+ logistics companies) the grid was congested. Liander could not handle 60+ upgrades at once, charging infrastructure for electric trucks was missing and every company was looking for its own solution. The Province of Fryslân and the Municipality of Heerenveen asked Energyc to coordinate an area-based approach.
Project management of a three-year programme: stakeholder mapping and a joint energy masterplan, then the design of an energy hub with one grid connection, cable pooling and a 4 MWh battery, plus three shared charging hubs. The final step is handing governance over to an area cooperative.
Three shared charging hubs (1.2 MW DC combined) have been operational since late 2025. Construction of the energy hub starts in Q2 2026, and 28 companies are joining the cooperative that will be formalised in Q4 2026. The Ministry of Housing and Spatial Planning (VRO) designated IBF as a national pilot for area-based energy transition on business parks.
A business park in crisis.
With 250 hectares and 60+ logistics companies, IBF Heerenveen is the largest business park in the northern Netherlands. But the park ran into several constraints at once: grid congestion (no new connections), a shortage of charging infrastructure for the growing fleet of electric trucks, and no overall coordination between companies.
Individual companies tried their own solutions but ran into grid limits. Liander's message: the network cannot handle 60+ upgrades at once, so the park has to work out collectively what makes sense.
The Province of Fryslân and the Municipality of Heerenveen brought in Energyc to coordinate the area-based approach, as long-term project lead on a multi-year programme rather than as a one-off advisor.
Energy hub, shared charging hubs, cooperative governance.
We set up a three-year project structure. Year 1: stakeholder mapping (60+ companies, municipality, province, Liander, business association, grid operator) and a joint energy masterplan. Year 2: first construction, with 3 shared charging hubs and the first phase of an energy hub. Year 3: governance handover to an area cooperative.
The energy hub is the core of the approach: one large grid connection for the park instead of 60+ individual connections. Companies connect behind it through cable pooling. A 4 MWh battery on site shaves peaks and offers flexibility to Liander at peak times.
The three shared charging hubs (1.2 MW of DC capacity combined) serve logistics operators on demand, with smart charging linked to truck scheduling. This works especially well for companies that do not yet have a fully electric fleet and cannot justify their own charging infrastructure.
You can't improve an area of 250 hectares with 60+ companies piece by piece. It has to be tackled as an ecosystem. That's what works here, and what other parks now want to copy. Energyc · Area-based approach
Three charging hubs live, a model for the whole of the Netherlands.
The first 3 charging hubs have been operational since late 2025. Construction of the energy hub starts in Q2 2026. In Q4 2026 the cooperative governance will be formalised, and 28 companies are already joining.
The Ministry of Housing and Spatial Planning (VRO) has designated IBF as a national pilot for area-based energy transition on business parks. Other municipalities (including Tilburg and Almelo) are in exploratory talks with Energyc.
What this project delivered.
- ✓3 shared DC charging hubs operational (1.2 MW total)
- ✓Energy hub design with 4 MWh battery, construction Q2 2026
- ✓28 companies joining the cooperative (formalisation Q4 2026)
- ✓National pilot status granted by VRO
- ✓Liander prioritises the area-based solution over individual upgrades
- ✓Model transferable to other large business parks