Grid congestion & sustainability · Drachten · 2026
Metalis. Growth without extra grid capacity.
Metalis wanted to grow, build new premises and go gas-free, but Liander offered zero kilowatts of available capacity. Energyc developed an integrated energy system that keeps the company fully operational, takes it from 67 to 0 tonnes of CO2 and turns sustainability into a commercial advantage.
Metalis, a metalworking company in Drachten, wanted new premises, gas-free processes and room for extra production lines, but Liander offered zero kilowatts of available capacity. Waiting for a grid upgrade would take years.
Design and project management of an integrated energy system: 450 solar panels, a 1.2 MWh battery, a CBC-T contract with Liander and an EMS controlling it all. From initial scoping to commissioning, including permits, financing and supplier selection.
New building fully operational after a lead time of 10 months, without waiting for the grid. CO2 emissions down from 67 to 0 tonnes a year; the investment is expected to pay back in 6–8 years through lower energy costs and no longer paying for gas.
Situation
Zero kilowatts. So how do you grow?
Metalis is a metalworking company in Drachten with ambitions to grow. The plans: new premises, gas-free processes, room for extra production lines.
Liander had one answer: within the requested timeframe there were zero kilowatts of available capacity. Grid congestion. A new building without electrical capacity is of no use, and nor are gas-free processes without electricity.
Waiting for a grid upgrade was not an option. It would take years and the growth opportunity would be lost. The question became: how do you get a building into operation on a congested grid?
Approach
An integrated energy system.
No standalone solar panels, no standalone battery. A single system in which generation, storage and flexible consumption together solve the capacity problem.
1. Solar: 450 solar panels on the roof of the new building, sized to the company's load profile.
2. Storage: 1.2 MWh battery that shaves peak-hour demand and stores surplus solar.
3. Smart contracting: CBC-T (temporary capacity restriction contract) with Liander for the winter peak hours when the system needs extra capacity.
4. EMS: energy management system that coordinates everything and provides data for further optimisation.
Operational. Gas-free. With a commercial edge.
From waiting for the grid to leading the way.
The system has been operational since 2026. Metalis has achieved its growth ambition. CO2 emissions have been cut from 67 tonnes a year to zero. And its positioning on sustainability opens commercial opportunities with large customers that set ESG requirements for their supply chains.
Figures from Energyc's project evaluation (2026). CO₂: scope 1, annual natural gas consumption before and after the conversion. Payback period: calculated (6–8 years), not yet achieved.
Thanks to Energyc we've got to grips with grid congestion and made lasting cuts to our energy costs. Pragmatic, knowledgeable and always a step ahead. Metalis B.V. · Drachten
What was the insight that made the difference?
Solve the problem at the connection itself instead of waiting for a grid upgrade (years). Designing generation, storage and control together made the available capacity sufficient.
How long was the lead time?
10 months from initial scoping to commissioning, including permits, financing, supplier selection and construction. Much faster than waiting for a grid upgrade.
What is the return?
The investment pays back in 6–8 years through lower energy costs and no longer paying for gas. On top of that come commercial opportunities from ESG positioning and CO2-neutral production.
Has your grid operator offered you zero kW too?
Schedule an exploratory call. We will show you which strategies could work in your situation. There are often more options than you think.
Discuss your situation →