Grid congestion & housing · Drachten · March 2026
Grid-aware new build: national pilot with VRO.
The electricity grid has run out of capacity. Across the Netherlands, grid congestion threatens to halt new-build projects, a problem the new Energy Act (Energiewet) only makes more urgent. Energyc worked with municipalities, Liander and the Ministry of Housing and Spatial Planning (VRO) to develop a unique, integrated approach that makes housebuilding possible all the same.
Grid congestion threatens to halt housebuilding across the Netherlands: Liander cites waiting times of more than 5 years to connect new housing developments. The Ministry of VRO wanted an approach that works with the grid capacity available now, rather than waiting for grid expansion.
Design of the area's energy system with municipalities, Liander and VRO: a collective neighbourhood battery, local PV using cable pooling, smart metering with dynamic tariffs and a connection of 15 kW per home instead of 35 kW. We also ran the MEAT (EMVI) tender for the builder and energy system supplier, after a market consultation with 4 parties.
Pilot of 84 homes in Drachten, with first-phase completion in Q2 2026, Liander monitoring grid use and the ministry funding 30% of the pilot's additional costs. VRO has designated the pilot a nationally scalable model; 12 other municipalities are in exploratory talks.
A country that can no longer build.
In 2026, grid congestion threatens to stall new-build projects across the Netherlands. Liander has indicated that waiting times to connect new housing developments are exceeding 5 years. Meanwhile the housing shortage is growing more acute: the Netherlands needs 100,000+ extra homes a year.
The crux: traditional housing developments are designed for guaranteed peak capacity (35–50 kW per home), while actual peaks are usually lower. But the grid has to be able to handle peak demand, or it goes down. With all the new heat pumps and EV chargers, peaks will rise further.
The Ministry of VRO (Housing and Spatial Planning) wanted an alternative approach that works with the capacity available now, rather than waiting for grid expansion.
An alternative energy system, with connections that stay within capacity.
Energyc developed an area-wide energy system in which the neighbourhood absorbs its own peaks through a combination of (1) a collective neighbourhood battery that shaves peak-hour demand, (2) local PV generation using cable pooling, (3) smart metering with dynamic tariffs for residents, and (4) a fundamentally smaller grid connection (15 kW per home instead of 35 kW).
That sounds like less capacity, but the average peak is 8–12 kW. The extra capacity from the battery and PV absorbs the peaks. Residents notice no loss of comfort, and the connection fits within the existing grid.
We ran the tender for delivery (a turnkey builder plus energy system supplier) after a market consultation with 4 parties, and awarded on MEAT (EMVI). The ministry funded 30% of the pilot's additional costs.
We're not waiting for grid expansion that won't arrive until 2030. We build neighbourhoods that work within the grid we have, and residents don't notice the difference. Energyc · Grid-aware new build pilot
Pilot under way, blueprint ready to scale.
The pilot in Drachten covers 84 homes, the first phase of which is due for completion in Q2 2026. Liander monitors grid use and is closely involved in data exchange. Results are shared directly with other municipalities.
On scalability: 12 other municipalities in the Netherlands are in exploratory talks about applying the same model. The Ministry of VRO has designated the pilot a nationally scalable model and is working on a subsidy scheme to cover the additional costs at area level.
What this project delivered.
- ✓First national pilot for congestion-proof new build
- ✓84 homes, first-phase completion Q2 2026
- ✓Collective neighbourhood battery + cable-pooled PV system
- ✓15 kW connection per home instead of 35 kW (comparable comfort)
- ✓MEAT (EMVI) tender with 4 bidders, no challenges
- ✓Model shared with 12 other municipalities; VRO is working on a national scheme
Figures from Energyc's project evaluation; measurement period and scope defined per project.