Aerial photo of Raben Group's logistics charging hub with 400 kW DC charge points

Logistics charging & grid congestion · Northern Netherlands · January 2025

Raben Group: first large-scale DC charging hub in the northern Netherlands.

Raben Group, one of Europe's largest logistics providers, wanted a charging hub for heavy electric transport in the northern Netherlands. Energyc ran the whole programme, from subsidies and permits to procurement and delivery.

400 kWDC charge points
ANWConnected within 6 months
AanZET + EIASubsidies secured
The brief

Raben Group wanted a DC charging hub for heavy electric trucks in the northern Netherlands within 18 months. The site was in a congestion area: Liander quoted a 5–7 year wait for a 400 kW connection, while the trucks had already been ordered for Q4 2024.

Energyc's role

The whole programme: negotiating an ANW contract with Liander, sizing four DC chargers with smart charging and a 200 kWh battery, the subsidy stack (AanZET and EIA) and coordinating the planning, environmental and grid connection permits, through to procurement and delivery.

Result

Connected within 6 months instead of 5+ years. The charging hub has been operational since Q4 2024, with 8 electric trucks running line-haul services from the northern Netherlands. AanZET subsidy of €175,000 plus EIA tax deduction secured.

The challenge

An international fleet plan needs local delivery.

Raben Group is a European logistics giant with 14,000 employees in 15 countries. The corporate target: 30% of the fleet electric by 2027. For the Dutch business, that meant building a DC charging hub for heavy trucks within 18 months.

But the site was in a congestion area. Liander said a 400 kW connection would mean waiting 5–7 years. Raben could not wait that long: the electric trucks had already been ordered and were due in Q4 2024.

Our approach

ANW connection + smart use of the contract + subsidy stack.

Energyc negotiated an ANW contract with Liander: a capacity restriction contract under which Raben agreed to a maximum of 3 hours a day of curtailment at peak times, in exchange for an accelerated connection (within 6 months instead of 5+ years).

We sized four DC chargers of 400 kW each with smart charging: total power demand stays below 800 kW at all times, however many trucks are charging. A supporting 200 kWh battery at the hub provides peak shaving.

Subsidies: AanZET for heavy commercial vehicle charging infrastructure (€175,000), EIA tax deduction for the battery and the supporting electrical installation. Permits: we coordinated the planning permit (omgevingsvergunning), environmental permit and grid connection permit.

Waiting five years for grid expansion wasn't an option. But you don't have to wait, if you're prepared to plan within the capacity available. Raben Group · Logistics director
The result

Operational within 14 months, with no waiting time.

The charging hub has been operational since Q4 2024. The first 8 electric trucks (Volvo FH Electric and Mercedes eActros) now run line-haul services from the northern Netherlands to the rest of Europe. In the first months of operation the ANW contract was rarely called on, and the rest of the time Raben used the full capacity.

For Raben Group, an important marker of delivery reliability on the way to its 2027 corporate target. For Energyc, proof that ANW + smart charging + smart sizing is a route that works, even in a heavily congested area.

Highlights

What this project delivered.

  • ✓4 DC chargers of 400 kW each with smart charging up to 800 kW total
  • ✓ANW contract with Liander: connected within 6 months
  • ✓200 kWh support battery for peak shaving
  • ✓AanZET subsidy of €175,000 secured plus EIA tax deduction
  • ✓Operational Q4 2024, fleet of 8 electric trucks running
  • ✓Model applicable to other logistics sites in congestion areas

Figures from Energyc's project evaluation; measurement period and scope defined per project.