The business battery in 2026: costs, payback and subsidy, independently calculated
In 2026 a business battery (battery storage) earns money in two ways you can calculate in advance: a lower monthly peak (at Liander €3.57 per kW per month at medium voltage) and more self-consumption of your solar power. The subsidy consists of the 40% energy investment allowance and, in congestion areas, 40% Flex-e up to €300,000 (2026 window closed on 15 October); the two do not stack on the full investment, and SDE++ does not cover batteries. Below we run the numbers, using only the 2026 grid tariffs and scheme texts as sources, and show the situations in which you are better off not buying the battery.
Does a business battery pay off in 2026, and what subsidy can I get?
A business battery pays off in 2026 if it lowers the monthly peak (kWmax tariff, at Liander €3.57 per kW per month at medium voltage, MV) and uses your own solar power; income from a capacity restriction contract or trading is conditional. The subsidy is the 40% energy investment allowance (net 10.3% in RVO's worked example) and, in congestion areas, 40% Flex-e with a minimum of €25,000 and a maximum of €300,000; the window closed at 17:00 on 15 October 2026. Flex-e is deducted from the EIA base, so the two schemes together do not cover 80%. Batteries do not fall under SDE++. On a low-voltage (LV) connection up to 50 kW, with no renewable generation installation above 15 kW peak on the same connection and no congestion, a battery is rarely profitable.
What a battery earns, and which two value streams you can calculate in advance.
A business battery can make money in four ways. Two are set by published tariffs, so you can calculate them in advance. The other two depend on a contract you do not yet have or a market you do not control.
| Value stream | How it works | How firm |
|---|---|---|
| 1. Peak reduction (kWmax) | The battery discharges at the moment of the monthly peak, so the highest quarter-hourly demand comes out lower. The kWmax tariff per grid level is in the grid operator's tariff sheet. | Firm. Published tariff (Tarievencode elektriciteit 2026, art. 3.10; Liander 2026). |
| 2. More solar self-consumption | Store surplus solar power during the day and use it yourself later instead of buying electricity. | The mechanism is firm. The return depends on your own purchase and feed-in prices. |
| 3. Congestion mitigator or capacity restriction contract | Reducing capacity at the grid operator's request. Earns priority in the queue (congestion mitigator) or a payment in euros per MW (CBC or CSC). | Conditional. No fixed price; bespoke per contract (ACM). |
| 4. Trading on the electricity market | Charging at low prices and discharging at high prices, using software linked to a sub-market. | Conditional. Market-dependent. If trading is the primary purpose, that is grounds for rejection under Flex-e (Stcrt. 2026, 12853). |
A business case that only stacks up with stream 3 or 4 is a business case built on an assumption. So we first calculate streams 1 and 2 using the published tariffs, and only then what a contract or trading can add on top. The sums in a supplier's quotation often run exactly the other way round.
The calculation basis: kW contract and kWmax.
Alongside the kWh tariff, the Tarievencode elektriciteit 2026 (the Electricity Tariff Code) has two capacity tariffs: kW contracted, for the capacity you may contractually use, and kW max per month, for your actual highest quarter-hourly demand in a month. How grid costs are divided across these tariff components differs by grid level. At medium voltage, kW contracted covers 25% of the allocated costs, kW max per month 25% and the kWh tariff 50% (Tarievencode elektriciteit 2026, art. 3.10(1)). At low voltage above 3x80 A there is no kW max: kW contracted covers 16% and the kWh tariff 84% (art. 3.11(1)). A battery affects both capacity tariffs, but not in the same way.
| Grid level (Liander) | Contracted capacity | kW contract, per kW per month | kWmax, per kW per month |
|---|---|---|---|
| LV | up to 50 kW | € 1,49 | no kWmax tariff |
| MV/LV | > 50 to 136 kW | € 3,74 | € 3,57 |
| MV | > 136 to 2,000 kW | € 2,29 | € 3,57 |
| IV/MV or HV/MV | > 2,000 kW | € 3,99 | € 6,24 |
| IV | > 2,000 kW | € 3,93 | € 5,39 |
Liander, large-consumer tariff sheet 2026 (version 2026.1.1), valid 1 January to 31 December 2026, excluding VAT. Other grid operators publish their own amounts using the same tariff structure from the Tarievencode. LV = low voltage, MV = medium voltage, IV = intermediate voltage (TS), HV = high voltage.
Worked example (our calculation from these tariffs, not a published figure). An MV customer with 500 kW contracted capacity pays 500 × €2.29 × 12 = €13,740 a year in kW contract charges. If a battery takes 100 kW off the peak every month, that saves 100 × €3.57 × 12 = €4,284 a year in kWmax charges. If the contracted capacity is then also lowered by 100 kW, that adds 100 × €2.29 × 12 = €2,748 a year. Together that makes €7,032 a year.
That second lever is the risky one. Liander only lowers contracted capacity if it has not been adjusted upwards in the past 12 months. If you then exceed it just once, the overrun counts as a request for an increase, backdated to the date of your reduction. Liander gives its own example: reduction requested on 1 February, overrun on 1 July, you pay for the higher capacity from 1 February (Liander, tariff sheet 2026). In congestion areas, moreover, capacity is not increased automatically after an overrun.
Two things stand out in the tariff sheet. A large consumer at Liander pays no transport charges for feed-in; feeding in costs nothing on the grid side and earns nothing there either. And on an LV connection up to 50 kW there is no kWmax tariff. There, a peak saving comes only through the kW contract tariff of €1.49 per kW per month, and that is the smallest lever of all.
Two battery codes, one three-month notification deadline.
The energy investment allowance is 40% (Wet IB 2001, the Income Tax Act, art. 3.42(3), version of 1 January 2026). It is a deduction from profit, not a subsidy. RVO works it through in its own brochure: with €500,000 profit and €300,000 in energy investments, the deduction is €120,000, corporate income tax falls from €115,400 to €84,440 and the benefit is €30,960, or 10.3% of the investment (Brochure EIA Energielijst 2026, p. 4). The minimum per asset is €2,500.
The Energielijst 2026 has two battery codes with different conditions. The condition linking the battery to your own generation applies to one and not the other, and that is where notifications go wrong.
| Code 251118 | Code 260101 | |
|---|---|---|
| Description | Battery for storing renewably generated electricity | Storage of electrical energy, switching on or off automatically depending on an electricity sub-market |
| Minimum size | at least 5 kW and 15 kWh | at least 5 kW and 15 kWh |
| Generation link requirement | Required: connected to a renewable generation installation with a peak capacity above 15 kW, on the same grid connection | None |
| Software requirement | None | Required: no deduction without a software link to an electricity sub-market |
| Excluded | Flooded lead-acid; batteries in vehicles, including internal transport | Flooded lead-acid |
| Changed in 2026 | Gel lead-acid now qualifies; peak capacity counts for the generation installation | — |
Brochure EIA Energielijst 2026, codes 251118 (p. 63) and 260101 (p. 66), changes in chapter 4 (p. 77).
Your situation determines the choice. If the battery is connected to a renewable generation installation, such as solar panels, with more than 15 kW installed peak capacity on the same grid connection, 251118 is the route. Without such an installation, that leaves 260101, which requires the battery to switch on and off automatically depending on an electricity sub-market. A battery that only flattens your own peak, with no such generation installation and no automatic control linked to a sub-market, fits neither code.
The notification deadline is strict. The notification must reach RVO within three months of entering into the investment commitment. That moment is the signing of the purchase agreement, or an order given verbally or digitally; expressly not the quotation, invoice or payment date (Brochure EIA 2026, § 2.1.2). If the battery is part of a main contract, the date that main contract is concluded counts.
For production costs, the deadline is three months after the end of the calendar quarter in which they were incurred, or three months after commissioning if that falls in the same quarter. You submit the notification online using eHerkenning (the Dutch business login) at assurance level 2+; paper notifications are not accepted.
In the Belastingplan 2027 (the 2027 Tax Plan, presented on Budget Day, Prinsjesdag, 15 September 2026), the cabinet proposes raising the rate to 45% for 2027. The proposal still has to pass both houses of parliament; the law currently says 40%. If it is adopted, the date of the investment commitment counts: a commitment in January 2027 falls under it, one in December 2026 does not. On a €200,000 investment that is a deduction 5 percentage points higher, or €10,000 extra, worth roughly €2,580 net at 25.8% corporate income tax (our calculation using the proposed percentages).
Flex-e and EIA: you can combine them, but not add them up.
In 2026 Flex-e covered 40% of the eligible costs of flexibility measures, with a minimum of €25,000 and a maximum of €300,000 per application (Stcrt. 2026, 12853). The rate had been 35% and was raised this year. A battery-only application needed at least 50 kW of capacity, and RVO checked whether the quotation was in line with the market. The 2026 window closed on 15 October 2026 at 17:00.
To qualify, you needed a large-consumer connection in an area the grid operator had declared as having offtake congestion. From 100 kW of flexible capacity (part d, sub-ceiling €9,690,344) you also had to show a signed offtake congestion management contract with the grid operator: a capacity steering contract, including the capacity restriction contract, or a bid-obligation contract for redispatch. A time-block contract (blokstroom) did not count. Below 100 kW (part c, sub-ceiling €6,460,229) that contract requirement did not apply, but RVO asked for a conceptual technical design and for energy saving to be addressed first. Mobile or temporary batteries were excluded, as was a battery intended primarily for trading. Only installation costs directly related to siting and connecting the battery counted. Our Flex-e guide sets out the application route.
Now for the stacking. EIA may be combined with an investment subsidy such as Flex-e, but you deduct the subsidy amount, once finally determined, from the purchase costs before calculating the EIA (Brochure EIA 2026, § 1.3). So twice 40% is not 80%. Our calculation for a €200,000 battery:
| How the leaflet adds it up | What RVO requires | |
|---|---|---|
| Battery investment | € 200.000 | € 200.000 |
| Flex-e, 40% | € 80.000 | € 80.000 |
| EIA base | € 200.000 | €120,000 (investment minus Flex-e) |
| EIA deduction, 40% of the base | € 80.000 | € 48.000 |
| Tax benefit at 25.8% corporate income tax | € 20.640 | € 12.384 |
| Coverage in this example (subsidy + tax benefit) | € 100.640 = 50,3% | € 92.384 = 46,2% |
| From your own funds | € 99.360 | € 107.616 |
Our own calculation. Percentages from Wet IB 2001 art. 3.42 and Stcrt. 2026, 12853; the 25.8% corporate income tax rate applies to profit above €200,000; below that the rate is 19%, so the benefit is lower. The €80,000 subsidy falls within the Flex-e limits of €25,000 to €300,000. Assumptions: the full investment is eligible, the battery meets the conditions of both schemes and the full deduction is used at 25.8%.
Anyone who reads "40% subsidy plus 40% deduction" in the leaflet as 80% coverage is counting on €160,000 where this example gives €92,384. That €67,616 difference is the amount by which most battery business cases in quotations look too good.
Other combinations: EIA and MIA are mutually exclusive for the same costs. You choose one scheme or split the costs, and a notification cannot be converted afterwards. EIA and ISDE are mutually exclusive for the same asset. An SDE++ award rules out EIA, but for a battery that is an academic question: the Aanwijzingsregeling SDE++ 2026 (window 27 October to 26 November 2026, ceiling €8 billion) does not once use the words "batterij" (battery), "accu" (accumulator) or "elektriciteitsopslag" (electricity storage). A business battery gets no SDE++. Nor does the Milieulijst 2026 (the Environment List) include a stationary battery. The overview of schemes is on our subsidy page.
Congestion mitigator or capacity restriction contract: priority is not payment.
Quotations often confuse two terms. They come from different rules and deliver different things: one a place in the queue, the other money.
A congestion mitigator (congestieverzachter) is a term from the ACM's prioritisation framework. Since 1 January 2026, grid operators in congestion areas have had to give priority to three categories of transport request. Category 1 is congestion mitigators: parties that free up grid space so that others gain access. Category 2 is safety, category 3 basic needs such as housing and education (ACM, code decision on prioritisation of transport requests, 12 December 2025). The reward is a better place in the queue, and you supply the documentation yourself. No money comes with it.
The capacity restriction contract (CBC) is a contract under the Netcode elektriciteit (the Dutch grid code). In return for payment, you give up part of your connection and transport capacity to help resolve anticipated congestion. The contract states at least the maximum capacity you may use, whether the restriction applies permanently or in agreed periods, the price in euros per MW, the connection's EAN code and the term (ACM, Q&A on congestion management and CBC, § 3.3). Since the code decision of 11 December 2025 there has been the broader capacity steering contract (CSC), under which the grid operator can also ask you to use capacity in the opposite direction: feeding in from your battery at times of offtake congestion.
There is no fixed price. The ACM deliberately sets no tariff because the services are offered on a market basis; the CBC is bespoke, not a standard contract. What is fixed is the financial limit per grid area, the amount a grid operator may spend on congestion management each year. As examples, the ACM cites around €18 million a year for offtake congestion at TenneT in Noord-Brabant and €419,000 a year for the Liander area of Schenkeschans (ACM, Q&A, § 3.5). The price you can negotiate depends on how long, how often and with how much notice the grid operator wants to call on your restriction. Any amount per MW in a quotation before the contract exists is the supplier's estimate.
Flex-e part d, from 100 kW of flexible capacity, required a signed offtake congestion management contract with the grid operator; a CSC, including a CBC, or a bid-obligation contract for redispatch could qualify. Congestion mitigator status alone was not enough. How to approach such a contract is covered in our guide to solving grid congestion.
When a business battery does not pay off.
What a battery costs is not in any government source. RVO commissioned research into the average purchase price to set the Flex-e lower limit, but does not publish the amount. The scheme does allow one inference, and it is ours: at 40% subsidy, the €25,000 minimum requires at least €62,500 of eligible costs for a 50 kW battery. That is a lower limit for the subsidy, not a verified battery price.
Set that against the savings in the section on grid tariffs. A battery that takes 100 kW off the peak every month on an MV connection earns at most €7,032 a year on grid charges, including the saving from lower contracted capacity.
That saving can be calculated in advance; the payback period cannot, because it depends on the quoted price of the battery and your consumption profile. We calculate that case by case. The business case rarely stacks up on peak reduction alone. It needs the sum of peak reduction, your own solar power, the subsidy and, if it can be had, a contract with the grid operator.
In these situations we usually advise against buying (for now):
- Your connection is LV up to 50 kW. There is no kWmax tariff; on the grid bill, peak reduction yields only €1.49 per kW per month through the contracted capacity.
- Your peak lasts hours, not quarter-hours. The battery runs empty before the peak is over and the quarter-hourly maximum stands.
- There is no renewable generation installation above 15 kW peak on the connection, and the battery has no automatic control linked to an electricity sub-market. Then it fits neither EIA code.
- The battery is below 50 kW and the only Flex-e measure. Then Flex-e is not an option, quite apart from the closure of the 2026 window.
- You are not in a declared offtake congestion area, or you do not have a large-consumer connection. Again no Flex-e; only EIA remains.
- You did not notify RVO of the purchase costs within three months of entering into the investment commitment. The notification is then too late, whatever the invoice date.
- The business case relies on a CBC payment that has not yet been contracted. There is no fixed price; what is not on paper does not count.
- You want to lower the contracted capacity, but your peaks are unpredictable. One overrun and Liander charges you for the higher capacity retroactively.
- The battery is flooded lead-acid, mobile or temporary. Flooded lead-acid falls outside both EIA codes (gel lead-acid does qualify under code 251118); mobile and temporary fall outside Flex-e.
We make our money from the calculation, not from the battery. Advice that ends in "do not buy yet" costs you a study and saves you an investment. So that conclusion simply appears in our reports, with the figures you can use to test it again later.
Metalis: 450 solar panels, a 1.2 MWh battery and a CBC-T contract.
Metalis, a metalworking company in Drachten, combines 450 solar panels with a 1.2 MWh battery and a capacity restriction contract (CBC-T) with Liander. An energy management system (EMS) controls the whole installation. CO2 emissions from natural gas use (scope 1) went from 67 to 0 tonnes a year. Read the Metalis case study.
Want to know whether your situation resembles Metalis or the list above? That is the question a flexibility scan answers: your quarter-hourly data, your generation, your grid level and the contract options with your grid operator, calculated using this year's tariffs and scheme texts. In the 2026 round, now closed, the scan itself fell under part a of Flex-e.
Questions about the business battery.
How much subsidy can I get for a business battery in 2026?
There are two schemes. The energy investment allowance (EIA) gives a 40% deduction from profit on a battery that meets code 251118 or 260101 of the Energielijst 2026 (the Energy List); in RVO's worked example the net tax benefit is 10.3% of the investment. Flex-e covered 40% of the cost of flexibility measures, with a minimum of €25,000 and a maximum of €300,000, for businesses with a large-consumer connection in a declared offtake congestion area; a battery as the only measure had to be at least 50 kW. The 2026 Flex-e application window closed on 15 October 2026 at 17:00. The Flex-e subsidy is deducted from the EIA base, so the two schemes together do not cover 80%. SDE++ does not cover batteries.
Does a business battery qualify for SDE++?
No. The Aanwijzingsregeling SDE++ 2026, the scheme's designation order (Staatscourant 2026, 25954), does not once use the words batterij, accu or elektriciteitsopslag (battery, accumulator, electricity storage). The renewable electricity categories are onshore wind, wind on flood defences and solar panels on buildings, on land or on water. Storage appears in the scheme only as CO2 storage and thermal storage. The window runs from 09:00 on 27 October 2026 to 17:00 on 26 November 2026, with a ceiling of €8 billion, but you cannot apply for a business battery. The schemes that do apply are EIA and Flex-e (2026 window now closed).
What is the payback period for a business battery?
No official source publishes a payback period or purchase price for business batteries; any such figure is someone's own calculation. What is certain is the revenue side, which comes from grid tariffs: on a Liander medium-voltage (MV) connection, 100 kW of peak reduction in 2026 saves 100 × €3.57 × 12 = €4,284 a year in kWmax charges, plus €2,748 a year if the contracted capacity can also come down by 100 kW (our calculation from Liander's 2026 tariff sheet). The payback period does not follow from those tariffs alone: it depends on the quoted price of the battery and on your consumption profile, such as when the peak occurs and how long it lasts. Your own solar power, subsidy and a contract with the grid operator determine whether it gets shorter. We calculate this case by case using your own quarter-hourly data, before you sign.
Can I combine Flex-e and EIA for the same battery?
Yes, but you cannot simply add them up. The 2026 EIA brochure requires the amount of an investment subsidy such as Flex-e, once finally determined, to be deducted from the purchase costs before the EIA is calculated. Our calculation for a €200,000 battery, assuming the full investment is eligible, the battery meets the conditions of both schemes and the full deduction is used at 25.8% corporate income tax: the Flex-e subsidy is €80,000, the EIA base €120,000, the deduction €48,000 and the tax benefit €12,384. Together that is €92,384, or 46.2% coverage in this example, not 80%. An operating subsidy need not be deducted from the base. EIA and MIA, EIA and ISDE, and EIA and SDE++ are mutually exclusive for the same costs.
What is the difference between a congestion mitigator and a capacity restriction contract?
A congestion mitigator (congestieverzachter) is category 1 in the ACM prioritisation framework that grid operators have applied in congestion areas since 1 January 2026: anyone who frees up grid space so that others gain access gets priority for transport requests. That earns a better place in the queue, not a payment. A capacity restriction contract (CBC) is a contract under the Netcode elektriciteit (the Dutch grid code) in which you give up part of your transport capacity in return for payment; the price in euros per MW is set in the contract and is bespoke, because the ACM does not set a fixed fee. Since December 2025 there has also been the broader capacity steering contract (CSC), under which the grid operator can ask you to feed in during offtake congestion. In the 2026 Flex-e round, now closed, part d (from 100 kW of flexible capacity) required a signed offtake congestion management contract with the grid operator; a CSC, including a CBC, or a bid-obligation contract for redispatch could qualify. Congestion mitigator status alone was not enough.
Which EIA code applies to my battery: 251118 or 260101?
Code 251118 (battery for storing renewably generated electricity) requires the battery to be connected to a renewable generation installation with a peak capacity above 15 kW on the same grid connection. Code 260101 (storage of electrical energy) has no such condition, but requires software that automatically switches the battery on and off depending on an electricity sub-market; without that software link there is no deduction. Both codes require at least 5 kW and 15 kWh and exclude flooded lead-acid. New in 2026: gel lead-acid now qualifies under 251118, and peak capacity is what counts for the generation installation. A battery with no renewable generation installation above 15 kW peak on the same connection and no automatic control linked to an electricity sub-market fits neither code.
When do I have to file the EIA notification for a battery?
Within three months of entering into the investment commitment. That is the moment when it is settled what you are buying and at what price: usually the signing of the purchase agreement, but an order given verbally or digitally also counts. The quotation, invoice and payment dates are not decisive. If the battery falls under a main contract, the date that main contract is concluded counts. For production costs, the deadline is three months after the end of the calendar quarter in which the costs were incurred. If those costs fall in the same quarter as commissioning, it is three months after commissioning. You submit the notification online through the RVO portal using eHerkenning (the Dutch business login) at assurance level 2+; paper notifications are not accepted.
Does a battery pay off on a low-voltage connection up to 50 kW?
On the grid bill, usually not. At Liander, the low-voltage (LV) category up to 50 kW contracted capacity has no kWmax tariff in 2026; there is only a kW contract tariff of €1.49 per kW per month. Peak reduction, a battery's most reliable value stream, therefore yields little there. Flex-e also required a large-consumer connection in a declared offtake congestion area and, for a battery as the only measure, at least 50 kW. What remains is more self-consumption of solar power and, with a renewable generation installation such as solar panels above 15 kW peak on the same connection, the EIA under code 251118. Whether that justifies the investment depends on your purchase and feed-in prices and on the price of the battery.
Run the numbers first, then buy.
In an initial conversation we map your connection, your peak profile and your generation, and tell you honestly whether it is worth running the numbers on a battery. No obligation, and no stake in the outcome: we do not sell batteries.
Discuss your situation →Sources
- Wet IB 2001, artikel 3.42 (versie 1 januari 2026) · EIA rate of 40% and statutory maximum per taxpayer (accessed 22 September 2026)
- RVO — Brochure EIA Energielijst 2026 (pdf) · worked example net benefit 10.3% (p. 4), codes 251118 (p. 63) and 260101 (p. 66), notification deadline (§ 2.1.2), combinations with MIA/SDE++/ISDE/investment subsidy (§ 1.3), 2026 changes (p. 77); accessed 22 September 2026
- Belastingdienst — Energie-investeringsaftrek 2026 · minimum €2,500 per asset (accessed 22 September 2026)
- RVO — Brochure Milieulijst 2026 (pdf) · MIA excluded on costs to which EIA has been applied; no stationary battery on the Milieulijst (accessed 22 September 2026)
- Rijksoverheid — Belastingplan 2027 (15 september 2026) · cabinet proposal to raise the EIA rate from 40% to 45% from 2027; status: proposal, not yet law (accessed 22 September 2026)
- Staatscourant 2026, 12853 — Wijzigingsregeling tweede openstelling Flex-e · 40% subsidy, min. €25,000 / max. €300,000, 50 kW lower limit for batteries, sub-ceilings, eligibility requirement, congestion management contract for part d, exclusions (accessed 22 September 2026)
- RVO — Flex-e: Flexibiliteitsmaatregelen · window closing 15 October 2026, 17:00 (accessed 22 September 2026)
- Staatscourant 2026, 25954 — Aanwijzingsregeling SDE++ 2026 · window 27 October to 26 November 2026 inclusive, ceiling €8 billion; batteries and electricity storage do not appear in the scheme (accessed 22 September 2026)
- Tarievencode elektriciteit 2026, artikelen 3.9 tot en met 3.11 (BWBR0052321) · division of grid costs per grid level: 25% kW contracted, 25% kW max per month and 50% kWh at medium voltage (art. 3.10); 16% kW contracted and 84% kWh at low voltage above 3x80 A (art. 3.11); 50/50 only at EHV, HV, IV and the HV+IV/MV transformer (art. 3.9) (accessed 23 September 2026)
- ACM — Ontwerpbesluit tijdgebonden transporttarieven (ACM/UIT/605184) · how the kW contracted and kWmax tariffs work, quarter-hourly metering (paragraphs 16 and 18; accessed 22 September 2026)
- Liander — Tarieven aansluiting en transport elektriciteit grootverbruik 2026 (versie 2026.1.1) · kW contract and kWmax tariffs per grid level, no transport charges for feed-in, rules for lowering contracted capacity (accessed 22 September 2026)
- ACM — Vragen en antwoorden congestiemanagement en capaciteitsbeperkingscontract (ACM/INT/457084) · definition and content of the CBC, no fixed fee, financial limit per grid area (§§ 3.1, 3.3, 3.5; accessed 22 September 2026)
- ACM — Codebesluit capaciteitssturingscontract (11 december 2025) · broader CSC contract form, including use in the opposite direction (accessed 22 September 2026)
- ACM — Codebesluit prioriteringsruimte transportverzoeken 2025 (12 december 2025) · category 1 congestion mitigators, category 2 safety, category 3 basic needs; mandatory from 1 January 2026 (accessed 22 September 2026)