Practical guide, September 2026

EHUB subsidy: funding for an energy hub scan and study

From 09:00 on 1 October 2026, companies with a large connection can apply for subsidy for research into an energy hub. A scan qualifies for €5,000 or €8,500. A study of a new hub qualifies for 70% of eligible costs, up to €42,000. The €9.6 million budget is allocated on a first-come, first-served basis; if it falls short, lots are drawn. Three rules decide whether you are on time: you apply for the scan subsidy after the scan, earlier participation can rule out a new application for the same component, and you need information from the grid operator.

What is the EHUB subsidy and who can apply?

EHUB (Onderzoek Energiehubs) is an RVO subsidy for the scan and study that precede an energy hub. Applications are open from 1 October 2026 to 1 May 2027 inclusive. The energy hub consists of at least three companies that do not belong to the same corporate group, each with a connection larger than 3x80 A. A scan qualifies for €5,000 or €8,500. A study qualifies for 70% of eligible costs for a new hub (€25,000 to €42,000) or 40% for an expansion (€25,000 to €32,000). The €9.6 million budget is allocated on a first-come, first-served basis; if it falls short, lots are drawn.

The scheme

What EHUB covers: a scan and a study

EHUB is a subsidy module of the Ministry of Climate Policy and Green Growth, run by RVO (Netherlands Enterprise Agency). The scheme has two components, which you can apply for separately or together (Staatscourant 2026, 31575, art. 4.16.2).

ComponentWhat it involvesSubsidyWhen you carry it out
ScanMaps the current collective usage profile and future collective energy demand, and explores at least three packages of measures€5,000 for the applicant plus up to four partners; €8,500 for five or more partnersBefore applying; you pre-finance the costs
Study, new hubAn organisational, technical, financial or legal design of the energy hub70% of eligible costs, minimum €25,000 and maximum €42,000After the application is approved; one-year completion period
Study, expansionThe same design, for the expansion of an existing energy hub40% of eligible costs, minimum €25,000 and maximum €32,000After the application is approved; one-year completion period

Source: Staatscourant 2026, 31575, art. 4.16.2, 4.16.3 and 4.16.6; RVO, accessed 23 September 2026.

For the scan, the scheme states a fixed amount ("De subsidie bedraagt", "the subsidy is"); on its own page RVO describes it as the maximum. If you apply for a scan and study together, the scan subsidy counts towards the study's minimum amount (art. 4.16.3, para. 2). For a study you receive a 90% advance.

Two types of cost are expressly excluded: mapping individual usage profiles, and process facilitation (art. 4.16.4, para. 3). You calculate eligible costs using the fixed hourly rate method.

Who

Who can apply, and on whose behalf

To qualify for EHUB, an energy hub must consist of at least three companies established in the Netherlands that do not belong to the same corporate group, each with a large connection (art. 4.16.2, para. 3). The Energy Act (Energiewet) defines a large connection as one with a capacity greater than 3 x 80 amperes for electricity (art. 1.1).

According to RVO, the application can be submitted in three ways:

  • by an energy hub partner with a large connection;
  • by a legal entity set up for the energy hub, such as a cooperative, private limited company (bv) or foundation. Under the scheme, such an entity can apply only for study subsidy (art. 4.16.2, para. 2); RVO mentions this route for a study into expansion;
  • by an authorised representative, such as a business park manager, hub coordinator, business association or municipality, on behalf of a partner with a large connection or of the legal entity. RVO may later ask for proof of authorisation.

Our guide to energy hubs explains what an energy hub is and how a group transport agreement (GTO) works. Whether an energy hub is the right route for your site is covered in Is an energy hub right for you?

Timing

Three rules that decide whether you are on time

The €9.6 million budget is allocated on a first-come, first-served basis (art. 4.16.5); if it falls short, RVO draws lots. Three provisions in the scheme make the difference between being ready early and being ready late.

1. For scan subsidy, the scan comes before the application. For a scan, only costs incurred before the application is submitted count (art. 4.16.4, para. 2). So if the scan has yet to be carried out, you can only apply afterwards.

2. A company can take part only once per component. RVO rejects a scan application if the applicant or an intended partner was previously involved in a scan that received subsidy under this scheme. The same applies to a study, per type of study: formation or expansion (art. 4.16.7). Anyone who took part in a scan can still take part in a study later. So decide up front which companies you will work with on the hub.

3. Two documents come from third parties. The application includes the energy hub's registration number on the initiative radar (initiatievenradar) of the Kennisplatform Energiehubs, and an overview from the grid operator showing which ring the applicant and partners are connected to; for cooperation on the transmission system, a written statement is sufficient (art. 4.16.9, parts g and h). The sources consulted give no lead time for that overview, so request it in good time.

According to RVO, decisions will be issued from 1 January 2027. You have six weeks to lodge an objection to a decision.

The application

What the application must contain

Under article 4.16.9, an application must contain at least:

  • a statement that the applicant and at least two partners have a large connection, with the EAN codes. RVO cites the connection and transport agreement (ATO) or an invoice from the metering company as proof;
  • a statement that each intended partner has signed a declaration of intent: to take an active part in the scan or study, and to use their best efforts to form or join the energy hub;
  • the registration number on the initiative radar of the Kennisplatform Energiehubs, and the grid operator's overview of which ring the partners are connected to or, for cooperation on the transmission system, a written statement;
  • for each partner, the completed Individuele energiehuishouding (individual energy management) template: how the company handles procurement, generation, storage and consumption;
  • a graph of the current collective usage profile and a description of future collective activities and energy demand;
  • for a scan: an overview of at least three packages of measures in the RVO template, with a reasoned choice of the most suitable package, or a reasoned explanation of why none of the packages is suitable;
  • for a study: a project plan setting out the objective, the measures to be investigated, the research method, the tasks and who carries them out, the schedule and the financing plan. RVO rejects an application if the quality of that plan is inadequate (art. 4.16.7).

You apply through the RVO portal using eHerkenning (the Dutch business login) level 2+. RVO has said that the project plan template will soon appear on the scheme page.

After the study

What a study must deliver

A study must be completed within one year (art. 4.16.6). In unforeseen circumstances you can request a limited extension, stating your reasons. During the study you take part in the provincial implementation programme, if your province has one (art. 4.16.8).

The final report is no formality (art. 4.16.10). If the energy hub proves promising, the report describes, among other things, the measures and any group transport agreement (GTO), with the contract terms and the limits of the group contracted transport capacity. It also describes the chosen legal form, with deed of incorporation, articles of association and arrangements for joining and leaving. And it contains a three-year business case, with costs and benefits, a settlement model and the financing of the start-up phase.

If the hub does not prove promising, the report describes the packages investigated, the reasons, and the circumstances in which it would be promising. Such an outcome can help you decide whether to invest further. Why energy hubs founder in practice is covered in Is an energy hub right for you?

In practice

What matters when preparing the application

The scheme requires, among other things, a collective usage profile, signed declarations of intent from all partners and information from the grid operator. Under the scheme, a usage profile is an overview based on quarter-hourly values over one year or, where available, several years (art. 4.16.1). That data comes from several parties, so do not wait until the application window is open to start on it.

Energyc works on collective energy projects on business parks. At Azeven-Noord in Drachten we developed a collective energy strategy for 17 companies, with cooperative governance, one joint supply contract with the energy supplier and a shared PV installation through cable pooling. At IBF Heerenveen we coordinate the area-based approach for more than 60 companies. There is a separate scheme for the flexibility of a single company: Flex-e, whose application window closed on 15 October 2026.

Frequently asked questions

Questions about the EHUB subsidy.

When can I apply for the EHUB subsidy?

From 09:00 on 1 October 2026 to 17:00 on 1 May 2027, through the RVO portal using eHerkenning (the Dutch business login) level 2+. RVO allocates the €9.6 million budget on a first-come, first-served basis and draws lots if the budget falls short. Decisions will be issued from 1 January 2027.

How much subsidy does EHUB give?

For a scan, €5,000 if the energy hub consists of the applicant and up to four partners, and €8,500 with five or more partners. For a study of a new energy hub, 70% of eligible costs, with a minimum of €25,000 and a maximum of €42,000. For a study of the expansion of an existing energy hub, 40%, with a minimum of €25,000 and a maximum of €32,000.

Does the scan have to be finished before I apply for the scan subsidy?

For the scan subsidy, yes. For a scan, only costs incurred before the application is submitted count (art. 4.16.4). So you have the scan carried out first, pre-finance the costs and then apply for the subsidy. According to RVO, a study is carried out only after the application has been approved.

Who can submit the application?

A company with a large connection that is part of the energy hub or, for a study, a legal entity set up for the energy hub, such as a cooperative, private limited company (bv) or foundation. An authorised representative can also apply on behalf of one of those parties, for example a business park manager, hub coordinator, business association or municipality.

What is the minimum number of companies in an energy hub?

At least three companies established in the Netherlands that do not belong to the same corporate group, each with a large connection: larger than 3x80 amperes for electricity, under the Energy Act (Energiewet).

Can a company take part more than once?

That depends on the component. Earlier involvement in a scan that received EHUB subsidy rules out a new scan application; for studies the rule applies per type, formation or expansion (art. 4.16.7). Anyone who took part in a subsidised scan can still take part in a study later.

Are process facilitation costs eligible?

No. The scheme expressly excludes the costs of process facilitation, as well as the costs of mapping individual usage profiles (art. 4.16.4, para. 3).

What do I need from the grid operator?

An overview provided by the grid operator showing which ring the applicant and partners are connected to; for cooperation on the transmission system, a written statement. The sources consulted give no lead time, so request it in good time.

Sources & references

Sources

Free initial assessment

Is your site ready for an EHUB application?

In an initial review we go through the partners, the connections and the required documents with you. If you are applying for scan subsidy, the scan must be carried out before you apply. The initial review is free.

Discuss your situation →