Practical guide, September 2026

Charging electric trucks when your grid connection is too small

If you cannot get a larger grid connection for now, there are two things you can start straight away. Since 1 January 2026 you have been able to apply to the RDW (the Dutch vehicle authority) for a grid congestion exemption for zero-emission zones; it costs €100 per vehicle and is valid for 2 years. Enexis, Stedin, Liander and RENDO also offer time-block transport (blokstroom): extra capacity between 00:00 and 06:00, each on its own terms. Our calculation at 147 kW charging power (3x250 A at Liander): nearly 2 trucks with 6 charging hours, 3 with 10 hours and 4 with 14 hours. We assume 525 kWh × 85% per truck (RVO, Netherlands Enterprise Agency), excluding charging losses and other consumption on the connection.

My grid connection is too small for electric trucks. What can I do now?

Ask your grid operator about time-block transport (blokstroom): extra capacity between 00:00 and 06:00, which Enexis, Stedin, Liander and RENDO each offer on their own terms. If a truck that is not zero-emission has to enter a zero-emission zone, apply to the RDW for a grid congestion exemption: €100 per vehicle, valid for 2 years. Our calculation at 147 kW charging power (3x250 A at Liander): nearly 2 trucks with 6 charging hours, 3 with 10 hours and 4 with 14 hours. We assume 525 kWh × 85% per truck (RVO), excluding charging losses and other consumption on the connection.

Zero-emission zones

The grid congestion exemption for zero-emission zones

Since 1 January 2025, municipalities have been allowed to introduce zero-emission zones for city logistics (Op weg naar ZES, the Dutch zero-emission zones programme). So far, 19 municipalities and Schiphol have such a zone, and 9 others have decided to introduce one or are looking into it. In Groningen the zone has applied since 1 April 2025, in Assen since 1 January 2025. We found no Frisian municipality in the Op weg naar ZES overview.

Access rules depend on the truck’s date of first registration (DET).

Truck (N2 and N3, over 3,500 kg)Access without exemption
New, DET from 1 January 2025zero-emission only
Euro 6 rigid truck, DET 1 January 2017 to 31 December 2019until 1 January 2028
Euro 6 rigid truck, DET 1 January 2020 to 31 December 2024until 1 January 2030
Euro 6 tractor unit, DET 1 January 2017 to 31 December 2024until 1 January 2030

Exceptions apply, until 1 January 2030 at the latest, to fairground and circus trucks, abnormal-load transport and removal vehicles, among others. Trucks with a loader crane of 35 tonne-metres or more and body codes 15, 16, 19, 23, 26, 27, 31 and SB/SF are also exempt. For the exempt body codes, the exemption ends on 1 January 2030 at the latest, or earlier when the vehicle reaches 13 years of age, counted from the DET. Source: Op weg naar ZES, Toegangsregels vrachtauto (N2 en N3), accessed 23 September 2026.

Since 1 January 2026 there has been a separate grid congestion exemption (Op weg naar ZES, 2 December 2025). The RDW aims it at companies that cannot invest in an electric vehicle because upgrading their connection is not yet possible. The exemption is valid for 2 years in all zero-emission zones. After that you can renew it ‘until your connection has been upgraded’ (Op weg naar ZES).

You apply to the RDW for the exemption per vehicle. Each application costs €100, even if refused. Processing takes up to 8 weeks, and during that time the vehicle may not enter the zone. A day exemption is possible in that period (RDW).

You must be able to show that upgrading your connection is not possible at present (RDW).

DocumentStatus
Completed Netcongestie form, available on request through the RDW contact form; one form covers up to 4 vehiclesrequired
Copy of the vehicle registration certificaterequired
Correspondence with the regional grid operator showing that an upgrade is not possible at present, or a screenshot of the business location on the capacity maprequired
Chamber of Commerce (KvK) registrationrequired
Energy bill or connection and transport agreement showing the contracted transport capacityrequired
Quarter-hourly readings (smart meter only)optional
Report from a logistics property agent, consultancy or recognised installer (Techniek Nederland) stating that the charging infrastructure cannot be expandedoptional

Source: RDW, Ontheffing bij overbelast stroomnet (netcongestie), accessed 23 September 2026.

Renewal costs €0 and gives another 2 years (RDW). You then show that an upgrade is still not possible, with correspondence with the grid operator or a report from a recognised installation company. A renewal can also take up to 8 weeks to process. Grid congestion exemptions issued earlier can be renewed free of charge 6 months before they expire; if renewed in 2026, they also apply nationwide (Op weg naar ZES).

If you have 1 or 2 electric vehicles, charging on your existing connection is ‘often possible’, according to the RDW. Ask your installer to assess whether that works for you. If charging is possible, you do not need a grid congestion exemption.

A zero-emission exemption usually does not apply in a low-emission zone (milieuzone); separate rules apply there (RDW). Op weg naar ZES warns about unofficial sites that charge fees, so apply through the RDW website.

According to agreements described by Op weg naar ZES, specific exemptions will remain after 2030, including for grid congestion. These rules have yet to be set down in the municipalities’ joint exemptions policy.

Blokstroom

Blokstroom: extra capacity between 00:00 and 06:00

Blokstroom is the time-block transport right; Liander describes it as extra capacity within fixed time blocks, on top of your existing contracted capacity. Under the grid code, this right had to be available from 1 April 2025 (Netbeheer Nederland, the Dutch grid operators’ association, 2025). The four grid operators below each list a block from 00:00 to 06:00. The difference lies in the conditions.

Grid operatorTime blockWhere and on what conditionPrice
Enexis00:00–06:00, fixedOnly if the transformer substation you are or will be connected to has capacity between 00:00 and 06:00You pay 25% of the GTV for blokstroom (6 of the 24 hours); 75% is credited
Stedin00:00–06:00First phase: consumption in Zeeland only; calculated per site, only in Stedin off-peak hours that overlap with TenneT’sNo tariff on the page consulted
Liander00:00–06:00Phase 1: consumption in Friesland and the Noordoostpolder only; large-consumer connection above 3x80 A; queue after grid checkNot checked by us
RENDO00:00–06:00, one fixed blockAs long as capacity is available in this periodNo tariff on the page consulted

GTV = contracted transport capacity. Sources: Enexis, Blokstroom; Stedin, Transportrechten; RENDO Netwerken, Flexibele oplossingen (all accessed 23 September 2026); Liander, Blokstroom (accessed 22 September 2026).

On 7 July 2026 RENDO signed its first blokstroom contract, with a transport company. That company now draws extra capacity between 00:00 and 06:00 to charge electric trucks (RENDO, news item of 7 July 2026). RENDO’s stated target group includes ‘charging hubs, energy storage systems and industrial processes’.

All four contracts run indefinitely. At Enexis and Liander the contract stays in force once the congestion is resolved, and at Stedin after grid reinforcement. At Enexis, a blokstroom application does not affect a pending application for firm transport capacity. At Stedin, you can also apply for blokstroom while you wait, without losing your place in the queue.

At Enexis, the customer cannot change the window. Enexis does reserve the right to change it ‘if the grid is at risk of overload’. Persistent overruns can lead to the transport right being suspended or terminated. At Enexis, the capacity allocated falls within the connection capacity of the current or requested connection.

At Enexis you can exchange all or part of your existing firm capacity for blokstroom; that part can then only be used at night. If there is not enough capacity, Enexis allocates what is available and puts the rest in a queue. The tariff category follows from the sum of your current GTV and the full blokstroom GTV (Enexis).

Where there is congestion, Stedin also offers an ATO ‘supplemented with a restriction with fixed time windows’. This lets Stedin offer some or all of the requested firm capacity in off-peak hours ahead of grid reinforcement.

Stedin describes Reststroom as a fully variable transport right during congestion, with no guarantee. According to the page consulted, there is currently too little visibility of available transport capacity to use this right. On 1 April 2025, Netbeheer Nederland called this variable right ‘not yet technically possible’.

RENDO’s other options include a capacity restriction contract (CBC) with fixed time windows, for example lower consumption between 16:00 and 19:00. If you are in RENDO’s queue for extra capacity and take a capacity steering contract (CSC) as a congestion mitigator, you can ‘sometimes temporarily get extra capacity after all’. The conditions for congestion mitigators and the other contract types are in our guides on the grid operator’s queue and solving grid congestion.

The calculation

How many trucks can a 3x250 A connection charge per night?

Liander classifies a 3x250 A connection as category AC4b, from over 100 up to and including 160 kVA. It gives 147 kW as the maximum demand for this category. Converting 3x250 A at 400 volts gives about 173 kVA (our conversion). We therefore use the capacity the grid operator gives or the capacity stated in your ATO.

Liander categoryConnectionMaximum demand
AC4a> 3x80 A up to 100 kVA (3x160 A)94 kW
AC4b> 100 up to 160 kVA (3x250 A)147 kW
AC5a> 160 up to 630 kVA535 kW
AC5b> 630 kVA up to 1 MVA850 kW

Source: Liander, Soorten grootverbruik elektriciteitsaansluitingen; ampere values from Liander, PvE opstellingsruimte AC4 klantaansluiting (version 1.1). Accessed 23 September 2026. Liander publishes categories up to 10 MVA; above that it is bespoke. At Enexis, 3x80 A is the largest small-consumer connection, with a maximum capacity of 55 kW.

The number of trucks per night is a simple calculation: available capacity times charging hours, divided by the energy per truck. For the energy per truck we use the worked example RVO gives for SPriLa. RVO assumes 2 trucks, each with a 525 kWh battery pack, of which 85% is used. That comes to about 446 kWh per truck per night (our calculation).

Charging windowEnergy at 147 kWTrucks per night at 446 kWh per truck
6 hours (00:00–06:00, the blokstroom window)882 kWhjust under 2 (1.98)
10 hours (e.g. 20:00–06:00)1,470 kWh3 (3,3)
14 hours (charging time in the RVO example)2,058 kWh4 (4,6)

Our calculation, not a published figure. Assumptions: 147 kW maximum demand at 3x250 A (Liander, AC4b) and 525 kWh × 85% ≈ 446 kWh per truck (RVO, SPriLa worked example). No charging losses and no other consumption on the connection during the charging window. In its example, RVO assumes 14 hours of charging time and a 50 kW depot charger. The 10- and 14-hour examples assume charging power is available for that entire window; blokstroom applies here from 00:00 to 06:00.

If a truck uses less than the assumed 446 kWh per day, more will fit. Charging losses reduce the number; we found no benchmark for these in a primary source. If your building itself consumes electricity during the charging window, that comes off the 147 kW. Our guide on peak demand and contracted capacity explains how to map that consumption.

For an initial check, Op weg naar ZES points to the Laadscantool, which shows ‘how many charge points you can connect’. The Handreiking Depotladen (depot charging guide) from the NAL Logistics working group comes in versions for fewer than 5, about 15 and about 50 vehicles. Public charging is still limited for trucks; RVO maintains a charging map for heavy transport (Op weg naar ZES).

If you want more capacity than the connection can technically handle, you need a larger connection, according to Liander. In congestion areas, the wait for grid capacity can reach 10 years (Netbeheer Nederland). Our guide on applying for or upgrading a connection explains what that process involves.

Charging next door

Sharing capacity: group contract or cable pooling

On business parks with high charging demand and congestion, ‘it can be worth teaming up with your neighbours’, writes Op weg naar ZES. Its example is a collective charging hub at another company with enough space and capacity. The table below sets out two arrangements side by side. With a group transport agreement (GTO), companies share transport capacity; with cable pooling, they share one connection.

GTO at StedinGTO at RENDOCable pooling
ContractOne shared contract; the group is jointly responsible for not exceeding the limitOne agreement on a joint maximum transport capacity; each participant keeps its own connection and its own contractNew joint connection and transport agreement; the parties arrange everything behind the connection point themselves (RVO)
Who can take partLarge-consumer connection (> 3x80 A), same connection type (LV, MV or HV), behind the same distribution substation and currently only on the same medium-voltage ring; for a connection above 1,750 kVA: the same busbar at the substationSame distribution substation (transportverdeelstation) and same voltage category (LV/MV)Connection of 100 kVA or more; up to 4 installations (WOZ properties) located close together (ACM, the Dutch regulator)
Other pointsEnergy management system required; optional transition period of up to 3 years, and if it does not work, the individual transport rights are reinstatedGroup CBC in development; applying is ‘not possible for now’Notify the ACM; ‘parties cannot derive any rights from the notification’

Sources: Stedin (GTO voor energiehubs), RENDO (Flexibele oplossingen), ACM (Cable pooling melden, last modified 27 February 2026) and RVO (Deel uw aansluiting), accessed 23 September 2026. We did not check Liander’s and Enexis’s GTO conditions for this guide.

In congestion areas, a joint cable pooling application must not increase the existing transport capacity, because that would worsen congestion (RVO). If there is no connection yet for cable pooling, the new application goes into the queue (RVO). Our reading: for overnight charging, sharing mainly pays off if your neighbour has contracted capacity to spare at night.

With a GTO, Stedin sets a joint grid limit based on historical profiles and then enforces that group limit. A Netburenscan (grid neighbours scan) shows which companies are on the same part of the grid. Among the benefits Stedin lists: ‘Your neighbour’s solar panels can power your charging hub.’ Our guides on the energy hub and choosing an energy hub explain how a group works.

If you share a charging hub, check the SPriLa rules. The charging infrastructure must remain private, and the scheme is ‘not intended for businesses wanting to operate charging infrastructure’ (RVO). SPriLa is, however, open to ‘businesses with customers with electric vehicles’. We have not looked into whether paid charging at a neighbour’s site counts as operating; put that question to RVO first.

Battery at the depot

A battery at the depot: SPriLa pays per kWh

Where there is congestion, Op weg naar ZES points to smart charging and a battery system, referring to the NKL guide ‘Mitigerende maatregelen’. A battery charges when there is room on your connection and discharges when the trucks charge. In itself it does not change your contracted capacity. We work out what a battery costs and earns in our guide on the business battery.

SPriLa pays €60 per kWh (large company) or €85 per kWh (SME) for a stationary battery, up to a maximum of 1,000 kWh (RVO). For a battery combined with new charging infrastructure, the subsidy is at least €25,000 (RVO). The battery must demonstrably deliver 70% of the discharged kWh to charging stations and remain in your ownership for 24 months. The C-rate is at most 0.5; that requirement does not apply to an integrated battery (RVO).

The 2026 annual budget is €45 million for stationary batteries up to 1,000 kWh per charging bay and €68.5 million for private charge points (RVO). SPriLa is not for government bodies or operators of charging infrastructure (RVO).

The SPriLa application window closes on 18 December 2026 at 12:00. For subsidies above €25,000, you apply first and only then place the order. RVO then asks for a capacity calculation showing that the charging infrastructure can be operational within 24 months; see our SPriLa guide.

The 2026 Flex-e application window closed on 15 October 2026 at 17:00. If you were counting on Flex-e for the battery, note that part d (from 100 kW) requires a congestion management contract, and a time-block contract such as blokstroom does not count (Staatscourant, the Dutch Government Gazette, 2026, 12853).

HGV charge

Dutch HGV charge: what a zero-emission truck saves per kilometre

Since 1 July 2026, truck owners in the Netherlands have paid per kilometre driven (Rijksoverheid, the Dutch government). The Dutch HGV charge (vrachtwagenheffing) applies on motorways and some provincial and municipal roads, to vehicles in categories N2 and N3. The amount per kilometre depends on technically permissible maximum laden mass, Euro emission class and CO2 emission class. ‘The cleaner and lighter the vehicle, the lower the amount per kilometre’ (vrachtwagenheffing.nl).

Technically permissible maximum laden massEuro 6, CO2 class 1Zero-emission (CO2 class 5)
> 32,000 kg€ 0,156€ 0,030
18,000 to 32,000 kg inclusive€ 0,141€ 0,028
12,000 to under 18,000 kg€ 0,125€ 0,027
> 3,500 to under 12,000 kg€ 0,088€ 0,019

Rate per kilometre from 1 September 2026 to 1 January 2027, with the temporary 22.3% discount. In the heaviest class, the statutory rate in force until 1 September was €0.201 (Euro 6, CO2 class 1) and €0.038 (zero-emission). Source: vrachtwagenheffing.nl, Dit gaat u betalen, accessed 23 September 2026.

A policy decree (goedkeurend beleidsbesluit) temporarily lowers all tariff components by 22.3%, from 1 September to 31 December 2026 inclusive (Staatscourant 2026, 18058). According to that decree, the average rate falls from €0.191 to €0.148 per kilometre. The reduction ‘has no consequences for the level of the terugsluis’ (revenue recycling) or for the subsidies for electric trucks and charging infrastructure. The 2027 rates will follow in October 2026 (vrachtwagenheffing.nl).

For zero-emission trucks in CO2 emission class 5, the external-cost charge for CO2 is ‘already €0.00’ (Staatscourant 2026, 18058). Our calculation from the table: in the heaviest class, a zero-emission truck pays about 81% less per kilometre than a Euro 6 truck (CO2 class 1). That is (€0.201 − €0.038) divided by €0.201, at the statutory rate. Assuming 100,000 tolled kilometres a year, that saves €16,300 a year; proportionally less during the discount.

A large part of the revenue goes to subsidies for making road transport cleaner and more innovative (Rijksoverheid). For 2026 there is more than €253 million, including for electric or hydrogen trucks and charge points. The Meerjarenprogramma Terugsluis (2024) budgets €1,672 million for 2026 to 2030 inclusive, of which €481 million for SPriLa. The scheme for the truck itself is AanZET; its second round of 2026 opened on 29 September and was oversubscribed on 1 October. See our AanZET guide.

Our reading: once a grid congestion exemption has been granted, a truck that is not zero-emission may enter the zones. The difference in charge per kilometre remains. So when you weigh keeping your current trucks on the road against electrifying, the charge still counts, even if the zone puts you under no time pressure.

Approach

Five steps while you wait for the upgrade

In 2025, about 5% of transport requests could be granted (Netbeheer Nederland, Stand van de Uitvoering 2025). You can take the steps below in the meantime.

1. Find your contracted transport capacity. It is in your connection and transport agreement (ATO). Use it to work out the number of trucks per night: capacity times charging hours, divided by the energy per truck.

2. Ask your grid operator about blokstroom. At Enexis, the application does not affect a pending application for firm capacity; at Stedin you keep your place in the queue. Ask Liander and RENDO how this works there.

3. Keep your application for firm capacity live. Priority in the queue is determined by the ACM categories of congestion mitigators, safety and basic needs. We did not find goods transport in Netbeheer Nederland’s list of safety and basic needs. Congestion mitigators do not automatically get capacity either (Netbeheer Nederland, Stand van de Uitvoering 2025).

4. Apply for the exemption for trucks that need to enter the zone. Allow up to 8 weeks for processing, during which the vehicle may not enter the zone. A day exemption is possible in that period (RDW).

5. Check the subsidy windows against your schedule. The second AanZET round of 2026 opened on 29 September and was oversubscribed on 1 October; the SPriLa application window closes on 18 December 2026 at 12:00. For SPriLa subsidies above €25,000, you apply first and only then place the order.

Raben Group got the connection for a 400 kW DC charging hub for logistics within 6 months instead of 5+ years. The hub has been operational since Q4 2024, for 8 electric trucks. For NVO Transport, a cooperative of 54 transport companies, we developed a phase-in strategy for electric transport. Our page on the e-mobility transition explains how we approach such projects.

Frequently asked questions

Questions about electric trucks and grid capacity.

Can I get a zero-emission zone exemption if my grid connection is too small?

Yes. A grid congestion exemption has been available since 1 January 2026. You apply to the RDW (the Dutch vehicle authority) for each vehicle. You must show that upgrading your connection is not possible at present, using correspondence with your grid operator or a screenshot of the capacity map. An application costs €100, even if refused, and the exemption is valid for 2 years in all zero-emission zones. Processing takes up to 8 weeks. During that time the vehicle may not enter the zone, although a day exemption is possible.

What is blokstroom (time-block transport) and which grid operators offer it?

Blokstroom is the time-block transport right; Liander describes it as extra capacity within fixed time blocks, on top of the existing contracted capacity. Enexis, Stedin, Liander and RENDO offer it between 00:00 and 06:00, each on its own terms. In the first phase Stedin offers it only for consumption in Zeeland, and Liander, in its phase 1, only for consumption in Friesland and the Noordoostpolder. Enexis offers it only if the transformer substation has capacity between 00:00 and 06:00; RENDO for as long as capacity is available in that period.

What does blokstroom cost at Enexis, Liander, Stedin or RENDO?

Enexis publishes its price structure: you pay for 6 of the 24 hours, i.e. 25% of the contracted transport capacity for blokstroom, and 75% is credited. Enexis bases the tariff category on the sum of your current contracted capacity and the full blokstroom capacity. We found no tariff on the Stedin and RENDO pages we consulted, and we did not check Liander’s tariff. So ask your own grid operator for the price.

How many electric trucks can I charge on a 3x250 A connection?

For 3x250 A (category AC4b), Liander gives a maximum demand of 147 kW. By our calculation, that lets you charge just under 2 heavy trucks a night with 6 charging hours, 3 with 10 hours and 4 with 14 hours. We assume 446 kWh per truck: 85% of a 525 kWh battery, as in a worked example from RVO (Netherlands Enterprise Agency). Charging losses and other consumption on the connection are not included and would reduce that number.

Will I lose my place in the queue if I apply for blokstroom?

Not at Enexis or Stedin, according to their own product information. Enexis states that a blokstroom application does not affect a pending application for firm transport capacity. Stedin states that you can also apply for blokstroom while you wait, without losing your place. Our sources do not cover this for Liander and RENDO, so ask them directly.

How much is the Dutch HGV charge for an electric truck?

Since 1 July 2026, owners of trucks (N2 and N3) have paid this charge (vrachtwagenheffing) per kilometre on motorways and some provincial and municipal roads. From 1 September 2026 to 1 January 2027, a zero-emission truck above 32,000 kg pays €0.030 per kilometre and a Euro 6 truck in CO2 class 1 pays €0.156. That includes a temporary 22.3% discount; the 2027 rates will be announced in October 2026. Our calculation at the statutory rate: in that class, a zero-emission truck pays about 81% less than a Euro 6 truck in CO2 class 1 (€0.038 against €0.201).

Can I charge my electric trucks on my neighbour’s connection?

Under certain conditions, through cable pooling: one connection of 100 kVA or more for up to 4 installations (WOZ properties) located close together (ACM, the Dutch regulator). In a congestion area, the joint application must not increase the existing transport capacity, according to RVO. Another route is a group transport agreement (GTO), which Stedin and RENDO describe differently: at Stedin one shared contract, at RENDO each party with its own contract. Stedin and RENDO require, among other things, the same distribution substation and the same voltage category; we have not checked the conditions at Liander and Enexis.

What subsidy is available for charge points and a battery at the depot?

Businesses can apply for SPriLa, subject to conditions, for private charge points and a stationary battery on their own premises. Trucks are explicitly covered; government bodies are excluded (RVO). The application window closes on 18 December 2026 at 12:00; the 2026 budget is €68.5 million for private charge points and €45 million for batteries. For a battery, the subsidy is €60 per kWh (large company) or €85 per kWh (SME), up to a maximum of 1,000 kWh. The scheme for the truck itself is AanZET; its second round of 2026 opened on 29 September and was oversubscribed on 1 October.

Free initial assessment

Want to know what fits on your connection at night?

An initial assessment is free. You send us your connection and transport agreement and your trip profiles, and we calculate how many trucks will fit at night. We then discuss which route you can put to your grid operator.

Discuss your situation →
Sources & references

Sources