Decision guide — September 2026

Is an energy hub right for your business park? The drawbacks, and when it does fit

An energy hub may suit your site if companies on the same part of the grid want to work together for years and can monitor their group capacity. According to an evaluation commissioned by RVO (Netherlands Enterprise Agency), by 2025 hubs had got off the ground “almost nowhere in our country”. From 1 January 2027, however, a group that meets the grid code's conditions has a right to a group transport agreement (Dutch Government Gazette, Stcrt. 2025, 43262). From 1 October 2026 you can apply for a subsidy for a scan or study through RVO's new EHUB scheme.

Is an energy hub right for our business park, and what are the drawbacks?

An energy hub can work if the participants are on the same part of the grid and want to work together over the long term (Netcode elektriciteit; Stedin). The drawbacks are real: an evaluation commissioned by RVO cites, among other things, liability that deters business owners and prolonged uncertainty that makes them drop out. Under pilot contracts, all participants can be held liable for all of the damage, sometimes with no cap (report commissioned by the climate ministry KGG, 2025). From 1 January 2027, a group that meets the grid code's conditions has a right to a group transport agreement (Stcrt. 2025, 43262).

Why hubs run aground

What the RVO-commissioned evaluation found

Commissioned by RVO, Arjen Zuijderduijn and Jolly Kerkstra studied how the first energy hubs worked in practice. Between May and August 2025 they spoke to 7 business parks, to TenneT, Alliander, Enexis and Stedin, to two provinces and to two development agencies. Their main conclusion: despite good intentions, “almost nowhere in our country had anyone yet succeeded in actually getting an energy hub off the ground”. According to energiehubs.nl, the report was published on 9 October 2025.

The report identifies six bottlenecks. For each one, the table shows what the researchers found, and what has changed since or what we recommend. That last part is our reading, not a conclusion of the report.

BottleneckWhat the report saysCurrent status and our reading
1. Legal and organisationalIn 2025 the GTO was not yet established in the grid code. Collective contracts “often have unclear or disproportionate liability obligations, which deters business owners”. This makes risks within the hub hard to insure.The GTO is set out in the code decision of 11 December 2025 (Stcrt. 2025, 43262). Articles I to III entered into force on the day after publication of the Staatscourant of 19 December 2025. Our reading: work out the liability position beforehand; see the next section.
2. Bureaucracy and delaySlow procedures at grid operators and public authorities lead to “loss of momentum and trust”. Subsidy funds are fragmented across municipalities, provinces and national government.Our reading: agree beforehand who leads the process, and what length of delay triggers a fresh decision by the group. What the municipality can do is covered in our guide on grid congestion and municipalities.
3. Little standardisation“Each grid operator has its own approach.” Information on grid capacity and procedures is hard to follow.Our reading: read your own grid operator's conditions. They still differ between operators; see the section on the grid code.
4. Cooperation and trustInterests diverge and are sometimes opposed. “Prolonged uncertainty leads to business owners dropping out.” The report advises starting with small-scale clusters and expanding step by step.Our reading: start with a few companies whose profiles complement each other, and expand only once that group is up and running.
5. Grid congestion and grid topologyComplex grid structures (“who are your grid neighbours, multiple loops and rings on one business park”) hinder sharing in front of the meter. Congestion is usually what prompts an all-electric hub; if the congestion disappears, the urgency risks disappearing too.Our reading: first have someone establish who your grid neighbours are. At Stedin, the Netburen tool in Mijn Stedin Zakelijk shows who is behind the same substation.
6. Inflated expectationsGovernment targets “are seen in the field as unrealistic”. “(Commercial) advisors and consultancies sometimes ‘promise’ business owners energy hubs that they cannot deliver in practice.”Our reading: ask your advisor, including us, under what conditions the hub will not go ahead.

Source: Zuijderduijn and Kerkstra, Geleerde lessen uit de praktijk van de eerste energiehubs (commissioned by RVO, 2025), conclusions 1–6. Status of the grid code: Stcrt. 2025, 43262.

TPN-West in Nijmegen shows how complex a site can be: around 100 hectares with around 450 companies. In the first year, one hub for the whole site proved “a far too complex undertaking”, with two substations and post-war underground infrastructure. Even in the smaller Binnenhaven sub-area, the businesses were on five medium-voltage feeders behind two transformers (RVO evaluation, part 3).

After the TenneT congestion in Flevoland, Gelderland and Utrecht in early 2024, the hub was put on hold, with seven companies ready to go. Alliander put TPN-West back on the list of sites for rollout in early July 2025. During the year and a half of delay, a corporate participant with flexibility in its processes dropped out after a change of course.

Powerhub Overbetuwe at De Aam in Elst, around 80 hectares with around 150 companies, needed €3.6 million. The businesses were to provide half; the other half eventually came from the province of Gelderland. A subsidy for a battery in front of the meter ran into state aid rules, after which “nearly all the civil servants changed jobs” and the process had to start again. The initiators pulled the plug (RVO evaluation, part 3).

A regional Beuningen-Nijmegen-Wijchen hub with 80 MW of wind and solar also failed to go ahead in the form envisaged. The feasibility study was positive, but for one small municipality it was a “no-go” (RVO evaluation, part 3).

The report recommends agreeing in advance “what to do if a party drops out”, and ensuring predictable cash flows, for example with shared storage. Our reading of these cases: every month of delay is a month in which a participant can drop out. A small group that can decide quickly runs that risk for less time than a plan for the whole site.

Liability

Joint and several liability: what the pilot contracts provide

The Ministry of Climate Policy and Green Growth (KGG) had consultancy AT Osborne map out liability in energy hubs. The report of 25 August 2025, published by RVO, describes the pilot contracts that pre-date the final code decision. Under them, all participants can be held liable for all of the damage, “even if the participant did not make the error itself”. “Grid operators wish to hold on to this”, and according to the report this leads to “cold feet”, especially with unlimited liability.

The level of liability “currently varies widely between grid operators in the pilot phase”. Sometimes there is no cap. Where there is a ceiling, it is for example a maximum of €2.5 million per event and €5 million per contract year, “set pragmatically” without an underlying risk analysis. Direct material damage is always recoverable; indirect damage is “not yet routinely” excluded (KGG report, sections 2.4.2-2.4.3).

“The chance of the group capacity being exceeded is small,” the same report states, and grid operators also consider the likelihood of damage “very small”. However, there is no quantitative risk analysis. The report does give a qualitative estimate of possible types of damage:

Type of damageOrder of magnitude according to the report
Burnt-out cableThousands to a few tens of thousands of euros
Fire at an electricity substation“Usually more than a hundred thousand euros”
Outage of a grid levelThousands to a few tens of thousands of euros in outage compensation
Incorrect load forecast sent to TenneT“A few thousand euros”

Source: Rapport Aansprakelijkheid bij energiehubs. Handelingsperspectief voor energiehubs, AT Osborne for the Ministry of KGG, 25 August 2025, pp. 2–3. The report describes pilot contracts, not the final GTO terms.

The Kennisplatform Energiehubs (energy hubs knowledge platform) carries a Q&A on liability in GTOs, from AT Osborne “in consultation with Netbeheer Nederland” (5 August 2026). According to that Q&A, the group's authorised representative and all participants are “jointly and severally liable” for damage suffered by the grid operator (art. 6:10 in conjunction with 6:102 of the Dutch Civil Code). Whoever pays can seek a contribution from the other participants internally. According to the platform itself, the Q&A confers no rights.

According to the same Q&A, the approach may still differ between grid operators, and they are working on uniform provisions. We have not seen the final contract texts. Request them before you sign. Record internally how you will share any damage and what happens if a participant drops out; RVO's EHUB study lists agreements on liability as one of its components.

Grid code and GTO

What the grid code requires of a group, and what changes from 2027

The ACM (the Dutch regulator) set out the group transport agreement in a code decision of 11 December 2025, published in the Staatscourant (Dutch Government Gazette) of 19 December 2025 (no. 43262). Until 1 January 2027, a group can only enter into a GTO “if the grid operator offers that option”. From that date this wording lapses, and a group that meets the conditions is “entitled” to enter into a GTO (art. IV and V). The national government plans for the GTO to be “available from Q1 2027” (Voortgangsrapportage LAN, the national grid congestion programme's progress report, spring 2026).

Until that date, the GTO is “not yet an obligation for the grid operator”; grid operators were given a one-year implementation period. The ACM does require them to publish their policy for entering into GTOs in advance, to prevent arbitrariness (paras 12 and 206). We read the product pages of Liander, Enexis and Stedin; we did not check that policy separately. The basics of how a GTO works are explained in our guide to energy hubs and the GTO.

TopicWhat the grid code requires (Stcrt. 2025, 43262)What grid operators and RVO add
Number of participants“A group of two or more connected parties.” The grid code sets no maximum number of participants or maximum capacity (art. 7.1e(1)).The EHUB subsidy requires at least 3 unrelated companies with a connection above 3x80 A (RVO).
Who signsAll participants jointly appoint “an authorised representative within the meaning of Article 3:60 of the Civil Code”, who enters into the GTO. The grid code requires no specific legal form. Each participant keeps its own connection agreement.Enexis: a legal entity that manages the transport capacity and makes the arrangements with Enexis. Stedin: a joint authorised representative who manages the contract.
Metering and controlEach connection has a telemetry-enabled large-consumer metering installation, sized to the connection capacity. The telemetry must be in place when the GTO is entered into; the sizing may be adjusted no later than 6 months afterwards (art. 7.1e and 7.1f).Stedin lists an energy management system for real-time coordination as a requirement. At Enexis, participants arrange an energy management system themselves “in most cases”.
Connection categoriesBelow 110 kV, only A.3 to A.7: A.3-A.5 together, A.6 with A.6 and A.7 with A.7. If the grid operator offers it, also A.3-A.5 with A.6 connections that only feed in, and A.6 with A.7.Liander lists AC4 and AC5 together, AC6 with AC6 and AC7 with AC7. Liander is still investigating “other combinations”.
Position on the gridBelow 110 kV, in normal operation the connections are on one medium-voltage busbar or on galvanically connected MV busbars. For A.3-A.5 and A.6 connections that feed in, MV rings or MV/LV substations, or a combination, are also allowed. At 110 kV and above, only A.7, at the same substation.Liander: all participants at the same electricity substation. Stedin: “grid neighbours” behind the same distribution substation, with the same type of connection (low, medium or high voltage).
Group capacityParticipants surrender their individual contracted transport capacity (GTV) “in exchange for the group GTV” (art. 7.1e(5)). The grid operator determines this with the authorised representative, based on factors including annual profiles of the past 24 months and the degree of coincidence within the group.Liander: “Even with 0 contracted capacity (GTV) you can take part”, provided at least one customer in the group has capacity. “A group contract is not dependent on the queue.”
Leaving the groupOn entering into the agreement, the group makes a one-off choice on whether it wants a transition period of up to three years; a departing participant can then fall back on its original GTV. The period may be shortened but not extended. After that period, a departing participant takes a share of the group capacity only if the group agreed this in advance. The grid operator must then have assessed that division (art. 7.1e(7)-(9)).Liander: leaving “up to 3 years after the energy hub was set up” while keeping the original GTV, thereafter according to the allocation key in the agreement. Stedin: “maximum 3 years (optional)”.
Monitoring and sanctionsBefore the start and at every change, the grid operator satisfies itself that the group can guarantee the group GTV will not be exceeded. After two or more breaches it can suspend the group's transport right; if this recurs after the suspension is lifted, the right can lapse (art. 7.1g and 7.1h).Grid operators had to publish assessment protocols by 1 July 2026. We have not checked whether and where this was done.

Sources: Staatscourant 2025, 43262, art. 7.1e to 7.1h; GTO product pages of Liander, Enexis and Stedin, accessed 23 September 2026. We could not confirm whether AC3 connections can take part at Liander.

A grid operator may refuse if reliability, safety or efficient grid management is at stake. The four assessment criteria are voltage management, the load capacity of grid elements, any direct grid investment triggered, and power flows in that part of the grid (art. 7.1e). A refusal must be in writing, with “sound” reasons and the underlying information. The group may first remedy shortcomings in guaranteeing the group GTV before it is rejected (art. 7.1g).

Two provisions affect day-to-day practice. A group may exceed the group GTV for offtake if feed-in is taking place within the group at that same moment (para. 10). If a participant receives its own transport offer while taking part, it chooses: bring it into the group or leave with that connection (art. 7.1e(6)).

A GTO group also falls under the congestion management rules and appoints one or more Congestion Service Providers (CSPs) for this (amendment to art. 9.1). We could not find how many GTOs have been signed so far. From 2027, grid operators report this to the ACM annually before 31 March (art. 7.1i).

Business case

Costs and returns: what the rules settle, and what they don't

A GTO can pay off in two ways: headroom within the group capacity, and a transport tariff calculated on the group's net balance. The tariff components kWcontract and kWmax(gewogen) are calculated jointly and net for the group, per imbalance settlement period of 15 minutes (art. 3.7.18 Tarievencode, the Dutch tariff code). If one participant is drawing power while another feeds in, the net balance for that quarter-hour counts for those two tariff components. The kWh tariff remains based on the total of the individual connections.

The ACM chose this net calculation “to encourage local coordination” (para. 11). The grid operators proposed a correction factor of 1.21 to prevent “undesirable and improper tariff advantage”. The ACM did not adopt it. In the event of “disproportionate tariff advantages”, the ACM leaves room for a later tariff solution (paras 163 and 171–178).

Groups containing A.3 connections together with A.4 and/or A.5 pay an additional monthly component (art. 3.7.19 Tarievencode). This is 1/12 of the increase under art. 3.7.10(a), multiplied by the sum of the kWmax values of all A.3 connections in the group. The ACM asks grid operators to evaluate the GTO, including the tariffs, no later than two years after entry into force. In designing the tariffs, “no data from ongoing pilots with groups was used” (paras 176 and 180).

Our reading: do not treat a tariff advantage as guaranteed for the whole term of the cooperation. The obligations and tasks the group takes on, by contrast, are fixed:

Obligation or taskWho requires it
Telemetry-enabled large-consumer metering installation per connection, sized to the connection capacityGrid code, art. 7.1e(1) (Stcrt. 2025, 43262)
Energy management systemStedin (requirement); Enexis (“in most cases”)
Technical provision that enforces a capacity restriction per connection, at your own expenseGrid code, art. 7.1f(2), if the grid operator imposes such a restriction
Installation agreement for controllable installations, such as a battery or heat pump, and agreements on dividing the contracted capacityRVO, Uw energiehub juridisch regelen
Internal settlement of the group invoice for transportLiander invoices individually (connection service and kWh) and per group (transport service): “Whoever uses the capacity pays for it.”
Congestion management: the group appoints one or more CSPsGrid code, amendment to art. 9.1

We found no amount from an official source for any of these items (as at 23 September 2026).

Nor did we find an official benchmark for savings on the transport tariff or for avoided grid upgrades. If someone does quote you a percentage or amount, ask what it is based on.

One real-world figure appears in the evaluation for RVO: Powerhub Overbetuwe, with a battery, wind and solar and collective charge points, needed €3.6 million. That is one case, not a benchmark, and the project stopped anyway. For the group GTV, the grid operator looks at factors including annual profiles of the past 24 months. Those same profiles are the starting point for modelling your own group, for example in a flexibility scan.

EHUB subsidy

New EHUB scheme: subsidy for scan and study from 1 October 2026

On 1 October 2026 at 09:00, RVO opened the Onderzoek Energiehubs (EHUB) scheme for research into energy hubs. You can apply until 17:00 on 1 May 2027, and the total budget is €9,600,000. RVO processes applications in order of receipt; if the budget is insufficient, lots are drawn. So submit a complete application as early as possible.

ComponentWhat it coversSubsidy
ScanNew hubs only. According to RVO, carried out in advance and pre-financed.Up to €5,000 with up to 5 companies; up to €8,500 with 6 or more
Study, new hubCooperation, technical design, agreements on participation, withdrawal, liability and costs70%, minimum €25,000, maximum €42,000
Study, expanding an existing hubThe same topics, for a hub that already exists40%, minimum €25,000, maximum €32,000

Source: RVO, Onderzoek Energiehubs (EHUB), checked by RVO on 17 September 2026. If you apply for a scan and a study in one application, the scan subsidy counts towards the study's minimum amount (Stcrt. 2026, 31575, art. 4.16.3(2)). RVO pays an advance of 90%.

At least 3 companies with a connection above 3x80 A must take part, and they must not be related to each other. Here, related means parent and subsidiary, sister companies or a shared shareholder. Other participants need not have a large connection. The initiative registers with the Initiatievenradar of the Kennisplatform Energiehubs, and takes part in the provincial implementation programme if there is one.

EHUB does not pay for process support. Costs for this during the scan or study are excluded, as are the costs of gaining insight into your own energy use (RVO, EHUB). Bear this in mind when you draw up a budget.

The government set aside €166 million for the Stimuleringsprogramma Energiehubs (energy hubs stimulation programme) for the period 2024–2030 (RVO). Of this, 85% goes to “development capacity” in the regions and 15% to developing and sharing knowledge at national level. RVO counts “almost 400 initiatives” and names a target of 500 active energy hubs in 2030. “Many energy hubs are still in the exploratory or planning phase,” says RVO.

Our guide to the EHUB subsidy sets out what EHUB requires, which costs count and in what order to apply.

Noord-Holland and Limburg have their own energy hub schemes. In its second phase for 2026, Noord-Holland offers €30,000 to collectives in category A, and 75% up to €80,000 in category B. This subsidy is for research, administration and organisation: “The assets themselves are not eligible.” The subsidy ceiling is €950,000.

Limburg offers up to €40,000 in the feasibility phase and up to €120,000 in the design phase, and awards no subsidies below €25,000 (CVDR761626). Prior consultation is mandatory and the de minimis rules apply. We found no energy hub scheme for Friesland.

Flex-e applicants were organisations with a connection above 3x80 A and a contract with a metering company. Each application covered one of the three parts. RVO's main page says nothing about collective applications. We discuss the scheme itself in the Flex-e guide.

Legal form

Cooperative, BV or just an authorised representative?

The grid code requires no legal form for the GTO itself. All participants jointly appoint one authorised representative within the meaning of Article 3:60 of the Dutch Civil Code (BW), who enters into the GTO on their behalf (Stcrt. 2025, 43262, art. 7.1e). Enexis does ask participants for a legal entity that manages the transport capacity and makes the arrangements with Enexis. Stedin speaks of a joint authorised representative who manages the contract.

According to RVO, you do need a legal form to properly record the cooperation with all participants. “That way, as an energy hub, you can pay money, receive money and enter into contracts.” “Most energy hubs choose a cooperative, a BV or a combination of both.” RVO outlines this sequence:

  1. a letter of intent, which the municipality or business park manager can also sign;
  2. a legal form, with articles of association in a deed of incorporation;
  3. a members' agreement;
  4. an installation agreement for controllable installations;
  5. agreements on dividing the contracted capacity;
  6. then the contract with the grid operator.

Model agreements are on the Invest-NL website, in two sets: one for a Groeps-CBC (group capacity restriction contract) and one for a Groeps-TO (group transport agreement) (RVO, Uw energiehub juridisch regelen).

Our reading: if the group only shares transport capacity, an authorised representative is enough to satisfy the grid code, although Enexis asks for a legal entity. If the hub itself invests in, say, a battery or generation, you need a party that can enter into contracts and manage money. We have not checked the tax and legal differences between a cooperative and a BV against an official source for this guide. Have a civil-law notary or tax advisor assess them.

The Energy Act (Energiewet, Stb. 2025, 12) provides for the energy community: a legal entity that carries out activities on the energy market for the benefit of its members, partners or shareholders. The main purpose is environmental, economic or social benefit, not making a profit (art. 1.1). The articles of association, or for a partnership the agreement, must specify among other things who has effective control (art. 2.4(1)). These must be members that are natural persons, micro or small enterprises, municipalities, water boards, provinces or joint public bodies.

Our reading: a hub run by medium-sized and large companies is therefore often not an energy community. That is no obstacle to a GTO. It can matter for subsidy, though: in Limburg, an application by an energy community can receive up to 100% of eligible costs (CVDR761626). A collective may also apply there without legal personality: at least three companies and/or civil society organisations with a letter of intent.

According to the text in the Staatsblad (the Dutch official journal of laws), article 2.30 gives active customers, and connected parties within an energy community, a right to share energy. Conditions include an agreement with a supplier offering energy sharing, and sharing per imbalance settlement period. We have not established whether article 2.30 was already in force as of September 2026.

Deciding

Promising or not: a checklist, and the alternatives

This checklist is our own, derived from the sources on this page, and is not an official assessment framework. If your site mainly matches the middle column, an initial assessment is worthwhile. If you more often land in the right-hand column, look at the alternatives further down first.

QuestionMore promising ifLook at an alternative first if
Where do the participants sit on the grid?Within the grid-location requirements of the grid code and your grid operator. At Liander that means the same electricity substation, at Stedin the same distribution substation.The participants are spread across several loops, rings or substations. At TPN-West, even within one sub-area they were on five medium-voltage feeders behind two transformers.
How big is the group?A small cluster that can expand step by step, as the evaluation for RVO recommends.The plan is one hub for the whole site in one go. At TPN-West, for around 450 companies, that proved “a far too complex undertaking”.
Is there contracted capacity in the group?At Liander: at least one participant has capacity. Others can then take part “even with 0 contracted capacity”.At Liander: no one in the group has contracted capacity.
Do the profiles complement each other?Peaks fall in different quarter-hours, or offtake coincides with feed-in within the group. The grid operator takes the degree of coincidence into account for the group GTV (art. 7.1e(5)).Our reading: all participants peak in the same quarter-hours and no one is feeding in at that point. Sharing then creates little headroom.
Can the group meter and monitor?Telemetry per connection and an energy management system can be organised, and someone monitors the group GTV.No one takes on the monitoring. After two or more breaches, the grid operator can suspend the group's transport right (art. 7.1h).
Will the participants stay long enough?“A group of like-minded business owners who have confidence in long-term cooperation” (Stedin).One or more participants expect to relocate or change course within a few years. At TPN-West, a corporate participant dropped out during the delay.
Do the participants accept the liability risk?Yes, and the group records internally how damage is divided and what happens if a party drops out.A participant does not want to bear the risk of another participant's error. Under the pilot contracts, all participants can be held liable for all of the damage.
Why do you want a hub?Our reading: there is a reason that still holds if congestion eases.Your only reason is congestion. If the congestion disappears, according to the evaluation for RVO, the urgency risks disappearing too.
Does the EHUB subsidy fit?At least 3 unrelated companies with a connection above 3x80 A take part.Fewer than 3 such companies take part. In that case you do not meet this EHUB condition. A GTO is still possible with two or more connected parties.

Our own analysis. Sources: Staatscourant 2025, 43262; Liander and Stedin (GTO pages); evaluation commissioned by RVO (2025); report commissioned by KGG (2025); RVO, EHUB. Accessed 23 September 2026.

If a hub doesn't fit yet, other routes remain open. The table sets them side by side, with what the sources say about them. If you still want to upgrade your own connection, read our guide on upgrading a connection.

AlternativeWhat it isConditions and caveats
Cable poolingSeveral installations or companies share one connection. According to the national government, legally possible since the Energy Act (Energiewet) entered into force on 1 January 2026, including for technologies other than solar and wind.At Enexis: joint connection of at least 100 kVA, up to 4 companies in the same region and one lead contracting party. You report joint use to the ACM, and if the connection is larger than 10 MVA, a grid check follows. The parties are “responsible for a mechanism to prevent overruns”. The installations must not be connected to the grid through other connections, and a joint connection and transport agreement is needed.
Group CBC (Groeps-CBC)A group capacity restriction contract with the grid operator. RVO mentions it alongside the Groeps-TO: “You can also take out both.”In the national action plan, “enabling Groeps-CBC” is a separate action. Model agreements are available from Invest-NL.
Shared batteryThe Energy Act counts stored renewable energy in its definition of “sharing of energy” (art. 1.1). This concerns an installation behind another connection that participants jointly own, lease or rent in whole or in part, or the right to which has been transferred.We found no grid operator page describing a shared battery as a separate contract type. Enexis allows batteries in cable pooling. In Overbetuwe, a subsidy for a battery in front of the meter ran aground on state aid rules. See also our guide to business batteries.
Closed distribution systemAn energy hub with its own grid (RVO).The regional Beuningen-Nijmegen-Wijchen hub was conceived as a closed distribution system and did not go ahead in that form (RVO evaluation).
Alternative transport rightAn individual contract with the grid operator, such as non-firm, time-block or time-duration transport.Which form your grid operator offers, and on what terms, is covered in our guides on the grid operator's queue and solving grid congestion.

Sources: Rijksoverheid, Voortgangsrapportage LAN voorjaar 2026 (2 April 2026); Enexis, Cablepooling; RVO, Uw energiehub juridisch regelen; Energiewet, Stb. 2025, 12; evaluation commissioned by RVO (2025). Accessed 23 September 2026.

If you contract with more than one market party on a single shared connection, the Energy Act sets metering requirements (art. 2.2). These include a metering installation with the communication function in use and enough additional allocation points, one per market party.

At Azeven-Noord in Drachten we worked on a collective energy strategy for 17 companies, with cable pooling. IBF Heerenveen is an area-based energy transition for 60+ companies, with an energy hub and Liander as partner.

Frequently asked questions

Questions about choosing an energy hub.

What are the disadvantages of an energy hub?

According to an evaluation commissioned by RVO (Netherlands Enterprise Agency), by 2025 hubs had got off the ground “almost nowhere in our country”. The report lists six bottlenecks; prolonged uncertainty “leads to business owners dropping out”. Under pilot contracts, all participants can be held liable for all of the damage, sometimes with no cap (AT Osborne report commissioned by the climate ministry KGG, 2025). A group transport agreement (GTO) also requires telemetry per connection and a group that can guarantee that the group capacity is not exceeded (Stcrt. 2025, 43262).

Why do energy hubs fail?

At TPN-West in Nijmegen, one hub for around 450 companies proved “a far too complex undertaking” (evaluation commissioned by RVO, 2025). During a year and a half of delay, a corporate participant with flexibility in its processes dropped out. At Powerhub Overbetuwe (investment needed: €3.6 million), a subsidy for a battery in front of the meter ran into state aid rules; the initiators eventually called it off. The report advises starting small and agreeing in advance “what to do if a party drops out”.

How big is the liability risk in an energy hub?

A report by AT Osborne for the climate ministry KGG (25 August 2025) describes the pilot contracts that pre-date the final code decision. Under them, all participants can be held liable for all of the damage, even if they were not at fault. Sometimes there is no cap; where there is one, it is, for example, €2.5 million per event and €5 million per contract year. Grid operators consider the likelihood of damage “very small”, but there is no quantitative risk analysis.

When does the group transport agreement become a right?

From 1 January 2027, a group that meets the grid code's conditions is “entitled” to enter into a GTO (Stcrt. 2025, 43262). Until that date, this is only possible “if the grid operator offers that option”. Conditions include two or more connected parties, one joint authorised representative and telemetry metering per connection (art. 7.1e). A grid operator must give written and “sound” reasons for a refusal, assessed against four criteria.

Can we join without contracted capacity of our own?

At Liander, yes: “Even with 0 contracted capacity (GTV) you can take part”, provided at least one customer in the group has capacity. According to Liander, a group contract is “not dependent on the queue”, and: “Whoever uses the capacity pays for it.” We found no comparable statement for other grid operators. The grid code lets the grid operator set the group GTV based on factors including annual profiles over 24 months and the degree of coincidence within the group (Stcrt. 2025, 43262).

What does an energy hub cost, and what does it deliver?

We found no figures in official sources for an energy management system, telemetry metering, savings on the transport tariff or avoided grid upgrades. What is settled is how the tariff works: kWcontract and kWmax(gewogen) are calculated net for the group per quarter-hour, while kWh continues to count per connection (Tarievencode, art. 3.7.18). The ACM did not adopt the proposed correction factor of 1.21, but leaves room for a later tariff solution in the event of “disproportionate tariff advantages” (Stcrt. 2025, 43262). One real-world figure from the evaluation for RVO: Powerhub Overbetuwe needed €3.6 million, but that is one case, not a benchmark.

What is the EHUB subsidy, and when can I apply?

EHUB is a new RVO scheme for research into energy hubs, open from 09:00 on 1 October 2026 until 17:00 on 1 May 2027. A study for a new hub qualifies for 70%, with a minimum of €25,000 and a maximum of €42,000. For an expansion the rate is 40%, with a minimum of €25,000 and a maximum of €32,000. If you apply for a scan and a study in one application, the scan subsidy counts towards the study's minimum amount (Stcrt. 2026, 31575, art. 4.16.3). A scan for a new hub qualifies for up to €5,000 with a maximum of 5 companies, and up to €8,500 with 6 or more. At least 3 unrelated companies with a connection above 3x80 A must take part. RVO processes applications in order of receipt; if the budget is insufficient, lots are drawn.

Which legal form suits an energy hub: cooperative or BV?

The grid code requires no specific legal form for the group transport agreement. It does require one joint authorised representative within the meaning of Article 3:60 of the Dutch Civil Code (BW) (Stcrt. 2025, 43262). Enexis does ask for a legal entity, and according to RVO “most energy hubs” choose a cooperative, a BV (private limited company) or a combination of both. An energy community under the Energy Act (Energiewet) requires effective control to rest with, among others, natural persons and micro or small enterprises (art. 2.4). Our reading: a hub in which medium-sized and large companies have effective control is therefore often not an energy community. A GTO does not require energy community status.

Free initial assessment

Let us assess whether a hub can work on your site

An initial assessment is free. We discuss with you who your grid neighbours are and whether their profiles complement yours. You can then decide whether a hub merits further study or whether an alternative is the more obvious route.