Practical guide, updated October 2026

Setting up an energy hub with a group transport agreement

On a congested grid, a company acting alone can often get no further. A group can. In an energy hub, companies share grid capacity, generation and storage, all set out in a group transport agreement (GTO) with the grid operator. This guide explains how that contract works legally, who plays which role and what steps to take, with cable pooling as a practical first step and two completed area-based case studies as evidence.

What is an energy hub?

An energy hub is a local partnership between several companies with a large-consumer connection that share grid capacity and often generation and storage too. The group sets out its arrangements with the grid operator in a group transport agreement (GTO): one joint transport contract, with each company keeping its own connection. Matching the participants' peaks and troughs creates room on the grid that is not available to any of them alone.

The contract type

What is a group transport agreement?

The group transport agreement is the legal core of an energy hub. Instead of each company having its own transport agreement, the group signs one contract with the grid operator and receives jointly contracted transport capacity (GTV). The group divides that capacity itself, and its members schedule their use smartly around each other's peaks. ACM (the Dutch regulator) wrote this contract type into the grid code in a final code decision of 19 December 2025; grid operators now offer the GTO on a small scale.

Component How it works
Contract type One transport agreement between the group and the grid operator, with jointly contracted transport capacity instead of individual contracts per company.
What stays individual Each participant keeps its own connection and its own connection agreement with the grid operator. The GTO replaces only the transport part.
Organisation The group sets up a legal entity, often a cooperative or association, that manages the transport capacity and is the point of contact for the grid operator.
Technical conditions Large-consumer connections (above 3x80 A). With Enexis, all participants sit behind the same distribution substation, at the same voltage level (low, medium or high voltage).
Allocation The group itself decides when each participant uses which share of the group capacity. That calls for metering data, allocation rules and active management of the group profile.
Status ACM code decision final since 19 December 2025. Grid operators offer the GTO on a small scale; Enexis expects to offer this contract type to a wider group of customers from 2027.

Sources: ACM (code decision on the group transport agreement), Enexis and Liander (conditions and contract variants), Netbeheer Nederland. The GTO is one of the routes around grid congestion. See the full decision framework in solving grid congestion: all the options and our wider grid congestion expertise.

The roles

Who does what in an energy hub?

An energy hub is not a product you order but a partnership you organise. The companies are jointly responsible for developing the hub; the grid operator facilitates and coordinates. Four roles determine whether it works.

The participating companies

Contribute their consumption and generation profiles and commit to the allocation rules. They keep their own connection and operations: the hub affects only transport capacity, not their autonomy. Buy-in from the participants is the first bottleneck in any hub project.

The legal entity

A cooperative or association that manages the shared transport capacity on behalf of the group, enters into the GTO with the grid operator and handles internal settlement. Governance design (decision rights, joining and leaving, cost allocation) is the real work here.

The grid operator

Counterparty to the GTO. Determines, in consultation with the group, how much transport capacity is available and facilitates the process. Since the ACM code decision, Liander, Enexis and the other regional grid operators have offered this contract type on a small scale, and they use step-by-step plans for energy hubs.

The energy coordinator / CSP

Someone has to measure, manage and monitor the group profile every day, or the GTO remains a paper exercise. Energyc has a Congestion Service Provider (CSP) in-house for this and supports hubs from feasibility through to operation, independent of suppliers and installers.

The physical variant

Cable pooling: sharing one connection

Alongside sharing transport capacity by contract (GTO), there is a physical variant: cable pooling. Installations or parties with complementary profiles share one grid connection: solar and wind, or generation and consumption. The cable is used more fully, and no new connection is needed on a grid that could not supply one anyway.

Cable pooling is often the quickest practical step within a wider area-based approach. On the Azeven-Noord business park in Drachten we put solar panels on the largest roof on the site, and 6 companies share the output through one connection. None of them had to apply for their own PV connection, which would have failed in this congestion area anyway. The installation runs within a collective site-wide approach with 17 companies, cooperative governance and a group contract with the energy supplier that delivers a lasting saving of around 12% on tariffs.

For cable pooling, allow a lead time of 6–18 months, depending on contracting and the technical work. A full energy hub with a GTO takes 1–3 years; Liander cites an average lead time of about two years. The sequence is therefore often to start with cable pooling where profiles directly complement each other, then build towards a hub once governance and metering data are in place.

How we work

How to set up an energy hub

Grid operators use step-by-step plans for energy hubs; Enexis uses eight steps, from initiative to operation. Energyc supports the whole process and groups it into four phases. We are an independent advisor: not an installer, not a supplier.

01

Initial assessment

Free initial consultation: the site's grid situation, willingness to take part, an initial profile analysis. Which companies will take part, and does a GTO, cable pooling or a combination fit? Our guide on the drawbacks, and when a hub does fit helps with that first assessment.

02

Feasibility & profiles

Consumption and generation profiles side by side, with the joint peak and flexibility potential worked through to a business case. For the scan and study, the EHUB subsidy is available from 1 October 2026; up to and including 15 October 2026, Flex-e covered 50% of a flexibility scan or feasibility study.

03

Governance & contract

Designing the legal entity, allocation rules and settlement; negotiating the GTO with the grid operator. The agreements between companies are the real work here.

04

Delivery & operation

Measuring, managing and monitoring the group profile, with CSP services in-house. Further development with storage, generation or charging infrastructure once the hub is running.

Subsidy for your hub's scan and study

From 1 October 2026, RVO (Netherlands Enterprise Agency) subsidises research into an energy hub through the EHUB scheme: €5,000 or €8,500 for a scan, and 70% of eligible costs for a study of a new hub (minimum €25,000, maximum €42,000). You can apply up to and including 1 May 2027. Flex-e also ran up to and including 15 October 2026, covering 50% of a flexibility scan (up to €10,000) or feasibility study (subsidy of €10,000 to €125,000), and up to 40% of measures such as storage (€25,000 to €300,000). See our EHUB guide, the Flex-e guide or the wider subsidy overview.

70% Reimbursement for a study of a new energy hub, up to €42,000 Source: RVO EHUB, 2026
Frequently asked questions

Questions about energy hubs and the GTO.

What is an energy hub?

An energy hub is a local partnership between several companies with a large-consumer connection that share grid capacity and often generation and storage too. Matching supply and demand locally creates room on the grid that is not available to any of them alone. The group sets out its arrangements with the grid operator in a group transport agreement (GTO); within the hub, a joint legal entity handles allocation and settlement.

What is a group transport agreement (GTO)?

A group transport agreement is a contract under which a group of companies signs one transport agreement with the grid operator and receives jointly contracted transport capacity (GTV). The participants divide that capacity among themselves, and each keeps its own connection and connection agreement. ACM (the Dutch regulator) wrote this contract type into the grid code in a final code decision of 19 December 2025.

What conditions apply to a group transport agreement?

The group sets up a legal entity that manages the transport capacity and agrees terms with the grid operator. All participants have a large-consumer connection (above 3x80 A); with Enexis, participants must also sit behind the same distribution substation and be connected at the same voltage level. Within those limits, the group itself decides when each participant uses which share of the group capacity. Grid operators currently offer the GTO on a small scale; Enexis expects to make this contract type more widely available from 2027.

How long does it take to set up an energy hub?

Allow 1–3 years, including governance and contracting; Liander cites an average lead time of about two years. Cable pooling as a first step is quicker: 6–18 months. The lead time depends mainly on organising the cooperation between companies, not on the technology.

What is the difference between cable pooling and an energy hub?

Cable pooling means physically sharing one grid connection between installations or parties with complementary profiles, such as solar and wind, or generation and consumption. An energy hub goes further: participants keep their own connection but share their contracted transport capacity through a group transport agreement, and often generation and storage too. Azeven-Noord was a case of cable pooling: a shared PV installation on one connection, within a collective site-wide approach with one joint supply contract.

What subsidy is available for setting up an energy hub?

For research into an energy hub, RVO opened the Onderzoek Energiehubs (EHUB) scheme on 1 October 2026. A scan qualifies for €5,000 or €8,500, depending on the number of participants; a study of a new hub receives 70% of eligible costs, with a minimum of €25,000 and a maximum of €42,000. At least three unrelated companies with a connection above 3x80 A must take part; applications are open up to and including 1 May 2027. Up to and including 15 October 2026, the Flex-e scheme also reimbursed 50% of a flexibility scan (up to €10,000) or feasibility study (subsidy of €10,000 to €125,000), and up to 40% of measures such as storage (€25,000 to €300,000). You choose your own advisor; RVO stresses the importance of an experienced professional, such as Energyc.

Sources & references

Sources

Real-world figures come from completed Energyc projects: Azeven-Noord (17 companies, joint supply contract, cable pooling) and IBF Heerenveen (area-based approach with 60+ companies on 250 hectares).

Working together on a congested grid?

Explore whether an energy hub is feasible on your site

A 30–60 minute exploratory conversation is free and without obligation. You tell us about the situation on the site; we come back with an initial view of profiles, participants and the most promising route: GTO, cable pooling or a combination.

Discuss your situation →