Business solar panels not, or no longer, allowed to feed in: which rules apply and what you can do
If your business is not, or no longer, allowed to feed in, you can still use the solar power yourself. On a large-consumer connection the grid operator can require you to feed in less (RVO, the Netherlands Enterprise Agency, 2026). If you use everything yourself, you can apply to Enexis with 0 kW of feed-in. Which route suits you depends partly on your consumption during sunlight hours; shifting consumption to those hours requires no purchase.
My business is not, or no longer, allowed to feed in its solar power. What can I do?
At Enexis, a new feed-in application in a congestion area joins a queue; if you use everything yourself, you can also apply with 0 kW of feed-in. If existing feed-in is being limited, ask the grid operator on what grounds; according to RVO this is possible on a large-consumer connection. You can increase self-consumption by shifting consumption to sunlight hours, which need not involve a purchase, or with storage (RVO). We found no payback period for a roof without feed-in in any primary source; we calculate it case by case.
What feed-in congestion means for a new application
The Netbeheer Nederland capacity map shows "where sufficient transport capacity is available and where shortages have arisen". Enexis uses four colours for feed-in, from transparent to red. All four concern new applications.
| Enexis colour | What Enexis says | Effect on a new application |
|---|---|---|
| Transparent | "Transport capacity is available." | You can (still) apply. |
| Yellow | Limited transport capacity available. Enexis expects a transport shortage in the short term. | It is uncertain whether Enexis can allocate capacity. Quotes are valid for 1 month instead of 3 months. |
| Orange | Expected shortage, reported to ACM. Enexis is investigating whether congestion management can free up enough capacity. | New applications join a queue. |
| Red | No transport capacity left. According to the investigation, congestion management will not solve the shortage. | New applications join the queue. |
Enexis, Beperkte capaciteit op het elektriciteitsnet voor terugleveren (accessed 23 September 2026). Enexis updates the map on the first Friday of every month.
Enexis adds a warning: "This data confers no rights." A technical assessment after your application determines whether capacity is available. Enexis advises against investing purely on the strength of the map if that investment requires extra capacity.
At the end of 2025, the regional grid operators had 8,687 feed-in applications in the queue, totalling 5,027 MW. A year earlier there were 8,440, totalling 4,123 MW (Netbeheer Nederland, Stand van de Uitvoering 2025, p. 19). On 1 September 2026, Stedin had 630 feed-in applications in the queue, totalling 270 MW (Stedin, 2026).
In August 2026, Liander reported two new feed-in bottlenecks in Friesland, at Schenkenschans substation (10-1i and 10-2i). In July 2026, Enexis reported a new feed-in bottleneck in Veendam (Groningen).
At Enexis, feed-in applications on an existing connection go first. Applications on a new connection, or on one still to be upgraded, follow. Within each group, the application date determines the order.
Enexis advises: "Always request a quote, even if no transport capacity is available." You only join the queue after applying; there is more on this in our guide to the grid operator queue.
In the Utrecht region, Stedin runs a queue for feed-in applications on new or existing connections above 3x80 A. According to Stedin, that means "more than about 200 solar panels". If you already have a suitable connection, you need a grid check. Stedin reports that it was able to connect 112 MW in Utrecht and so reduce the queue.
When the grid operator can limit existing feed-in
RVO writes: "on large-consumer connections (above 3x80 A), your grid operator may require you to feed less electricity back into the grid." The aim is to reduce or prevent grid congestion (RVO, Zonne-energie op gebouwen, 2026). For connections of 3x80 A or smaller, we found no such obligation in any primary source.
By law, your contracted transport capacity is "differentiated between offtake from the system and feed-in to the system" (Begrippencode elektriciteit 2026). So first check what feed-in capacity your contract states. Offtake capacity is covered in our guide to peak demand.
ACM describes an obligation to bid for congestion management. We also examined the 2024 GOTORK decision; we have not established whether it applies to feed-in capacity or how it carried over under the Energy Act (Energiewet). Enexis also lists technical requirements that an installation must continue to meet.
| Basis | Who it applies to | What it involves |
|---|---|---|
| Obligation to bid for congestion management ACM, decision of 22 August 2024 | Connected parties with a contracted transport capacity of 1 MW or more. | The grid operator can require you to offer congestion management services: redispatch and/or capacity restriction. The notice states whether the obligation applies to feed-in or offtake. You decide what fee to ask; if you make no offer, you must make a payment to the grid operator. |
| GOTORK ("use it or lose it") ACM, decision of 16 April 2024 | Only parties connected to the medium-, high- or extra-high-voltage grid, and only in congestion areas. | The grid operator can restrict unnecessarily contracted transport capacity, where substantial volumes are involved and only after consultation. You can show that the capacity is needed, or will be needed within a reasonable period. We have not established whether the decision applies to feed-in capacity or how it carried over under the Energy Act. |
| Technical requirements Enexis | Generation installations, including existing ones you substantially modify, for example by replacing inverters or changing capacity. | European and national requirements have applied since April 2019 (Requirements for Generators and Systeemcode elektriciteit). "You may only (continue to) feed energy into the grid if your installation meets the requirements." |
ACM, Codebesluit verplichting aanbieden congestiemanagementdiensten (ACM/23/186822) and Codebesluit niet gebruikte transportrechten (ACM/22/180812); Enexis, Terugleveren via bestaande aansluiting; accessed 23 September 2026.
The GOTORK decision refers to contracted transport capacity in general. It does not say in so many words that this also covers the capacity you may feed in. The exception for vital processes, however, expressly does not apply to connections of electricity generation installations. The decision still refers to the Electricity Act 1998 (Elektriciteitswet 1998); we have not checked how the rules carried over under the Energy Act.
For new generation, Enexis has one further requirement. Power control through a Realtime Interface (RTI) is mandatory for all new generation connections above 1 MW, which Enexis says is in line with European legislation. This does not apply to existing connections unless you apply for an upgrade; see also our guide to upgrading a connection.
Solar panels without feed-in: the 0 kW application at Enexis
Enexis describes a route for businesses that generate but do not feed in, because they use all their electricity themselves. You can then submit a feed-in application even in an area with limited capacity. Enexis's advice: "In your application, leave the requested feed-in transport capacity at 0 kW."
For advice, Enexis refers you to the supplier of your generation installation and your metering company: you can check with them whether you really use all the electricity yourself. Enexis's requirements for generation installations include the following two. You register the installation at least 3 months before commissioning. The installation must also meet the European and national requirements in force since April 2019.
Enexis does not mention a separate technical standard for export limiters on that page. Nor did we find a standard or notification requirement for them in other primary sources. Ask your grid operator before you buy anything. We found the 0 kW route described by Enexis; we have not checked it with other grid operators.
One question remained open: can you start at 0 kW and stay in the feed-in queue at the same time? We did not find this described; ask your grid operator about that too. For SDE++, a roof with 0 kW of feed-in may have a downside; see the section on SDE++ 2026.
Routes for a roof that is not allowed to feed in
RVO lists seven types of solution for grid congestion, from managing consumption to a direct line to a large customer. The table sets out the routes that suit a solar roof with no feed-in headroom, plus Enexis's 0 kW route. Not every route involves a purchase. For offtake, the wider overview is in our guide to solving grid congestion.
| Route | How it works | What it requires of you |
|---|---|---|
| Apply and wait | Submit a feed-in application even if no capacity is available, as Enexis advises. At Enexis, applications on an existing connection go first. | An application to the grid operator. Nothing to buy. |
| Shift consumption | Run processes and equipment during the hours the panels generate. RVO: "Can you, for example, switch equipment on or off at other times?" | A clear picture of your consumption and room in your schedule. In its basic form, nothing to buy. |
| 0 kW feed-in | Apply for solar panels with no feed-in capacity and use all the electricity yourself (Enexis). | Check that you really use all the electricity yourself. We found no standard for export limiters; ask your grid operator. |
| Storage | Store surpluses in a battery and use them yourself later (RVO). | A battery. For EIA code 251118 it must be connected to a renewable generation installation of more than 15 kW peak, on the same connection. |
| Cable pooling | Share a connection with another business, including in an area with grid congestion (RVO). | A connection of 100 kVA or more, up to 4 installations (WOZ properties) located close together, and a notification to ACM. |
| Group contract | Agree a joint contracted capacity with the grid operator as a group of businesses (RVO). | Neighbouring businesses that take part, and a group transport agreement (GTO). |
| Contract with the grid operator | Apply for priority as a congestion mitigator (congestieverzachter), at Liander also for feed-in, or for an alternative transport right. | Contractual agreements on limiting congestion. Discuss with your grid operator what is possible for feed-in. |
Routes based on RVO, Enexis, ACM, Liander and the Brochure EIA Energielijst 2026 (accessed 22 and 23 September 2026).
For a battery alongside your own generation there is EIA code 251118, a tax allowance (Brochure EIA Energielijst 2026, p. 63). It requires a battery of at least 5 kW and 15 kWh, and excludes flooded lead-acid. The battery must be "connected to a renewable generation installation with an installed (peak) capacity of more than 15 kW", on the same connection. The deduction rate is 40%, with a minimum of €2,500 per asset (Wet IB 2001, art. 3.42; brochure p. 4).
Code 260101 has no such link to your own generation, but requires a software link to an electricity sub-market. What else a battery can deliver, and how EIA and Flex-e fit together, is covered in our guide to the business battery.
Metalis, a metalworking company in Drachten, was given 0 kW of available capacity by Liander. The company now combines 450 solar panels, a 1.2 MWh battery, a capacity restriction contract (CBC-T) with Liander and an energy management system (EMS) that controls it all. You can read how it was set up in the Metalis case study.
According to ACM, cable pooling is possible with a connection of 100 kVA or more, for up to 4 installations (WOZ properties) located close together. According to RVO, it can involve generation, storage, consumption and conversion, and "the same or an adjoining plot" is often enough. In an area with grid congestion, the grid operator can connect you jointly with a business that already has a connection (RVO). The connection must then be able to carry enough transport capacity, and you must have sufficient contracted transport capacity.
First you arrange the shared connection with the grid operator, then you report it to ACM. Together, the installations must not exceed the maximum connection and transport capacity of the shared connection (RVO). A roof that is not allowed to feed in can thus be paired with a neighbouring business that uses the electricity.
RVO: "Within an energy hub, a group contract lets you agree a joint contracted capacity with the grid operator, together with several businesses." RVO expects "that this option will become available more often in the coming years". For a group with simultaneous feed-in and offtake, the transport tariff is based on "the net capacity profile of the group". That profile is "based on an imbalance settlement period of 15 minutes" (Tarievencode elektriciteit 2026, chapter 3).
How to set up such a hub is covered in our guide to the energy hub and the group transport agreement. To see whether a hub suits your business park, read our energy hub decision guide.
At Liander, the priority category of congestion mitigator (congestieverzachter) covers both consumption and feed-in; it requires contractual agreements on limiting congestion (Liander, Maatschappelijk prioriteren). For connections above 3x80 A there are alternative transport rights, such as non-firm transport on residual capacity, with no guarantee, and time-block contracts (Netbeheer Nederland). Discuss with your grid operator whether one of these is also available for your feed-in.
Under a capacity restriction contract (CBC), a connected party gives up part of its capacity in return for payment; the fee is set case by case (ACM). According to ACM, generators can generally provide such a restriction more cheaply than consumers.
SDE++ 2026: transport capacity indication and a 50% cap on additional feed-in capacity
SDE++ 2026 is open from 27 October 2026, 09:00, to 26 November 2026, 17:00 (Stcrt. 2026, 25954, art. 2). The subsidy ceiling is €8 billion. For solar PV on buildings there are categories from 15 kWp, split into below 1 MWp and 1 MWp or more (explanatory note § 5.1.2).
For solar PV on a connection above 3x80 A, the application must include a statement from the grid operator (Algemene uitvoeringsregeling, art. 2d(2)). That statement concerns "the availability of transport capacity" and is called the transport capacity indication. RVO describes the requirements for solar in 2026 as stricter. The grid operator is "slower to issue a transport capacity indication to an electricity producer, who therefore has to wait longer" (RVO, 2026).
The Aanwijzingsregeling SDE++ 2026 also caps the feed-in capacity of building-mounted solar PV. Additional contracted feed-in capacity "amounts to at most 50% of the peak capacity of the solar panels" (art. 19(3)). The same requirement applies to most ground-mounted and floating categories under art. 21(2). It does not apply to solar-tracking PV systems (explanatory note § 5.1.2).
The explanatory note gives the reason: "This allows more renewable energy projects to be built with the same grid capacity and limits grid congestion." The limited loss of yield is "offset by a lower number of full-load hours and a higher base amount".
Worked example (our application of art. 19(3); assumptions: new connection, building-mounted, no tracking system). A 500 kWp roof may then contract at most 250 kW of feed-in capacity for SDE++.
Under an existing contract, feed-in capacity for other facilities, such as an existing solar PV installation, need not be counted. If your current feed-in capacity exceeds the peak capacity of the existing installation, the difference is deducted from the 50%. Without contracted feed-in capacity, "the feed-in capacity otherwise agreed between the grid operator and the subsidy recipient prevails" (explanatory note § 5.1.2).
In the 2025 round, the feed-in capacity in the transport capacity indication had to be "greater than 0" (Brochure SDE++ 2025, pp. 19–20). The indication also had to be issued for that round, and was "no guarantee of transport capacity". We have not established whether this requirement also applies in 2026. Check with RVO before you plan a roof with 0 kW of feed-in for SDE++.
For solar, you also consent to data sharing between the grid operator and the minister (Algemene uitvoeringsregeling, art. 2d(5)). This covers "the feed-in capacity contracted with the grid operator and the EAN code" of the installation. For building-mounted solar PV, the 2026 scheme also sets a requirement for the panels (art. 19(4)). Their CO₂ footprint in the product stage (A1–A3) must not exceed 550 kg per kWp, as shown by an environmental product declaration.
Profitable without feed-in: what the outcome depends on
We found no payback period for a solar roof without feed-in in any primary source. Any figure you see is therefore someone's own calculation. What we can do is name some of the factors that determine the outcome.
Without feed-in, the value of the roof lies in electricity you use yourself and so do not have to buy. How much that is depends partly on your consumption during the hours the panels generate. RVO names two ways to make better use of the electricity yourself: shifting consumption to other times, and storage (Zonne-energie op gebouwen). We calculate this case by case, using your own consumption data.
At Liander, a large consumer pays no transport charges for feed-in in 2026 (Liander, large-consumer tariff sheet 2026). The Tarievencode elektriciteit 2026 allocates 100% of transport-dependent costs to "connected parties that receive electricity" (art. 3.6).
ACM has looked into a possible future network tariff for large producers and consulted the market on parts of it in 2025 (ACM, Focus op Energie 2026). According to that agenda, ACM will take "a decision on further developing network tariffs for producers" in 2026. We found no such decision up to and including 23 September 2026. If you are building a business case on feed-in, keep an eye on this process.
Flex-e required a large connection in a declared area with offtake congestion (Stcrt. 2026, 12853). In the 2025 round, SDE++ required a transport capacity indication with more than 0 kW of feed-in (Brochure SDE++ 2025). Our reading: with feed-in congestion alone you did not meet the stated eligibility requirement for Flex-e. We have not established whether a roof with 0 kW of feed-in qualifies for SDE++ 2026.
For a battery, however, the EIA tax allowance under code 251118 may apply if the conditions of that code are met. If your business was also in a declared area with offtake congestion and had a large connection, Flex-e could have been an option. Flex-e covered 40% of eligible costs, with a subsidy of at least €25,000 and at most €300,000 (Stcrt. 2026, 12853). If you applied for a subsidy for a battery alone, the battery had to be at least 50 kW (RVO).
The Flex-e 2026 application window closed on 15 October 2026 at 17:00 (RVO). The conditions are in our Flex-e guide and our subsidy overview.
Solar panels on the barn roof: what applies to farm businesses
RVO writes about solar in agricultural areas: "In agricultural areas the available roof area or field space is often large." But "there is a traffic jam on the electricity grid: grid congestion". For some farm businesses, an energy management system may therefore be of interest: "a system that matches electricity supply and demand" (RVO, 2024).
The rules in this guide also apply to farm businesses. If your business has a connection above 3x80 A, the grid operator can require you to feed in less (RVO). An SDE++ application for solar on a barn roof requires a transport capacity indication on a connection above 3x80 A (Algemene uitvoeringsregeling SDE++, art. 2d). In SDE++ 2026, additional feed-in capacity of building-mounted solar PV is capped at 50% of peak capacity, solar-tracking PV systems excepted (Stcrt. 2026, 25954).
The 2026 Flex-e scheme had no separate sub-ceiling for agriculture, only sub-ceilings for parts a to d (Stcrt. 2026, 12853). The word agriculture appears in the scheme and explanatory note only in connection with state aid. For parts c and d, the subsidy for flexibility measures, the agricultural de minimis regulation could apply "where relevant" (art. 4.12.11(4) and explanatory note).
We have not established how high the aid ceiling under that regulation is. So do not simply assume the Flex-e maximum of €300,000 (Stcrt. 2026, 12853) applied; check with RVO. Flex-e also required an area with offtake congestion. Our reading: if your business faced congestion on feed-in alone, it would not have qualified for Flex-e.
For a new barn roof with no feed-in headroom, you follow the same steps as any business. Enexis advises requesting a quote in that case too, since you only join the queue after applying. A neighbouring business on an adjoining plot can be a partner for cable pooling. EIA code 251118 may apply to a battery; it requires a renewable generation installation of more than 15 kW peak on the same connection (Energielijst 2026).
Questions about feed-in and grid congestion.
Can the grid operator limit my business's feed-in?
On a large-consumer connection (above 3x80 A), the grid operator can require you to feed in less, according to RVO (Netherlands Enterprise Agency). In grid code decisions by ACM (the Dutch regulator) we found an obligation to bid for congestion management at a contracted transport capacity (GTV) of 1 MW or more, and GOTORK ("use it or lose it") for unnecessarily contracted capacity. The GOTORK decision concerns medium, high and extra-high voltage in congestion areas; we have not established whether it applies to feed-in capacity or how it carried over under the Energy Act (Energiewet). For connections of 3x80 A or smaller, we found no such obligation in any primary source.
Can I put solar panels on my business roof without feeding in?
Yes. At Enexis you can do this through a feed-in application that sets the requested feed-in transport capacity to 0 kW. Enexis says you can check with your installation supplier and your metering company whether you really use everything yourself. According to Enexis, you register the installation at least 3 months before commissioning, and it must comply with the RfG and the Systeemcode elektriciteit (the Dutch electricity grid code). We found no separate standard or notification requirement for export limiters in any primary source; ask your grid operator what it expects.
Does a solar roof without feed-in pay off?
Without feed-in, the value of the roof lies in electricity you use yourself and so do not have to buy. How much that yields depends partly on your consumption during the hours the panels generate. RVO names two ways to use the electricity yourself: shifting consumption to other times, and storage. We found no payback period for a solar roof without feed-in in any primary source; any figure you see is someone's own calculation.
What does orange or red on the capacity map mean for feed-in?
At Enexis, orange means an expected shortage: new applications join a queue while Enexis investigates whether congestion management can free up enough capacity. Red means no transport capacity is left and, according to that investigation, congestion management will not solve the shortage; new applications join the queue. The colours concern new applications; the legend says nothing about existing contracts. The capacity data "confers no rights", Enexis writes: a technical assessment after your application determines whether capacity is available.
Can I get SDE++ for solar panels if I can feed in little or nothing?
For solar on a connection above 3x80 A, SDE++ requires a transport capacity indication from the grid operator (Algemene uitvoeringsregeling SDE++, art. 2d). In SDE++ 2026, additional feed-in capacity for building-mounted solar PV is capped at 50% of peak capacity, solar-tracking PV systems excepted (Stcrt. 2026, 25954, art. 19; explanatory note § 5.1.2). Worked example (our calculation for a building-mounted installation on a new connection, with no tracking system): at 500 kWp the maximum is 250 kW of feed-in capacity. In the 2025 round, the feed-in capacity in the transport capacity indication had to be "greater than 0"; we have not established whether that still applies in 2026.
Can I share my grid connection with a neighbouring business?
Yes. According to ACM, cable pooling is possible with a connection of 100 kVA or more, for up to 4 installations (WOZ properties) located close together. According to RVO, it can involve generation, storage, consumption and conversion, and "the same or an adjoining plot" is often enough. In a congestion area the grid operator can connect you jointly with a business that already has a connection, provided there is enough transport capacity and contracted transport capacity. Once you have made arrangements with the grid operator, you report the shared connection to ACM.
Does my business pay to feed electricity into the grid?
At Liander, a large consumer pays no transport charges for feed-in in 2026 (Liander, large-consumer tariff sheet 2026). The Tarievencode elektriciteit 2026 allocates 100% of transport-dependent costs to "connected parties that receive electricity" (art. 3.6). ACM has looked into a possible network tariff for large producers; according to Focus op Energie 2026, a decision on further development will follow in 2026. We found no such decision up to and including 23 September 2026.
Would my farm have qualified for Flex-e if it had not been allowed to feed in?
Flex-e required a large connection in a declared area with offtake congestion, and the 2026 scheme had no separate sub-ceiling for agriculture (Stcrt. 2026, 12853). Our reading: with congestion on feed-in alone you would not have qualified; if you were also in an area with offtake congestion, you might have. For subsidy towards flexibility measures, the agricultural de minimis regulation could apply where relevant; we have not established its ceiling. A battery may fall under EIA code 251118 (a tax allowance), which requires a renewable generation installation of more than 15 kW peak on the same connection (Energielijst 2026).
Know what is allowed before you buy.
An initial assessment is free. We go through your connection and transport agreement (ATO) with you, along with your consumption during the hours the panels generate. Energyc is an independent advisor, not an installer.
Discuss your situation →Sources
- Enexis — Beperkte capaciteit op het elektriciteitsnet voor terugleveren · legend for feed-in (transparent, yellow, orange, red), quotes valid for 1 month instead of 3 months, disclaimer on the capacity data, update on the first Friday of every month (accessed 23 September 2026)
- Enexis — Terugleveren via bestaande aansluiting · order of the feed-in queue, advice to always request a quote, application with 0 kW of feed-in, registration at least 3 months before commissioning, technical requirements since April 2019, power control (RTI) for new generation above 1 MW (accessed 23 September 2026)
- Stedin — Transportschaarste voor opgewekte energie (provincie Utrecht) · feed-in queue on connections above 3x80 A (more than about 200 solar panels), grid check, 112 MW connected (accessed 23 September 2026)
- Stedin — Wachtlijsten in congestiegebieden (pdf) · 630 feed-in applications, totalling 270 MW, as at 1 September 2026 (accessed 22 September 2026)
- Netbeheer Nederland — Capaciteitskaart · national map of available transport capacity and shortages (accessed 23 September 2026)
- Netbeheer Nederland — Stand van de Uitvoering 2025 (pdf) · feed-in queue at the regional grid operators: end of 2025, 8,687 applications and 5,027 MW; end of 2024, 8,440 applications and 4,123 MW (p. 19; accessed 22 September 2026)
- Liander — Update capaciteit elektriciteitsnet augustus 2026 · two new feed-in bottlenecks in Friesland: Schenkenschans 10-1i and 10-2i (accessed 22 September 2026)
- Enexis — Update netcapaciteit juli 2026 · new feed-in bottleneck in Veendam (accessed 22 September 2026)
- RVO — Zonne-energie op gebouwen · grid operator can require a large consumer (above 3x80 A) to feed in less; shifting consumption and storage (last modified 20 April 2026; accessed 23 September 2026)
- Begrippencode elektriciteit 2026 (BWBR0052320) · definition of contracted transport capacity, differentiated between offtake and feed-in (accessed 22 September 2026)
- ACM — Codebesluit verplichting aanbieden congestiemanagementdiensten (ACM/23/186822) · obligation to bid at a contracted transport capacity of 1 MW or more, for feed-in or offtake, fee set by the connected party; decision of 22 August 2024 (accessed 23 September 2026)
- ACM — Codebesluit niet gebruikte transportrechten, GOTORK (ACM/22/180812) · restricting unnecessarily contracted transport capacity, only on medium, high and extra-high voltage in congestion areas and after consultation; decision of 16 April 2024 (accessed 23 September 2026)
- ACM — Codebesluit GOTORK, besluittekst (pdf) · exception for vital processes does not apply to connections of electricity generation installations (article I, paragraph 7(a); accessed 23 September 2026)
- RVO — Oplossingen bij netcongestie voor bedrijven · seven types of solution, group contract within an energy hub (accessed 23 September 2026)
- ACM — Cable pooling melden · connection of 100 kVA or more, up to 4 installations (WOZ properties) located close together, including batteries, notification after arrangements with the grid operator (accessed 23 September 2026)
- RVO — Deel uw aansluiting met een bedrijf in de buurt (cable pooling) · generation, storage, consumption and conversion; the same or an adjoining plot; connecting in a congestion area jointly with a business that already has a connection (accessed 23 September 2026)
- Tarievencode elektriciteit 2026, hoofdstuk 3 (BWBR0052321) · 100% of transport-dependent costs allocated to connected parties that receive electricity (art. 3.6); net capacity profile under a group transport agreement (accessed 23 September 2026)
- Liander — Tarieven aansluiting en transport elektriciteit grootverbruik 2026 (pdf) · no transport charges for feed-in on large-consumer connections (accessed 22 September 2026)
- RVO — Brochure EIA Energielijst 2026 (pdf) · code 251118 with its generation-link condition (p. 63), code 260101 with its software-link condition (p. 66), minimum of €2,500 per asset (p. 4), flooded lead-acid excluded (p. 77) (accessed 22 September 2026)
- Wet IB 2001, artikel 3.42 (versie 1 januari 2026) · EIA rate of 40% (accessed 22 September 2026)
- Liander — Maatschappelijk prioriteren · congestion mitigator category for consumption and feed-in, contractual agreements on limiting congestion required (accessed 22 September 2026)
- Netbeheer Nederland — Zo werkt het: alternatieve transportrechten · non-firm, time-block and time-duration transport rights for connections above 3x80 A (accessed 22 September 2026)
- ACM — Vragen en antwoorden congestiemanagement en capaciteitsbeperkingscontract (pdf) · definition of CBC, no fixed fee, generally cheaper for generators to provide than for consumers (§§ 3.1, 3.3, 3.5; accessed 22 September 2026)
- Staatscourant 2026, 25954 — Aanwijzingsregeling SDE++ 2026 · open from 27 October up to and including 26 November 2026 and ceiling of €8 billion (art. 2); up to 50% additional feed-in capacity (art. 19(3), art. 21(2)); CO₂ requirement of 550 kg per kWp (art. 19(4)); reason and compensation (explanatory note § 5.1.2) (accessed 22 and 23 September 2026)
- Algemene uitvoeringsregeling stimulering duurzame energieproductie en klimaattransitie, art. 2d (BWBR0023563) · statement from the grid operator on transport capacity for a connection above 3x80 A (para. 2); consent to data sharing on feed-in capacity and EAN code (para. 5) (accessed 23 September 2026)
- RVO — Ondernemers krijgen in 2026 meer tijd voor subsidieaanvraag SDE++ · stricter requirements for solar, grid operator slower to issue a transport capacity indication (last modified 6 July 2026; accessed 23 September 2026)
- RVO — Brochure SDE++ 2025 (pdf) · feed-in capacity in the transport capacity indication greater than 0, indication per application round, no guarantee of transport capacity (pp. 19–20; accessed 23 September 2026)
- ACM — Focus op Energie 2026 (pdf) · research into a network tariff for large producers, consultation in 2025, decision on further development in 2026 (accessed 23 September 2026)
- Staatscourant 2026, 12853 — Wijzigingsregeling openstelling Flex-e 2026 · eligibility requirement of offtake congestion, 40% subsidy, at least €25,000 and at most €300,000, battery of at least 50 kW, sub-ceilings per part, agricultural de minimis regulation (art. 4.12.11(4)) (accessed 22 and 23 September 2026)
- RVO — Flex-e: Flexibiliteitsmaatregelen · 2026 application window closed on 15 October 2026 at 17:00 (accessed 22 September 2026)
- RVO — Zonne-energie in agrarisch gebied · large roofs, grid congestion, energy management system (last modified 21 October 2024; accessed 23 September 2026)