Practical guide, updated October 2026

Flex-e subsidy: the complete guide

The Flex-e scheme run by RVO (Netherlands Enterprise Agency) covers 50% of the cost of a flexibility scan and feasibility study where grid congestion is a problem, and up to 40% of flexibility measures such as a battery or e-boiler. The 2026 application window closed on 15 October. This guide explains who the scheme applies to, which costs qualify, how the application works step by step and which mistakes to avoid.

What is the Flex-e scheme?

The Flex-e scheme is an RVO subsidy for flexible electricity use where the grid is congested. It covers 50% of a flexibility scan (up to €10,000 in subsidy), 50% of a feasibility study (€10,000 to €125,000) and up to 40% of flexibility measures such as batteries, e-boilers and heat buffers (€25,000 to €300,000). Flex-e applies to connections above 3x80 A; the 2026 application window ran from 6 May to 15 October inclusive.

Eligibility & costs

What does the Flex-e scheme cover?

Flex-e is for companies running up against the limits of the electricity grid: businesses and institutions with a connection above 3x80 A and a metering contract with a metering company. Examples include a manufacturer looking to electrify, a logistics company planning a charging hub, or a business owner who cannot get extra capacity from the grid operator. The scheme covers both the advice (scan and feasibility study, 50%) and flexibility measures such as batteries, e-boilers and heat buffers (up to 40%). Solar panels and standard installations are excluded; separate schemes such as the EIA exist for those. See our subsidy overview.

15 October2026 window closed at 17:00
50%Subsidy on scan & study
Max. 40%On flexibility measures

The application window ran from 6 May until 17:00 on Thursday 15 October 2026. RVO decides within 8 weeks of a complete application.

Component Market price (excl. VAT) Flex-e contribution Your contribution (indicative)
Grid congestion review
Initial analysis of site and connection
Free from Energyc Not needed €0
Flex scan
Flexibility, battery, ANW contract, on-site generation
€5.000 - €10.000 50% (subsidy up to €10,000) €2.500 - €5.000
Feasibility study
Full business case + technical design
€10.000 - €30.000 50% (subsidy €10,000 - €125,000) €10,000 - €15,000
for study costs from €20,000
Flexibility measures
Battery, e-boiler, heat buffer, conversion
Varies by project Max. 40% (subsidy €25,000 - €300,000) 60% of the investment
Complex project with implementation support
E.g. energy hub or battery + cable pooling
€15.000 - €40.000 Advisory part eligible, depending on scope By quotation

Market prices in line with our energy advice cost guide. For agricultural businesses, flexibility measures are capped at €50,000. The exact eligible costs and conditions are on RVO's Flex-e page.

Step by step

The application in five steps

The application itself is not a big project, but the sequence matters. Rule of thumb for almost every RVO scheme: complete the application first, start the project afterwards. The 2026 window ran from 6 May until 17:00 on 15 October 2026; RVO decides within 8 weeks of a complete application. Before submitting, always check the current conditions on the RVO page.

01

Check the advisor

For the scan and the feasibility study, RVO refers applicants to qualified advisors in the Netcongestie Register. Choose an advisor who works independently, without commission from installers or suppliers.

02

Quotation with a clear scope

Have the quotation state what will be investigated (flex scan or feasibility study), which deliverables you get and at what price. A tight scope makes both the application and the final settlement straightforward.

03

Application to RVO

Submit the application to RVO, with the quotation as supporting evidence, before the project starts and while the window is open (the 2026 window closed on 15 October 2026 at 17:00). Your advisor supplies the documents.

04

The advisory work

The flex scan or feasibility study is carried out: data analysis, scenarios, business case and a report you can use to make a decision and to engage with the grid operator.

05

Final settlement

Afterwards you account for the costs incurred, with the quotation, final report and invoices. The subsidy amount is then finalised and paid out.

Pitfalls

Five common mistakes in Flex-e applications

1. Choosing an advisor who is not independent

Flex-e is about objective insight into your flexibility. RVO refers applicants to qualified advisors in the Netcongestie Register; an advisor who earns from the installation or supply rarely runs the numbers neutrally. Ask up front how the advisor is paid.

2. Starting the project before the application is complete

Subsidy schemes rarely cover costs already incurred. If the advisory work begins before the application has been submitted, you risk missing out on the subsidy. Apply first, then start.

3. Overlooking the measures component

Flex-e covers more than advice. Flexibility measures themselves are eligible too, at up to 40% of the cost of items including batteries, e-boilers, heat pumps with heat buffer and cold or heat buffers (subsidy €25,000 to €300,000). Solar panels and standard installations are excluded; schemes such as the EIA exist for those. A good advisor stacks schemes intelligently; see our subsidy overview.

4. A vague scope in the quotation

At final settlement you must be able to show what advisory work was done and what it cost. A quotation without clear deliverables makes it harder to account for the costs and delays payment. Keep the quotation, report and invoices together.

5. Starting too late

In congested areas the wait for a large-consumer connection can run past 2030 (see the capacity map from Netbeheer Nederland). The sooner you know which flexibility options exist (battery, ANW contract, on-site generation), the more routes stay open. The 2026 Flex-e application window closed on 15 October 2026 at 17:00. At Raben Group, an ANW contract delivered capacity within 6 months instead of a wait of 5+ years.

Why Energyc

FedEC-accredited, with a track record in flexibility

Energyc is FedEC-accredited and carries out Flex-e projects. We work only for the client, never on commission from installers, suppliers or energy companies. The initial review is free; after that you receive a quotation with a fixed price, scope and deliverables.

Our case studies show what that delivers in practice: at Metalis in Drachten, a system of 450 solar panels and a 1.2 MWh battery when the grid operator could not supply extra capacity; at Raben Group, a charging hub with four 400 kW DC chargers and a 200 kWh battery, made possible by an ANW contract; at BAT in Tilburg, thirty 400 kW chargers whose total demand stays under 600 kVA thanks to smart charging, well within the 800 kVA connection. For more on the approach, see our grid congestion page and the guide to all the routes around grid congestion; all rates are in the energy advice cost guide.

Frequently asked questions

Questions about the Flex-e scheme.

How much subsidy does the Flex-e scheme provide?

Flex-e has three components. The flexibility scan: 50% of costs, up to €10,000 in subsidy. The feasibility study: 50% of costs, with a minimum subsidy of €10,000 and a maximum of €125,000. Flexibility measures such as a battery, e-boiler or heat buffer: up to 40% of costs, with a subsidy of at least €25,000 and at most €300,000 (agricultural businesses: at most €50,000).

Who qualifies for Flex-e?

Flex-e is for businesses and institutions running into grid congestion, for example because the connection cannot be upgraded or the wait is too long. They need an electricity connection above 3x80 A and a metering contract with a metering company. The current conditions are on RVO's Flex-e page.

Which costs does Flex-e cover?

Flex-e covers three types of cost: the flexibility scan (market price €5,000–€10,000), the feasibility study (€10,000–€30,000) and flexibility measures, meaning investments in energy storage (battery, e-boiler, flywheel), energy conversion (heat pump with heat buffer, electrolysis) and cold or heat buffers. Measures must enable flexible electricity use and must not worsen grid congestion. Solar panels and standard installations are excluded; other schemes such as the EIA exist for those.

Does the advice have to come from an accredited advisor?

RVO does not make accreditation mandatory, but for the scan and the feasibility study it refers applicants to qualified advisors in the Netcongestie Register. The guiding principle is independence: a good advisor works without commission from installers or suppliers. Energyc is FedEC-accredited and carries out Flex-e projects.

How do I apply for the Flex-e subsidy?

The application has five steps: (1) choose a qualified, independent advisor, (2) request a quotation with a clear scope and price, (3) submit the subsidy application to RVO before the project starts, (4) have the advisory work or measure carried out, (5) account for the costs at final settlement. The 2026 application window ran from 6 May until 17:00 on 15 October 2026; RVO decides within 8 weeks of a complete application.

Sources & references

Sources

Free initial assessment

What could flexibility do for your connection?

In a 30–60 minute conversation we map out your connection and the issue you face and explore which route fits: a flexibility scan, a battery, smart control or a flexible contract with the grid operator. No obligation and no sales pitch.

Discuss your situation →