For municipalities and provinces — September 2026

Grid congestion: what municipalities and provinces can do, and when

A municipality cannot grant priority in the queue: the grid operator assesses that against the national prioritisation framework (VNG, the association of Dutch municipalities, 2026). What it can do is apply for transport capacity itself from 1 October 2026 for housing and educational buildings, up to 10 years ahead, through the Eerder Aanvragen (early application) route (VNG). The documents for priority and transport capacity must be submitted to the grid operator before 1 January 2027 (VNG). That route does not apply to business parks, and we found no official answer to whether plots can be released without grid capacity.

What can a municipality or province do about grid congestion?

A municipality may not make rules on generating, transporting or supplying electricity, but it does shape energy supply through the Environment and Planning Act (Omgevingswet), according to RVO (the Netherlands Enterprise Agency). What is new is Eerder Aanvragen: from 1 October 2026 the municipality itself applies for transport capacity for housing and educational buildings, up to 10 years ahead (VNG). If you want priority, submit the documents for priority and transport capacity before 1 January 2027 (VNG). Eerder Aanvragen does not apply to business parks; for those, RVO points to options including phasing and requirements attached to land sales.

From 1 October 2026

Eerder Aanvragen: the municipality applies for grid capacity itself

From 1 October 2026 municipalities can apply for transport capacity earlier in the planning process for housing and educational building projects (VNG, Eerder Aanvragen in het planproces). This is possible for specific projects up to 10 years ahead. Under this procedure, according to the VNG, the municipality submits the application; normally the developer applies for the connection. The regional grid operators Liander and Enexis confirm the procedure; Liander names project developers as well as municipalities.

Eerder Aanvragen consists of two separate applications (VNG). The first is the application for transport capacity: once that is complete, the project is in the queue. The second is the application for societal priority, with additional supporting evidence. Housing and education projects with priority fall into category 3 of the framework set by the ACM (the Dutch regulator).

Within category 3, the date determines the order. What counts is the date of the complete application for transport capacity, not that of the priority application (VNG, Voorwaarden Eerder Aanvragen). The VNG therefore considers it "worthwhile" to submit the capacity application even if not all the evidence for priority is available yet.

Priority comes with a hard deadline. According to the VNG, municipalities must submit "the documents for both a priority application and transport capacity" to the grid operator "before 1 January 2027". Enexis explains that the remaining reserved capacity becomes available step by step, in queue order. Until 1 January 2027 that capacity is available only to projects with priority (Enexis, Eerder aanvragen).

From 1 January 2027, the remaining capacity reserved for small consumers will be divided among non-prioritised applicants in the queue, in order of application date (Netbeheer Nederland, 12 December 2025).

The priority application requires an administrative declaration (bestuursverklaring) (VNG). It must come with one of these documents: a pre-planning agreement (anterieure overeenkomst), a purchase or cooperation agreement, a municipal executive or council decision, an environment plan, or subsidy or performance agreements. An additional declaration for KOVA is added if needed. The specific requirements are set out in a guide from the Ministry of the Interior, BZK (Volkshuisvesting Nederland).

KOVA stands for kleinschalige onlosmakelijk verbonden activiteiten: small-scale, inseparably linked activities such as a small neighbourhood facility on the ground floor. These can be included under the housing priority, up to a maximum of 1.3 kW of connection capacity per home for the project as a whole (VNG). A KOVA may not be an "independent commercial development or area development".

Each construction phase needs a separate application; several future phases cannot be combined (VNG and Enexis). If a project combines education, collective housing and housing, Liander asks for one application per use. Where there are several developers, the municipality can submit one application to Liander for the whole project. According to Liander, if the municipality adds the priority request, the developer does not have to upload supporting documents later.

Before submitting, the municipality adopts and publishes policy rules on the order in which it submits its projects (VNG). For this the VNG published model policy rules with an implementation manual, a Gemeentelijke Routekaart Eerder Aanvragen (municipal roadmap), a template and a connection capacity calculator. According to the VNG, the procedure "asks a lot of municipalities in a short time", but its advice is to use it.

Submissions go through Mijnaansluiting.nl, using a municipal user group set up in advance (VNG). According to Enexis, municipalities can prepare for this there from 15 September 2026 and must arrange it before 1 October. In October 2026, municipalities submit once and in a coordinated way, in time slots that each open at 09:00 (VNG and Liander).

Time slot, 09:00For projects starting construction up to and including
1 October 20262028
6 October 20262029
8 October 20262030
12 October 20262031
14 October 20262032
16 October 20262033
20 October 20262034
22 October 20262035

Source: VNG, Werkwijze Eerder Aanvragen oktober 2026, and Liander, Eerder aanvragen in het bouwproces (accessed 23 September 2026).

After the time slots, applications can be submitted on a continuous basis. The sources differ slightly on the transition. The VNG refers to continuous applications "from 23 October"; Liander and Enexis speak of coordinated submission "from 1 to 23 October 2026 inclusive". Follow the instructions of your own grid operator.

Eerder Aanvragen offers no guarantee. "Applying early does not mean that a project will get transport capacity automatically or on time," the VNG writes. Enexis: "a capacity request is no guarantee of space on the electricity grid". The procedure is intended solely for housing and educational buildings, including KOVA; business parks fall outside it (VNG).

Municipalities and sector organisations expect more than half of municipal housing projects to be delayed or not go ahead (VNG, Prioriteringskader ACM). They cite the loss of the reservation for small consumers as the cause. That is an expectation, not a measurement.

Dates and deadlines

Timeline: which date applies to what

In 2026 two arrangements run side by side: the ACM prioritisation framework and the Eerder Aanvragen procedure. The date 1 October 2026 belongs to Eerder Aanvragen, not to the prioritisation framework. The first prioritisation framework took effect on 1 October 2024 and was struck down by the CBb (the Trade and Industry Appeals Tribunal) for insufficient reasoning (Netbeheer Nederland). The current framework has different dates.

DateWhat happensSource
12 December 2025The ACM publishes the Codebesluit prioriteringsruimte transportverzoeken 2025 (case number ACM/25/194782).ACM
1 January 2026Grid operators apply the prioritisation framework in congestion areas.ACM
1 July 2026End of the implementation period for grid operators. Since then, large and small consumers have been in one integrated queue and the separate reservation for small consumers has lapsed.Netbeheer Nederland
15 September 2026Municipalities can prepare for Eerder Aanvragen in Mijnaansluiting.nl. This must be arranged before 1 October.Enexis
1 October 2026Start of Eerder Aanvragen for housing and educational buildings. The first time slot opens at 09:00.VNG, Liander, Enexis
1 October 2026, 09:00RVO opens the Onderzoek Energiehubs (EHUB) subsidy for an energy hub scan and study. You can apply until 17:00 on 1 May 2027; see our guide to the EHUB subsidy.RVO
1 to 23 October 2026 inclusiveCoordinated submission according to the grid operators' schedule.Liander, Enexis
1 January 2027Municipalities must have submitted the documents for the priority application and transport capacity before this date. From this date, the remaining capacity reserved for small consumers goes to non-prioritised applicants in the queue, in order of application date.VNG, Netbeheer Nederland
31 May 2027, 23:59Deadline for applications under the Adviesvoucherregeling Fryslân 2025–2027 (advice voucher scheme).SNN
31 October 2027End of the application period for Drenthe's Oplossingen belemmeringen door netcongestie 2.0 subsidy.Provincie Drenthe
31 December 2027The current EU procurement thresholds expire.PIANOo
1 July 2028Last day to apply for the NPG Subsidieregeling Netcongestie in Groningen.NPG
2030Target of 500 active energy hubs and final year of the Stimuleringsprogramma Energiehubs 2024–2030. The Expertpool Energie-infrastructuur runs until the end of Q4 2030. The existing implementation funding for municipalities and provinces ends.RVO, LAN, IPO and VNG

As at 23 September 2026. Full references are under Sources, at the bottom of this page.

How the queue and priority categories work for businesses is explained in our guide to the grid operator queue.

Division of roles

Who does what: municipality, province, grid operator and national government

Municipalities and provinces "may not make rules on generating, transporting or supplying electricity", RVO writes. Through the Omgevingswet they do shape energy supply in their area. An example from RVO: setting out in an environment vision where there is room for distribution substations, wind turbines or large batteries.

PartyRole according to the official documents
MunicipalityDecides how space is used. Can plan space so that supply and demand meet, reserve space for energy infrastructure, grant permits for generation, storage and infrastructure, and support businesses (RVO). Is the competent authority for grid infrastructure below 220 kV (RVO guide, table 1). Sets the preconditions, but "does not deliver the project or the connection itself" (RVO guide).
ProvinceCoordinates plans for energy infrastructure with parties in the region: integrated programming. Has a coordinating role in planning energy infrastructure, its spatial integration and combining it with other priorities such as housing and nature (RVO). Initiated the energy board, where documents including the energy vision and the pMIEK are drawn up (IPO, RVO guide).
Grid operatorConnects projects, provides system services, shares grid data where possible, flags congestion and identifies structural shortages. Applies congestion management and upgrades the grid (RVO guide). Assesses societal priority against the national framework (VNG).
National governmentSets out in the Programma Energie Hoofdstructuur which national grid infrastructure is needed towards 2050. The MIEK (multi-year programme for energy and climate infrastructure) sets out the schedule for the main energy infrastructure projects to 2035 inclusive; the Ministry of KGG (Climate Policy and Green Growth) selects the projects. MIEK projects get priority in grid operators' planning (RVO). Is the competent authority for grid infrastructure of 220 kV or higher.

Source: RVO, Hoe helpt u als provincie of gemeente netcongestie verminderen?; RVO guide of May 2025 (PDF pp. 10–15); IPO; VNG (accessed 23 September 2026). Competent-authority status can be transferred: from national government to a province or municipality, and from a municipality to a province, if the latter agrees.

The RVO guide "Rol van de gemeente bij netcongestie" (The municipality's role in grid congestion) was published in May 2025 and runs to 53 pages. The Ministry of KGG commissioned the consultancy MSG Sustainable Strategies to write it, through RVO. RVO publishes it and we cite it as an RVO publication.

The Landelijk Actieprogramma Netcongestie (LAN, the national action programme on grid congestion) is "a partnership between EZK, Netbeheer Nederland, IPO and the VNG" (VNG, LAN). The Sneller Bouwen (Building Faster) action line is explicitly about cooperation between grid operators, municipalities, provinces and national government (LAN, April 2026). Local and regional authorities have the Kenniscommunity Netcongestie (knowledge community); businesses can turn to RVO's Loket Netcongestie (help desk).

IPO and VNG wrote on 27 November 2025 that municipalities and provinces are "faced with a limited set of instruments". From 2026, provinces receive half of the implementation funding they need for national energy and climate policy. Municipalities face a shortfall averaging €400 million a year from 2026. The existing implementation funding ends in 2030 (IPO and VNG, position paper).

IPO and VNG ask national government for, among other things, "more insight into the queues" at grid operators. They also ask for it to be made possible "to reserve transport capacity for socially critical projects". Our reading: local and regional authorities do not currently have these powers.

Instruments

The tools a municipality has, and where it can find help

RVO distinguishes three main approaches: understanding the grid situation and local plans, using spatial planning to steer grid upgrades and grid integration, and supporting technical solutions. The May 2025 RVO guide lists the following instruments.

InstrumentWhat it involvesGuide
Environment and Planning Act (Omgevingswet)Steering grid integration "to serve an interest other than energy supply", where the environment vision or other policy provides a sufficient framework. The guide also mentions the experimentation provision (Article 23.3 of the Omgevingswet).PDF p. 25
Land policyReserving space for cables, substations and other grid infrastructure.PDF p. 26
Societal project selectionGiving priority in its own planning to projects of great public importance, "such as social housing or making business parks more sustainable", for example through selection criteria in tenders.PDF p. 26
Grid-aware or grid-neutral buildingEncouraging this in renovation, new build and area development.PDF p. 28
Involving the grid operator earlyAlso for housing, business parks and mobility infrastructure.PDF p. 30
Permits and spaceSimplifying permit procedures and reserving space for grid infrastructure, "for example in the layout of business parks or residential areas".PDF p. 34
One point of contactAppointing one municipal point of contact for the grid operator.PDF p. 13

Source: RVO, Rol van de gemeente bij netcongestie: handreiking met praktijkvoorbeelden voor gemeenten (May 2025), page numbers as in the PDF (accessed 23 September 2026).

This project selection concerns the municipality's own planning. The municipality does not decide the order in the grid operator's queue (VNG). RVO also advises municipalities and provinces: "Help businesses work together on flexibility through batteries, direct lines, cable pooling or an energy hub, and put sound arrangements in place."

IPO and VNG cite grid-aware building as a way for local and regional authorities to help grid operators, alongside controllable devices and energy hubs. Netbewuste Nieuwbouw (grid-aware new build) is a national pilot with municipalities, Liander and the Ministry of VRO (Housing and Spatial Planning).

For cooperation with the grid operator, the VNG names four specific steps.

StepWhat the VNG advises
1Appoint one account manager for all coordination with the grid operator, and ask the grid operator to do the same.
2Set up a regular coordination meeting.
3Proactively share information with the grid operator, such as planned housing, business park expansions, the EV charging strategy and the heat transition.
4Ask the grid operator to share planned locations for grid infrastructure, implementation schedules and dependencies.

Source: VNG, Landelijk Actieprogramma Netcongestie (LAN), updated 20 March 2026 (accessed 23 September 2026).

For a fast-track procedure for municipal energy projects of public interest, municipalities can use Article 5.55 of the Environment and Planning Act (Omgevingswet) (LAN, April 2026). According to the LAN, that instrument is "still little used by municipalities at present". A guide on it was scheduled for Q3 2026; we have not established whether it has been published.

Within the LAN, the Handreiking Buurtaanpak (neighbourhood approach guide) was completed in September 2025 and published on the Kenniscommunity Netcongestie. The coordination clause for the Modelovereenkomst transformatorhuisjes (model agreement for distribution substations) was completed in April 2025 (LAN, April 2026). In June 2023 the VNG produced a guide, Ruimtelijke inpassing van energie-infra, as a living document. A LAN study on "spatial steering" was scheduled for Q2/Q3 2026; we have not established whether that has been published either.

RVO's Expertpool Energie-infrastructuur supports municipalities and provinces with additional staff capacity and expertise in spatial planning and integration. Since 2026 this also covers complex high-voltage and medium-voltage projects. For Q1 2026 to Q4 2030 inclusive, €22.5 million is available from the Klimaatfonds (Climate Fund) (LAN, April 2026). RVO also names the Expertteam Integraal Programmeren, the Expertisecentrum GebiedsGewijs and regional liaisons per RES (Regional Energy Strategy) region, among others.

If the municipality buys in external advice, the EU threshold for supplies and services procured by local and regional authorities applies: €216,000 excluding VAT (PIANOo). That threshold applies from 1 January 2026 to 31 December 2027 inclusive. Below the threshold you do not need to run an EU procurement and can follow a national procedure. What counts is the total estimated value: similar contracts must be aggregated, and "splitting or combining contracts without good reason is not permitted".

Whether a contract below the threshold can be awarded without a public tender, and up to what amount, depends on your municipality's or province's own procurement policy. How an EU procurement of energy services works is explained on our page on EU procurement.

Societal prioritisation

Which municipal functions can get priority

Since 1 January 2026 grid operators in congestion areas have applied the ACM prioritisation framework. "Prioritising is about order, not about extra capacity," Netbeheer Nederland writes. Within a priority category, the order of submission applies. In 2025 about 5% of transport requests could be granted (Netbeheer Nederland, Stand van de Uitvoering 2025, p. 19).

CategoryWhat it covers
1. Congestion mitigators
Highest priority
Congestion mitigators do not get capacity automatically. The grid operator checks whether the solution makes a technical contribution and, if oversubscribed, selects on cost-efficiency (Netbeheer Nederland).
2. SafetyIncluding hospitals, defence, emergency response, security services, water management, electricity grids and road safety (VNG).
3. Basic needsIncluding homes, upgrades to an existing home connection, schools, public transport and gas, heat and telecoms networks (VNG). The 2025 ACM version also lists waste management and heat supply (Netbeheer Nederland).
No priorityIncluding shops, bakers and butchers, charge points, casinos, cinemas and data centres; they "come after that in the queue" (VNG).

Source: VNG, Prioriteringskader ACM voor netcapaciteit (updated 5 March 2026); Netbeheer Nederland, Stand van de Uitvoering 2025 (pp. 21–22) and Nieuwe prioriteringskader ACM (12 December 2025). Accessed 22 and 23 September 2026.

A municipality cannot assign a category. The municipal order of projects does "not itself determine what societal priority the grid operator assigns to a project", the VNG writes. The grid operator assesses this against the national prioritisation framework.

For housing, new connections and upgrades for a heat network, heat pump or electric cooking fall under category 3 (VNG, Netcongestie). "But that does not apply to a large share of SMEs and community buildings," the VNG writes. Those applications join the queue behind the prioritised applications, in order of receipt.

According to the VNG, this means municipalities cannot always comply with the statutory frameworks for delivering municipal heat programmes. The VNG advises discussing this with the grid operator.

We found nothing in primary sources on whether a sewage pumping station, sports hall, swimming pool, municipal office or recycling centre, for example, falls under a category. If in doubt, put the question to your grid operator, which assesses the application against the national framework.

What the municipality does control is when it applies. For housing and educational buildings it can bring that moment forward with Eerder Aanvragen, up to 10 years ahead (VNG). How the queue works for businesses is explained in our guide to the grid operator queue.

Business parks

Releasing plots without grid capacity: what the documents do and do not say

We found no official guidance in primary sources advising municipalities to suspend the release of plots while there is no grid capacity. Nor did we find an official answer to whether releasing plots without grid capacity is wise. The documents do offer instruments for aligning plot release with grid capacity.

RVO advises municipalities: "Phase and prioritise area development." Link the planning to available and expected grid capacity, so that projects can start on time. In RVO's example the municipality plans a business park and "reserves space for new infrastructure, such as a medium-voltage substation".

The 2023 RVO study describes steering through a tender when selling land (RVO, Ruimtelijk sturen op netinpassing). Its applicability under the Omgevingswet and the Bbl (Decree on Buildings in the Living Environment) has not been established here. The consultancy AT Osborne wrote the study for RVO; it dates from 9 June 2023, before the Omgevingswet. It is based on the Wro and the Wabo (the former planning and permitting acts) and the Bouwbesluit 2012 (Building Decree).

According to that study, tackling grid problems can form part of the selection and award criteria for the sale of public land. Selection criteria concern the bidder and may include requirements on grid problems. Award criteria on the use of the land must, according to the study, be drawn up so that a bidder can win "without offering performance beyond the statutory requirements".

The same study sets out limits. It states that the Bouwbesluit exhaustively regulates, subject to conditions, the obligation to connect to the grid: "The municipality cannot include this in a tender." In pre-planning agreements and conditions of land sale, the study says, terms covering subjects regulated by the Bouwbesluit 2012 are prohibited. Contracts based on equivalence and voluntary consent are an exception.

One example from the same study is the Chw zoning plan with extended scope (under the Crisis and Recovery Act) for Vinkenhoef in Amersfoort. The plan has open sustainability standards for the designations Bedrijf and Bedrijventerrein, worked out in a policy rule. The environmental permit requires a demonstrable contribution to sustainability, for example by using the roof for energy generation. The study also treats a subsidy scheme for project initiators as a form of spatial steering of grid integration.

According to the RVO guide, business associations are "logical partners". The municipality "can also take an active role in connecting these parties with each other and with the grid operator". In Amersfoort, park management and businesses on De Wieken-Vinkenhoef worked with the municipality and grid operator on an exploratory energy hub study using a digital twin. The guide refers here to the Programma Verduurzaming Bedrijventerreinen Nederland.

Eerder Aanvragen does not help here: the procedure applies only to housing and educational buildings (VNG). IPO and VNG wrote on 27 November 2025 that businesses in Flevoland, Gelderland and Utrecht had "not been connected for three years". They wrote: "New businesses are setting up elsewhere because there is no prospect of a connection." According to the VNG, municipalities in those provinces are preparing for a connection freeze that is looming in some regions.

Discuss the phasing of plot release with the grid operator, taking available and expected grid capacity into account (RVO). Keep an eye on the waiting time too: in congestion areas it can reach 10 years (Netbeheer Nederland). The official documents offer phasing, reserving space for grid infrastructure, requirements in land sales and energy hubs as instruments.

Note the word "gebiedsaanpak" (area approach). In LAN documents it is a way of working used by the regional grid operators on the medium-voltage grid. A contractor organises the work more efficiently area by area and more often lays several cables at once. In 2025 a total of 2,424 km of medium-voltage cable was laid, compared with 1,812 km in 2024 (LAN, April 2026).

For the low-voltage grid, the comparable method is called the buurtaanpak (neighbourhood approach), "in coordination with municipalities on choice of location, planning, limiting disruption and issuing permits". At the end of 2025 grid operators were working on grid expansion in 1,298 neighbourhoods, compared with 563 a year earlier (LAN, April 2026).

An area-based approach on a single site looks different. At IBF Heerenveen it means an area-based energy transition for 60+ businesses, with an energy hub and Liander as partner. At Azeven-Noord in Drachten it means a collective energy strategy for 17 businesses. This includes one joint supply contract with the energy supplier and a shared PV installation via cable pooling.

Provinces and energy hubs

pMIEK, provincial schemes and funding for energy hubs

The official term is provinciaal Meerjarenprogramma Infrastructuur Energie en Klimaat (provincial multi-year programme for energy and climate infrastructure), abbreviated to pMIEK (IPO). We did not come across a "PMIE" in primary sources. Every province has a pMIEK, which prioritises projects "that are necessary for the energy system of the future". In 2025 all provinces delivered a second pMIEK, partly as "input for the grid operators' investment plans" (IPO).

The pMIEK is drawn up in the energy board, each province's forum in which municipalities, grid operators and national government take part (IPO). Integrated programming is a five-step cycle repeated every two years. The next step is an implementation approach, with agreements on matters such as land acquisition or permitting.

For Fryslân we found no pMIEK document and no grid congestion page on the province's website. The province's energy page names energy infrastructure as a priority, without further detail or a scheme. In Drenthe the approach is set out in the Drents Actieprogramma Netcongestie, with an Energy Board Drenthe and a pMIEK updated every two years. Municipalities are "expressly involved" in it (Provincie Drenthe).

For energy hubs, national government set up the Stimuleringsprogramma Energiehubs 2024–2030. The working arrangements between EZK, IPO, VNG, Netbeheer Nederland and the ROMs (regional development agencies) are set out in the letter to Parliament of 5 June 2024 (RVO). The cabinet set aside €166.4 million for the programme (RVO energy hubs guide 2024, p. 4).

There are "almost 400 initiatives" for energy hubs; the target is 500 active energy hubs in 2030 (RVO). Of the programme funding, 85% is intended for "development capacity" in the regions and 15% for developing and sharing knowledge at national level.

The money channelled through the provinces is "entirely intended as 'process funding'", for example for hub coordinators and for research and advice (RVO energy hubs guide, p. 6). "The funds will not be aimed at the construction and operating phases," it also says. "An energy hub will have to arrange the funding for these costs itself."

In 2024, €23.8 million became available from the Klimaatfonds, of which €17.5 million through the provinces (€18.1 million after indexation). For 2025–2030, €142.6 million remained; choices on how to spend it "have yet to be made", the 2024 guide said. We have not established how that money is now being spent.

ProvinceShare2024 amount
Fryslân5,40%€0.9772 million
Groningen5,20%€0.9410 million
Drenthe4,20%€0.7601 million

Distribution of provincial funding for energy hubs in 2024, northern provinces. Source: RVO, Handreiking Stimuleringsprogramma Energiehubs 2024, p. 5 (accessed 23 September 2026).

Coordination lies with the province. Under its direction, the province, municipalities, grid operators and ROMs draw up an implementation agenda, including an assessment framework for allocating support (RVO). Involvement of the municipality and the regional grid operator is "indispensable in the decision-making" on allocating funds. Each province sets up an information point and help desk (RVO energy hubs guide, p. 9).

One of the criteria for supporting an initiative is: "The municipality is involved and facilitates the process." Another is co-financing for the initiation and development phases, from the municipality, province, businesses and/or other parties (RVO energy hubs guide, p. 12).

The RVO guide on the municipality's role warns: "A group contract is not a smart energy hub." According to the guide, the group contract is the end goal for grid operators. For businesses, it only counts as an energy hub when there is a cooperative within which electricity is exchanged and monitored.

In Groningen the province deploys hub coordinators; "together with municipalities they look at which business parks they can get to work on". If you want to start an energy hub, first contact your own municipality, through which the initiative reaches the province (Provincie Groningen). The municipality of Groningen has its own approach, Groningen Stroomt Door.

Drenthe works with a five-phase energy hub approach, from exploration to management, with support "on substance, process and financing" (Provincie Drenthe). The Community of Practice "Drents Net op Groen" brings businesses, municipalities, grid operators and the province together. In Emmen, ORTESE started in October 2024, with the municipality of Emmen, the province of Drenthe, Enexis and the Ministry of KGG.

In Fryslân the province and FREON studied Local4Local energy hubs (Provincie Fryslân, news item of 14 March 2024). At the time, provincial executive member Knol saw opportunities at the larger business parks of Leeuwarden, Drachten, Heerenveen and Sneek. We found no Frisian scheme specifically for grid congestion or energy hubs.

These provincial schemes in the northern Netherlands touch on grid congestion or collective solutions on business parks.

SchemeWho it applies toWhatApplications
NPG Subsidieregeling Netcongestie
Groningen
Individual businesses and businesses in a partnership in the province of Groningen.Researching and setting up (pilot) projects to tackle grid congestion on business parks. Up to €10,000 for insight into load and costs, up to €15,000 for an implementation plan and up to €250,000 for investment in a sustainable energy solution. NPG contribution: €6 million.Until 1 July 2028 inclusive, via SNN
Subsidie Oplossingen belemmeringen door netcongestie 2.0
Drenthe
Legal entities in Drenthe or partnerships of at least two independent parties.Feasibility study by an independent specialist, or implementation of a solution that reduces pressure on the grid. Budget 2026: €200,000 for feasibility and €600,000 for implementation. Conditions include: a large-consumer connection (> 3x80 A) or proof that one is needed; an individual battery and solutions using fossil fuels are excluded. Implementation requires at least 10 points on repeatability, innovation and future-proofing.1 November 2025 to 31 October 2027 inclusive
Adviesvoucherregeling Fryslân 2025–2027
Fryslân
Frisian SMEs, partnerships on business parks and local energy initiatives. Not the municipality itself.Hiring external expertise. Maximum €15,000 for making business parks more sustainable, €10,000 for local energy initiatives, and €2,500 for innovation in SMEs or for making micro and small businesses more sustainable. Subsidy rate up to 50%, or up to 60% for local energy initiatives.Until 23:59 on 31 May 2027, via SNN

Source: Nationaal Programma Groningen, Subsidieregeling Netcongestie; Provincie Drenthe, Subsidie oplossingen belemmeringen door netcongestie 2.0; SNN, Adviesvoucherregeling Fryslân 2025–2027 (all accessed 23 September 2026).

The Frisian voucher is a broad sustainability scheme: the words "netcongestie" and "energiehub" (grid congestion and energy hub) do not appear on the SNN page. On 23 September 2026, €1,671,976.10 remained, of which €602,350.00 for business parks (SNN).

From 1 October 2026, RVO's Onderzoek Energiehubs (EHUB) scheme is available for research into an energy hub. A municipality can apply as authorised representative, on behalf of an energy hub partner with a large connection or on behalf of the hub's legal entity (RVO). See our guide to the EHUB subsidy; whether a hub suits a specific site is something we discuss in Is an energy hub right for you?

What an energy hub is and how the group transport agreement works is explained in setting up an energy hub. Other schemes are on our subsidy page. You will find regional information under Friesland, Groningen and Drenthe.

Frequently asked questions

Questions from municipalities and provinces.

What can a municipality do about grid congestion?

A municipality may not make rules on generating, transporting or supplying electricity, but it can reserve space for grid infrastructure and simplify permit procedures (RVO, the Netherlands Enterprise Agency). The VNG (the association of Dutch municipalities) advises appointing one account manager for dealings with the grid operator and proactively sharing information on planned housing and business park expansions. From 1 October 2026 a municipality can itself apply for transport capacity for housing and educational buildings, up to 10 years ahead, through Eerder Aanvragen, the early application route (VNG). A municipality cannot assign a priority category; the grid operator assesses that against the national framework (VNG).

How does Eerder Aanvragen work for housing and schools?

Eerder Aanvragen (early application) lets municipalities apply for transport capacity earlier in the planning process from 1 October 2026, for specific projects up to 10 years ahead (VNG). It applies to housing and educational buildings, not to business parks; each construction phase needs a separate application. The municipality first adopts policy rules on the order of its projects and then submits in a coordinated round in October 2026, in time slots via Mijnaansluiting.nl. An application does not guarantee that a project will get capacity automatically or on time (VNG, Enexis).

What must a municipality submit before 1 January 2027 to get priority?

According to the VNG, municipalities must have submitted the documents for both a priority application and transport capacity to the grid operator before 1 January 2027. Until that date, the remaining reserved capacity at Enexis is available only to projects with priority. Priority requires an administrative declaration (bestuursverklaring) and one supporting document, such as a pre-planning agreement (anterieure overeenkomst), a council decision or an environment plan; for KOVA, an additional declaration if needed (VNG). Within category 3, the date of the complete capacity application counts, not that of the priority application (VNG).

Can a municipality release plots if there is no grid capacity?

We found no official guidance in primary sources advising municipalities to suspend the release of plots while there is no grid capacity. RVO advises linking the planning of a business park to available and expected grid capacity, and reserving space for infrastructure such as a medium-voltage substation. According to a 2023 RVO study, selection criteria in land sales may include requirements relating to grid problems; that study predates the Environment and Planning Act (Omgevingswet). Eerder Aanvragen does not apply to business parks; we have not established which legal conditions apply to releasing plots without grid capacity.

Can a province apply for grid capacity or give projects priority?

We found no route in primary sources by which a province itself applies for transport capacity or assigns a priority category. The implementation pages of VNG, Liander and Enexis on Eerder Aanvragen name municipalities as applicants, and Liander also names project developers. Provinces do have a coordinating role in planning energy infrastructure and its spatial integration (RVO). Their pMIEKs (provincial energy and climate infrastructure programmes) serve, among other things, as input for grid operators' investment plans (IPO, the association of provinces).

What subsidy does a province offer for an energy hub?

National funding for energy hubs through the provinces is process funding, not for construction or operation (RVO guide, 2024); nationally there is the EHUB scheme for studies, for which municipalities can act as authorised representative (RVO). The NPG Subsidieregeling Netcongestie offers businesses in Groningen up to €250,000 for investment in a sustainable energy solution to grid congestion on business parks (NPG). Until 31 October 2027 inclusive, Drenthe subsidises feasibility studies or the implementation of a solution that reduces pressure on the grid (Provincie Drenthe). In Fryslân the Adviesvoucher covers at most 50% of the cost of advice on business parks, up to €15,000; the word "netcongestie" (grid congestion) does not appear on the SNN page.

Does a school or other municipal building qualify for societal prioritisation?

According to the VNG, schools fall under category 3, basic needs, as do housing and public transport. For housing, new connections and upgrades for a heat network, heat pump or electric cooking also fall under category 3 (VNG). "But that does not apply to a large share of SMEs and community buildings," the VNG writes. We found nothing in primary sources on whether a sports hall, swimming pool or sewage pumping station, for example, falls under a category; the grid operator assesses that.

Does a municipality have to put energy advice out to EU tender?

For supplies and services procured by local and regional authorities, an EU threshold of €216,000 excluding VAT applies in 2026 and 2027 (PIANOo). Below the threshold you do not need to run an EU procurement and can follow a national procedure. Similar contracts must be aggregated; splitting or combining them without good reason is not permitted. Whether a contract can be awarded without a public tender depends on your municipality's or province's own procurement policy.

Free initial assessment

Preparing for Eerder Aanvragen or developing a business park?

An initial assessment is free. You tell us which projects are under way, from housing to business parks; together we discuss which route and which scheme fit.

Discuss your situation →