Practical guide, September 2026

The grid operator queue: how it works, how long it takes and how to move up

Since 1 July 2026, households and small and large businesses in congested areas have shared one queue, in order of request. To get priority, you must fall into one of the three categories set by the ACM, the Dutch regulator, and you have to earn the highest of them, congestion mitigator (congestieverzachter), with a technically demonstrable contribution to the grid. This guide explains how the queue is structured, how long it is, which deadlines legally apply and which steps do affect your position.

How long is the grid operator queue, and how do I move up?

In congested areas, the wait for grid capacity can reach 10 years (Netbeheer Nederland, the grid operators' association, 2026). Since 1 July 2026, large and small consumers have shared one queue, ordered by request date. At the end of 2025, the regional grid operators had 15,014 unique offtake requests in the queue; in 2025, about 5% of transport requests could be granted (Netbeheer Nederland, Stand van de Uitvoering 2025, p. 19). Priority is available only through the three ACM categories: apply for priority if your activity falls under safety or basic needs, or become a congestion mitigator with a battery or a contractual agreement to limit congestion that demonstrably makes room for others. Also discuss with your grid operator whether an alternative transport right (non-firm, time-block or time-duration) is possible for your request. Enexis requires a signed quotation for a place in the queue; at Stedin, your position lapses if you do not sign in time.

Since 1 July 2026

One queue, ordered by request date

As of 1 July 2026, all requests in congested areas go into one shared queue: households, small businesses and large businesses (Netbeheer Nederland, 2026). Until then, grid operators in congested areas set capacity aside for small consumers. That reservation has lapsed because of structural scarcity.

The basic rule is simple. First to apply, first in line once capacity becomes available. Parties with priority status rank above non-prioritised applicants, and within a priority category, order of submission applies again (Netbeheer Nederland, 2026). Whether you are a large or small consumer plays no part in this (RVO, the Netherlands Enterprise Agency, 2026).

What counts as the request date differs between grid operators. Enexis looks at the moment the request to increase contracted capacity was made or the quotation request was completed. Enexis requires a signed quotation for a place in the queue; a message that no capacity is available does not by itself earn you a place. Stedin uses the date on which the transport request is complete, and your position lapses if the quotation is not signed within the set period.

A transitional regime applies to pending requests. Requests made before 1 July 2026 are usually handled under the old rules and, at Liander, do not fall under the prioritisation framework; requests from 1 July 2026 go into the new queue (Enexis and Liander, 2026). The final step follows on 1 January 2027: grid operators will then reserve only limited capacity for unforeseen circumstances. From that date, the remaining capacity reserved for small consumers goes to non-prioritised parties in the queue, in order of request date (Netbeheer Nederland, 2025).

The figures

How long the queue is, and why it is growing so fast

At the end of 2025, the regional grid operators had 15,014 unique transport requests for offtake in the queue, together accounting for 9,305 MW (Netbeheer Nederland, Stand van de Uitvoering 2025). For feed-in, the figures were 8,687 requests and 5,027 MW. In 2025, about 5% of transport requests could be granted, mainly through better use of the existing grid.

Reference date (year-end)Offtake requestsCapacity requested
2022668811 MW
20236.0653,472 MW
202411.9226,739 MW
202515.0149,305 MW

Offtake queue at the regional grid operators. Source: Netbeheer Nederland, Stand van de Uitvoering 2025, p. 19 (published 2 April 2026). On TenneT's high-voltage grid there were 210 unique offtake requests (35.0 GW) and 168 feed-in requests (27.6 GW) at the end of 2025, fewer than a year earlier.

Stedin is the only grid operator that publishes a queue report with totals and figures per substation (Stedin, Wachtlijsten in congestiegebieden, status 1 September 2026). That report gives the figures as they stood around 1 July 2026.

Between 30 June and 1 September 2026, the number of offtake requests in the Stedin queue grew from 2,686 to 7,311. The capacity requested stayed virtually flat over the same period: from 1,269 MW to 1,291 MW (Stedin, status 1 September 2026).

Reference dateOfftake requestsCapacity requested
30-06-20262.6861,269 MW
08-07-20263.3311,275 MW
31-07-20265.0941,311 MW
01-09-20267.3111,291 MW

Stedin offtake queue, 2026. Source: Stedin, Wachtlijsten in congestiegebieden, status 1 September 2026. Stedin itself reports that, owing to data quality problems, 111 small-consumer requests (2.0 MW) are missing from this report. Feed-in as at 1 September 2026: 630 requests, 270 MW.

Of the 7,311 offtake requests as at 1 September 2026, 3,714 are classed as category 3 (basic needs) and 3,484 have no priority label (Stedin, status 1 September 2026). Our reading: the growth in requests at almost unchanged capacity coincides with the merging of small and large consumers into one queue on 1 July 2026. Stedin does not itself give that as the cause, and the figures say nothing about the position of an individual request.

Liander and Enexis do not publish such totals. Both refer you to their personal customer portals, Mijn Liander and Mijn Enexis, to see your own position. If you want to know how many businesses are queuing at your own grid operator, you have to make do with the national figure from the umbrella body, which dates from the end of 2025.

The prioritisation framework

Three categories, three dates

The ACM's Codebesluit prioriteringsruimte transportverzoeken 2025 (code decision on prioritising transport requests) was published on 12 December 2025 (case number ACM/25/194782). Grid operators must apply the framework in congested areas from 1 January 2026 and had until 1 July 2026 to implement it (Netbeheer Nederland, 2026). The date of 1 October you may come across in older publications is 1 October 2024: the start date of the first framework. The dates that matter now are 1 January 2026, 1 July 2026 and 1 January 2027.

Something else did start on 1 October 2026: municipalities can now request transport capacity earlier in the planning process for housing and education projects (VNG, the association of Dutch municipalities, Eerder Aanvragen). This approach does not apply to business parks. What else municipalities can do is set out in our guide on grid congestion and municipalities.

That first societal prioritisation framework did not survive. The College van Beroep voor het bedrijfsleven (CBb, the Dutch Trade and Industry Appeals Tribunal) struck it down for insufficient reasoning. The ACM then published a new version with fuller reasoning, open for consultation from 26 June 2025 and in force from 1 January 2026 (Netbeheer Nederland, 2025).

CategoryWho qualifiesWhat is expected of you
1. Congestion mitigators
Highest priority
Customers that reduce grid congestion and so make room for other customers. Liander's examples: large businesses with batteries or gas generators. Applies to both consumption and feed-in.Contractual agreements on limiting congestion, a solution that demonstrably reduces congestion in technical terms, and an assessment by the grid operator. Not granted automatically.
2. SafetyEmergency services, police, defence, security services, justice, water management and acute healthcare. The 2025 ACM version also covers electricity infrastructure, healthcare, drinking water supply, telecoms for safety networks, road safety, aviation, rail, waterways and roads.Apply to the grid operator for priority yourself and show that your activity falls under the category. Liander responds within 20 working days.
3. Basic needsEducation, heat supply, gas networks and future housing projects. The 2025 ACM version also covers waste management, public transport, telecoms and housing.Submit your own application. Liander automatically assigns category 3 to residential addresses with a connection of up to and including 3 x 35 A, via the BAG register (the national address and building register).
No categoryApplicants who have not been granted priority.No priority based on these categories; the transport request is still required. Handled in order of request; from 1 January 2027 this also applies to the remaining small-consumer reserve.

Source: Netbeheer Nederland, Stand van de Uitvoering 2025 (p. 22) and Nieuwe prioriteringskader ACM (12 December 2025); Liander, Prioriteit voor aanvragen op de wachtlijst and Maatschappelijk prioriteren (accessed 22 September 2026).

Priority determines order, not capacity. "Prioritisation is about order, not about extra capacity", writes Netbeheer Nederland. At the end of 2025, the queue held 448 requests in category 1, 454 in category 2 and 327 in category 3, compared with 316, 290 and 133 a year earlier (old framework). Netbeheer Nederland expects this number to keep rising in the coming years.

Check whether your activity falls under safety or basic needs; the list in the table is your starting point. For category 1, your solution must meet the conditions for mitigating congestion. At Enexis, a customer with a connection above 3 x 80 A applies for priority themselves, through a personal link sent once the quotation has been signed; this is possible only after you are in the queue for transport capacity (Enexis, Maatschappelijk prioriteren).

Category 1

Becoming a congestion mitigator: priority, no guarantee

According to Enexis, a congestion mitigator is a party whose allocation of transport capacity results in more capacity being available to other parties, and not in more congestion on another grid operator's network. Liander gives the example of large businesses that make room with batteries or gas generators. The category covers both consumption and feed-in and requires contractual agreements on limiting congestion, coordinated with other grid operators where necessary (Liander, 2026).

The grid operator assesses this in two steps. First, whether the request meets the conditions; then, whether the proposed solution can actually help reduce congestion in technical terms (Netbeheer Nederland, 2026). Enexis also judges for itself whether the contract delivers enough extra transport capacity for other customers, through organic growth or extra customers from the queue, and whether the financial compensation is acceptable.

Being granted the status does not automatically bring capacity. "However, this does not mean that congestion mitigators automatically receive transport capacity", writes Netbeheer Nederland (Stand van de Uitvoering 2025, p. 21). If there are more congestion mitigators in the queue than are needed to resolve the bottleneck, the grid operator selects the most efficient solutions, for example on cost-efficiency grounds. Only once all agreements are in place and the congestion mitigator can actually be deployed does it leave the queue.

The status gives priority, not extra capacity. Whether the financial compensation is acceptable is something Enexis assesses contract by contract (Enexis, Maatschappelijk prioriteren). A battery that only flattens your own profile without making room for others does not meet the condition that capacity is created for other parties. If there are too many candidates, the grid operator selects the most efficient solutions (Netbeheer Nederland, Stand van de Uitvoering 2025, p. 21).

If you are seriously considering category 1, start with what the bottleneck in your grid area needs, not with your own battery. How a battery or a capacity restriction contract is set up in practice is explained in solving grid congestion: all the options.

Connection deadlines

Which deadline legally applies, and which no longer does

For a large electricity connection (above 3 x 80 A), the connection deadline is 26 weeks, 52 weeks or a reasonable period set by the grid operator, depending on the complexity of the work (ACM, code decision of 25 March 2024). On top of that, the grid operator may set an extra waiting time per quarter and per region based on its backlog of work. This extra waiting time is capped at 40 weeks, and that maximum will be phased out over the next ten years.

ConnectionDeadlinePlusIf congested
Large consumer, low complexity26 weeksregional waiting time, up to 40 weeksdeadline does not apply; ACM: 3 months after congestion is lifted; Liander and Enexis: 13 weeks, each with its own conditions
Large consumer, medium complexity52 weeksregional waiting time, up to 40 weeksas above
Large consumer, high complexitybespoke, at Enexis often more than 52 weeksregional waiting time, up to 40 weeksas above
Small consumer (up to 3 x 80 A)ACM deadlines of 2023 (18 weeks new, 12 weeks modification) annulled by the CBb on 17 September 2024; new code decision in preparationn/asee note below the table

Source: ACM, Codebesluit aansluittermijnen grote aansluitingen elektriciteit (18 April 2024); ACM, Uitspraak CBb aansluittermijnen huishoudens (17 September 2024); Liander and Enexis, aansluittermijnen grootzakelijk; Netbeheer Nederland, Stand van de Uitvoering 2025, p. 16 (accessed 22 September 2026).

Average small-consumer lead times in practice in 2025: 45 weeks for a new connection and 21 weeks for a modified connection (Netbeheer Nederland, Stand van de Uitvoering 2025, p. 16). These are national averages, not a deadline for congested areas.

Where there is congestion, the connection deadline does not apply. The ACM gives 3 months after the congestion is lifted (ACM, code decision 18 April 2024). Liander and Enexis give 13 weeks, each with its own conditions. Other exceptions in the code decision are force majeure and agreements between the parties on later completion.

Liander has applied these deadlines since 1 January 2025; anyone who received an offer before that date still falls under the old deadlines. If the expected date for resolving the congestion is less than two years away, Liander looks at the complexity of the construction work. If that construction period is longer than the resolution date plus 13 weeks, the longer period applies (Liander, Aansluittermijnen grootzakelijk).

Enexis counts the 13 weeks from the moment transport capacity becomes available to the customer, "unless there is force majeure" (Enexis, Oplevertermijnen elektriciteitsaansluitingen). After you accept the quotation, Enexis emails you within 5 weeks with the latest date on which the connection will be completed.

Small-consumer connections (up to and including 3 x 80 A) are a different matter. In 2023 the ACM decided that a new small-consumer connection must be completed within 18 weeks at most, a modification within 12 weeks and, in congested areas, within 1 year at most, provided enough transport capacity is available (ACM, 9 June 2023). The CBb annulled those deadlines on 17 September 2024 because the ACM had not sufficiently investigated the facts and circumstances. The ruling is final and cannot be appealed (ACM, 17 September 2024).

Netbeheer Nederland reported in April 2026 that the grid operators are working with the ACM on a new code decision for small-consumer connection deadlines (Stand van de Uitvoering 2025, p. 16). The actual 2025 averages are given beneath the table.

Regional

Waiting time by region: Enexis publishes, Liander does not

Every quarter, Enexis sets the regional waiting time by regional office, based on the amount of work already scheduled, and publishes the table. This waiting time comes on top of the 26- or 52-week complexity deadline. The values below apply to the third quarter of 2026.

Enexis regional officeRegional waiting time, Q3 2026Selected municipalities
Groningen38 weeksEemsdelta, Groningen, Het Hogeland, Midden-Groningen, Oldambt, Pekela, Stadskanaal, Veendam, Westerkwartier, Westerwolde
Drenthe36 weeksAssen, Coevorden, Emmen, Hoogeveen, Meppel, Midden-Drenthe, Noordenveld, Tynaarlo
Overijssel-Oost27 weeksAlmelo, Enschede, Hardenberg, Hengelo
Overijssel-West17 weeksZwolle, Deventer, Kampen, Steenwijkerland
Brabant-Noordoost20 weeks
Brabant-Zuidoost22 weeks
Brabant-West38 weeks
Brabant-Midden38 weeks
Limburg-Noord37 weeks
Limburg-Zuid26 weeks

Source: Enexis, Wachttijd per vestiging 3e kwartaal 2026 (accessed 22 September 2026). The waiting time applies on top of the 26- or 52-week complexity deadline and only if transport capacity is available.

For Groningen, two published periods apply: 26 weeks for a low-complexity connection (Enexis) plus 38 weeks of regional waiting time in the third quarter of 2026 (Enexis). Added together, that is 64 weeks; the sum is ours, as Enexis does not publish the total. The deadline applies only if transport capacity is available. Where there is congestion, it does not apply, and according to Enexis the wait can then reach as much as 10 years. For a new gas connection or modification, Enexis currently gives an average waiting time of 1 to 2 years.

Liander, the grid operator for Friesland, also sets an extra waiting time per quarter and per region, but does not publish the table on its page about connection deadlines. The value for Friesland that we found appears in an illustrative worked example from Liander: 40 weeks of regional waiting time, bringing a low-complexity connection to 66 weeks. Liander states explicitly that the example is purely illustrative and confers no rights. We have not found a published current quarterly value for Friesland (Liander, Aansluittermijnen grootzakelijk, accessed 22 September 2026).

What is certain for the Liander area: for large business connections requested before 1 January 2025, the average lead time was almost 2 years, and Liander expects longer lead times to continue for "a few more years". Liander is laying more than 3,000 kilometres of electricity cable in Friesland and installing or renewing more than 400 distribution substations. None of this tells you when an individual request will reach the front of the queue.

The map is shifting. In August 2026, Liander reported two new feed-in bottlenecks in Friesland, at Schenkenschans substation (10-1i and 10-2i), while at Sumatrastraat substation (10-1i) limited consumption capacity became available through an adjustment of policy limits. In July 2026, Enexis reported new bottlenecks at Vierverlaten (offtake) and Veendam (feed-in) in Groningen; Meppel substation in Drenthe remains in phase 2 with congestion management. Customers stay in the existing queues throughout.

What you can do

Six steps that do affect your position

The grid operator sets the order, but some of the variables are within your control. The steps below help you assess your request and your options, and show the result of each.

1. Check capacity and apply early. Netbeheer Nederland advises checking the available capacity by postcode on the capacity map or grid checker (stroomnetchecker), and applying as early as possible. Result: an earlier request date. Without priority, that date alone determines your place.

2. Complete your request and sign the quotation. Enexis requires a signed quotation for a place in the queue; at Stedin, your position lapses if the quotation is not signed within the set period (Enexis and Stedin, Wachtlijst voor transportcapaciteit). Result: with these grid operators, a definitive queue position. Ask your own grid operator which condition it applies.

3. Apply for priority if your activity falls into category 2 or 3. Apply to your own grid operator; Liander responds within 20 working days. Result: if priority is granted, a place ahead of non-prioritised requests; within the category, order of submission applies.

4. Become a congestion mitigator. With a battery, generator or contractual agreement to limit congestion that demonstrably makes room for others. Result: if granted, category 1, the highest priority. It is not automatic: the grid operator assesses the technical contribution and the compensation and, if there are too many candidates, selects the most efficient solutions (see the section above).

5. Ask about an alternative transport right. For connections above 3 x 80 A, there are four contract types: the standard connection and transport agreement (ATO, with a 24/7 transport right), the non-firm ATO on residual capacity with no guarantee, the time-block contract (full transport right within fixed time blocks, zero outside them) and the time-duration transport right (TDTR: full transport right for an agreed number of hours per year). In return for this flexibility, you get a discount on the transport tariff (Netbeheer Nederland, 2024). Discuss with your grid operator whether one of these types is possible for your request; the non-firm ATO uses residual capacity with no guarantee.

TenneT shows that this works. Using measures that include the time-duration transport right, TenneT offered contracts to almost 50 customers, 20 of which have been signed. Partly as a result, about half of the requests in the TenneT queue at the end of 2024 were granted or cancelled in 2025 (Netbeheer Nederland, Stand van de Uitvoering 2025).

6. Save energy and shift consumption away from the peak. Grid operators explicitly name this as something parties in the queue can do (Netbeheer Nederland, Zo werkt het: de wachtlijst, 5 June 2026). Result: a lower peak on your own connection. Discuss with your grid operator whether that profile suits an alternative transport right.

Waiting is not the only route. Raben Group obtained the connection for a 400 kW DC logistics charging hub within 6 months instead of 5+ years; the hub has been operational since Q4 2024 and charges 8 electric trucks. Metalis in Drachten combines 450 solar panels, a 1.2 MWh battery and a capacity restriction contract (CBC-T) with Liander, and went from 67 to 0 tonnes of CO2 a year (scope 1, natural gas). The contract type and technology required are set out in solving grid congestion: all the options.

Frequently asked questions

Questions about the queue.

How long is the Liander queue for a large-consumer connection?

Liander sets the regional waiting time every quarter but does not publish it, nor any queue figures. What Liander does state: for large business connections (above 3 x 80 A) requested before 1 January 2025, the average lead time was almost 2 years, and it expects longer lead times to continue for a few more years. In congested areas, the wait can reach 10 years, according to Netbeheer Nederland (the grid operators' association), because the grid has to be expanded first. The 40-week regional waiting time for Friesland shown on the Liander website is an illustrative worked example that, Liander says, confers no rights. You can see your own position in Mijn Liander.

How has the grid operator queue worked since 1 July 2026?

Since 1 July 2026, all requests in congested areas have been in one shared queue (households, small businesses and large businesses), and the capacity reservation for small consumers has ended. Requests are handled in the order received: the first to apply is first in line once capacity becomes available. Parties with priority status under the framework of the ACM (the Dutch regulator) rank higher; within a category, order of submission applies again. Requests made before 1 July 2026 are usually handled under the old rules. From 1 January 2027, the remaining small-consumer reserve will be allocated to non-prioritised parties in the queue, in order of request date.

What is societal prioritisation and who qualifies?

Societal prioritisation (maatschappelijk prioriteren) is the ACM framework under which grid operators in congested areas give certain applicants priority in the queue. It has applied since 1 January 2026 and has three categories: 1) congestion mitigators (congestieverzachters), parties that reduce grid congestion and so make room for others; 2) safety, such as emergency services, police, defence, justice, water management and acute healthcare; 3) basic needs, such as education, heat supply, gas networks and future housing construction. Priority creates no extra capacity, only a different order. Check whether your activity falls under safety or basic needs; for category 1, your solution must meet the conditions for mitigating congestion.

How do I become a congestion mitigator with Liander or Enexis?

A congestion mitigator is a party whose allocation of transport capacity results in more capacity being available to other parties, without extra congestion on another grid operator's network. Examples are a battery or generator backed by contractual agreements to limit congestion. The category covers both consumption and feed-in. The grid operator assesses this in two steps: first whether the request meets the conditions, then whether the solution actually reduces congestion in technical terms. At Enexis, you apply for priority yourself through a personal link sent once the quotation has been signed, and only after you are in the queue. Enexis assesses whether the contract delivers enough extra transport capacity and whether the financial compensation is acceptable.

Does a congestion mitigator automatically get a connection or compensation?

No. Netbeheer Nederland states in so many words that congestion mitigators do not automatically receive transport capacity. If there are more congestion mitigators in the queue than are needed to resolve the bottleneck, the grid operator selects the most efficient solutions, for example on cost-efficiency grounds. Only once all agreements are in place and the congestion mitigator can actually be deployed does it leave the queue. On compensation, Enexis says only that it assesses whether the financial compensation in the contract is acceptable; the status itself gives priority, not extra capacity.

What is the legal deadline for a large-consumer connection?

For a connection above 3 x 80 A, the ACM code decision of 2024 sets a deadline of 26 weeks (low complexity), 52 weeks (medium complexity) or a reasonable period set by the grid operator (high complexity). On top of that, the grid operator may set an extra waiting time per quarter and per region of up to 40 weeks; that maximum will be phased out over the next ten years. Enexis publishes this regional waiting time by regional office: in the third quarter of 2026, for example, 38 weeks for Groningen and 36 weeks for Drenthe. Where there is congestion, the connection deadline does not apply: the ACM gives 3 months after the congestion is lifted, while Liander and Enexis give 13 weeks with their own conditions (Enexis counts from the moment transport capacity becomes available and allows for force majeure).

Does the 18-week deadline still apply to a small-consumer connection?

No. In 2023 the ACM decided that a new small-consumer connection must be completed within 18 weeks at most, a modification within 12 weeks and, in congested areas, within 1 year at most, provided there is enough transport capacity. The College van Beroep voor het bedrijfsleven (CBb, the Dutch Trade and Industry Appeals Tribunal) annulled those deadlines on 17 September 2024 because the ACM had not investigated sufficiently; the ruling is final. Netbeheer Nederland reported in April 2026 that the grid operators and the ACM are working on a new code decision. In practice, a new small-consumer connection took an average of 45 weeks in 2025 and a modified one 21 weeks (Netbeheer Nederland, Stand van de Uitvoering 2025, p. 16).

What can I do if I don't want to wait years for grid capacity?

First, complete your request and sign the quotation: Enexis requires a signed quotation for a place in the queue, and at Stedin your position lapses if you do not sign in time. Then apply for priority if your activity falls under safety or basic needs, or become a congestion mitigator with a battery or a contractual agreement to limit congestion that demonstrably makes room for others. Discuss with your grid operator whether an alternative transport right (non-firm ATO, or a time-block or time-duration contract, with a discount on the transport tariff) is possible for your request, and reduce your own peak by saving energy and shifting load. Raben Group obtained the connection for a 400 kW DC charging hub within 6 months instead of 5+ years; Metalis uses 450 solar panels, a 1.2 MWh battery and a capacity restriction contract (CBC-T) with Liander.

Free initial assessment

Want to know where you stand in the queue, and whether you can get out of it?

An initial assessment is free and without obligation. You tell us about your grid situation and the status of your request; we assess whether priority, a congestion mitigator contract or an alternative transport right stands a good chance in your case, and what that requires of your installation.