Practical guide, September 2026

Peak demand and contracted capacity: what happens when you exceed it, and how to lower the peak

The Systeemcode elektriciteit 2026 (the Dutch electricity system code) governs how contracted transport capacity (GTV) is adjusted after an overrun. We found no penalty amount or separate overrun tariff at Liander, Enexis or Stedin. At medium voltage (MV, Dutch MS) and medium-to-low voltage (MV/LV, Dutch MS/LS) transformer level, the offtake GTV goes up after an overrun, except in a congestion area for offtake, where the consequences differ by grid operator. A lower monthly peak feeds straight through to the kWmax charge, which at Liander on medium voltage is €3.57 per kW per month.

What happens if I exceed my contracted capacity?

Outside a congestion area for offtake, your contracted offtake capacity at medium voltage and MV/LV transformer level rises to the overrun level, with effect from that month. In a congestion area for offtake it does not go up: Liander asks for measures within four weeks, and Enexis mentions disconnection or legal action as a last resort. You can request a reduction, but no sooner than twelve months after the last increase unless you have reasonable grounds (Systeemcode elektriciteit 2026, art. 7.26). The reduction takes effect no earlier than the first day of the calendar month after your request.

Outside congestion areas

Outside congestion areas your GTV can go up.

Contracted transport capacity (GTV) is the maximum capacity you may use on your connection, set separately for offtake and feed-in (Begrippencode elektriciteit 2026, the electricity definitions code). For a large connection, you and the grid operator record it in the connection and transport agreement (Systeemcode elektriciteit 2026, art. 7.24(2)). What happens after an overrun is set out in § 7.4 of the same Systeemcode. The word "boete" (penalty) does not appear in those provisions.

For medium voltage and MV/LV transformer level, the rule is simple. After an overrun, the offtake GTV is adjusted to the value of the overrun (art. 7.26(1)). That new value applies from the first day of the calendar month in which the overrun occurs. It comes back down at your request, no sooner than twelve months after that increase (para. 2).

An earlier reduction is possible on reasonable grounds, for example if circumstances have changed substantially in a way you could not reasonably have foreseen (para. 4). The grid operator can ask you to substantiate this further. Offtake is measured per quarter-hour (ACM, 2024). On our reading, one quarter-hour above your GTV can therefore mean a full year of higher kW contract costs.

Worked example: our calculation using Liander's 2026 tariff, excluding VAT. A company at medium voltage has a GTV of 500 kW and is outside a congestion area for offtake. In March its offtake reaches 600 kW for one quarter-hour, and the GTV becomes 600 kW from 1 March. The higher GTV then stays in place for at least twelve months, which costs an extra 100 × €2.29 × 12 = €2,748 in kW contract charges.

That amount assumes a tariff of €2.29 per kW per month, held constant for twelve months for the purposes of this calculation. It is not a forecast of next year's tariff. Other assumptions: the connection stays in the same MV tariff category and the company requests the reduction in time. It has no reasonable grounds to reduce sooner and does not exceed the limit again.

The timing works differently at the highest grid levels. At extra-high voltage (EHV, Dutch EHS), high voltage (HV, Dutch HS), intermediate voltage (IV, Dutch TS) and HV+IV/MV transformer level, the new value after an overrun in normal operating conditions applies to the entire calendar year (art. 7.25). On our reading, the higher value therefore also counts for the months before the overrun. There you can request an adjustment at most once a year, on reasonable grounds (art. 7.25(3)).

Enexis writes that you will see an overrun on your invoice. We found no penalty amount or separate tariff for exceeding the GTV at Liander, Enexis or Stedin. What you pay extra outside a congestion area for offtake is, on our reading, the normal kW contract tariff on a higher GTV.

The automatic adjustment applies to offtake GTV at medium voltage and MV/LV transformer level (art. 7.26) and at EHV, HV, IV and HV+IV/MV transformer level (art. 7.25). For low voltage above 3x80 A, check the rule with your grid operator.

Systeemcode elektriciteit 2026, § 7.4, version of 9 July 2026. Stedin's tariff documents still refer to the old Netcode elektriciteit (art. 2.27 and 9.9); the provisions now in force are in the Systeemcode.

In congestion areas

In a congestion area your contracted capacity does not go up.

On 24 April 2025 ACM (the Dutch regulator), on a proposal from Netbeheer Nederland (the grid operators' association), decided that connected parties in congestion areas can no longer adjust their GTV by exceeding it. Anyone wanting more transport rights has to apply. ACM's stated reason is equal treatment of current and future connected parties within a congestion area.

In the Systeemcode this is set out in art. 7.25(4) and 7.26(5). In those areas an upward adjustment is not permitted, either automatically or on request. What matters is congestion in the same direction of energy flow: for offtake GTV, what counts is whether your connection is in a congestion area for offtake. According to Liander, such restrictions apply in most parts of its service area.

According to Liander, an overrun can endanger the safety and reliability of the grid. A fault can then leave you and other customers in the region without electricity for an extended period. What happens after an overrun in a congestion area differs by grid operator.

Grid operatorWhat grid operators themselves publish about overruns in a congestion area
LianderLiander notifies you of the overrun and asks you to take measures within four weeks to prevent further overruns. If you exceed the limit again after that, you are in default and Liander must take measures; the page does not say which. If that further overrun causes damage, you are liable.
EnexisYou receive an email and a phone call asking you to adjust your consumption or feed-in. If you keep exceeding the GTV, there can be consequences. As a last resort Enexis can disconnect you or take legal action.
StedinOfftake GTV is not adjusted after an overrun. Existing customers with a connection above 3x80 A can no longer grow within their connection capacity. Stedin stresses the importance of not exceeding the GTV. We found nothing on its public congestion pages about the consequences Stedin attaches to an overrun.

Liander, Overschrijding van uw gecontracteerde transportvermogen; Enexis, Overschrijden gecontracteerd transportvermogen; Stedin, congestion pages for offtake (including Zuid-Holland and Zeeland). All accessed on 23 September 2026. Liander adds that this approach only applies in an area with a transport restriction or congestion.

So in a congestion area there is no increase in contracted capacity to "solve" the overrun. If you have a different grid operator, ask which rules apply there.

GTV is also distinct from connection capacity: it is equal to or lower than that capacity (Begrippencode elektriciteit 2026). Stedin has a separate rule for exceeding connection capacity. Stedin may charge for that overrun under the Tarievencode (Tarieven- en vergoedingsregeling 2026, art. 4(14)). If it occurs in two or more consecutive consumption months despite measures being taken, Stedin can suspend the connection.

Grid tariffs 2026

What a kilowatt of peak costs: kW contract and kWmax by grid operator.

At medium voltage you pay for capacity through two tariff components. The kW contract tariff applies to your GTV, the kWmax tariff to the highest value measured per month (ACM, 2024). The Tarievencode elektriciteit 2026 (the electricity tariff code) divides the costs there between contracted kW (25%), kW max per month (25%) and kWh (50%) (art. 3.10). Under a connection and transport agreement with a variable transport right, the contracted kW component falls away (art. 3.14).

Other grid levels have a different split. Low voltage above 3x80 A has no kWmax: there 16% goes to contracted kW and 84% to kWh (art. 3.11). At MV/LV transformer level, the kW contract tariff is that of medium voltage plus a surcharge for the transformer; kWmax and kWh are the same (art. 3.10). At IV and HV+IV/MV transformer level it is 50/50 between contracted kW and kW max; at EHV and HV that kW max is weighted (art. 3.9).

At medium voltage, kWmax is your highest load of the month. With a metering period of 15 minutes or less, the Begrippencode elektriciteit 2026 determines it from the value per clock quarter-hour. With any other metering period, the highest value per metering period applies. Stedin describes it as the average load over 15 minutes, unless otherwise agreed with Stedin.

So each month has its own kWmax. How long a peak counts for makes a difference. A high peak in one month costs you kWmax for that month only. If the same peak exceeds your GTV, then outside a congestion area it also counts towards the kW contract, as a rule for twelve months (our reading).

The amounts and category boundaries differ by grid operator.

Grid operatorCategory (GTV)kW contractkWmax, per kW per month
LianderMV/LV (> 50 to 136 kW)€3.74 per kW per month€ 3,57
LianderMV (> 136 to 2,000 kW)€2.29 per kW per month€ 3,57
EnexisMV/LV (> 50 to 125 kW)€49.26 per kW per year (≈ €4.11 per month)€ 3,66
EnexisMV-D (> 125 to 1,500 kW; also > 1,500 kW with the MV distribution connection type)€28.91 per kW per year (≈ €2.41 per month)€ 3,66
StedinMV/LV transformer (51 to 150 kW)€3.9308 per kW per month€ 3,0966
StedinMV (151 to 1,500 kW)€2.0228 per kW per month€ 3,0966

2026 large-consumer tariff sheets from Liander (version 2026.1.1), Enexis (version 1.0) and Stedin (table 3), excluding VAT. Enexis's kW contract is an annual amount (ACM tariff sheet for Enexis 2026); the monthly amounts in brackets are our conversion. Above 1,500 kW, Enexis and Stedin have separate categories for an operating time of no more than 600 hours a year, with a kW max per week. Operating time is annual consumption divided by the maximum capacity drawn per year (Tarievencode, art. 3.9).

In the MV categories (Liander MV, Enexis MV-D, Stedin MV), the kWmax tariff at all three is higher than the monthly kW contract tariff. At MV/LV it is the other way round: a contracted kW per month costs more than a kW of monthly peak. Both observations come from our own comparison of the tariffs above.

Worked example (our calculation, not a published figure). Suppose the monthly peak at medium voltage is 100 kW lower for twelve months, with the GTV unchanged.

Grid operator (category)kWmax tariff 2026kWmax difference per year
Liander (MV)€3.57 per kW per month100 × €3.57 × 12 = €4,284
Enexis (MV-D)€3.66 per kW per month100 × €3.66 × 12 = €4,392
Stedin (MV)€3.0966 per kW per month100 × €3.0966 × 12 = €3,715.92

Our calculation, on these assumptions: 2026 tariffs excluding VAT, a monthly peak that is 100 kW lower in every month of the year, and an unchanged GTV. The kW contract only falls if the GTV is reduced as well; the section on reductions below covers that.

Reactive power

Reactive power: a separate tariff, only outside the limits.

Besides active power in kW, an installation also exchanges reactive power with the grid. The Systeemcode elektriciteit 2026 requires the power factor (cos φ) at the connection point to lie between 0.85 (inductive) and 1.0 (art. 2.19). The exceptions are further contractual arrangements on reactive power, brief deviations and periods of very low load.

If the reactive energy exchanged exceeds the amount corresponding to a power factor of 0.85 inductive or 1.0 capacitive, a reactive energy tariff per kvarh applies (Tarievencode, art. 3.17). Reactive energy you exchange at the grid operator's request falls outside this. The amounts for 2026 vary.

Grid operatorReactive energy tariff 2026, per kvarh
Liander€0.0000 for MV/LV, MV, IV/MV-HV/MV and IV; no tariff for LV
Enexis€0.0184 for MV and above; €0.0188 for LV above 3x80 A according to its own tariff sheet (the ACM tariff sheet gives €0.0184 for below MV)
Stedin€0.0169 for all categories

2026 large-consumer tariff sheets from Liander, Enexis and Stedin, and the ACM tariff sheet for Enexis 2026. Excluding VAT, accessed on 23 September 2026.

Stedin also takes the power factor into account at the boundary between your GTV and your connection capacity. The usual value there is 0.85 for offtake and 1.00 for feed-in (Tarieven- en vergoedingsregeling 2026, art. 5(7)).

What is coming

Time-dependent tariffs: in place at TenneT, a proposal for regional grids.

On the high-voltage grid, the time of use already counts. On 19 July 2024 ACM published the final code decision on time-based transport tariffs for high-voltage grids, which according to ACM works "as a form of peak-time charging". Parties connected to the transmission system have had those tariffs since 1 January 2025 (Netbeheer Nederland, 2026).

In the Tarievencode 2026 this is the weighted kW max, for EHV and HV (art. 3.9(5)). Each quarter-hourly value is multiplied by a weighting factor that is higher at times of peak demand and lower at times of low load. The highest value in that series counts.

For large consumers on the regional grids there is a proposal, not a decision. Netbeheer Nederland submitted the proposal on 13 March 2026. ACM published it for comment on 19 March 2026 (case ACM/26/200254).

In a letter to Parliament dated 10 June 2026, ACM wrote that the proposal is under consideration. As of 23 September 2026 we found no draft or final decision on acm.nl.

The proposal applies to connections above 3x80 A in the IV, HV+IV/MV transformer, MV and MV/LV transformer categories. There the kW max would become a weighted kW max, with a weighted kWh component added. There would be five levels of weighting factor, set per month for each hour of the day and the same at all locations (NBNL proposal, § 6).

The GTV would not change. Under the proposal it would stay based on the measured load, without weighting, and your maximum permitted offtake would remain equal to the GTV (p. 5). That would also apply at times with a weighting factor below 1.0. So under the proposal, the timing of your peak would count as well as its height.

The grid operators are asking ACM to bring the decision into force on the first 1 January once 18 months have passed since the final code decision. At the Gebruikersplatform (user platform) of 12 February 2026, the chair concluded that 1 January 2028 may be achievable if ACM decides before the summer. Stedin said that otherwise it would be 1 January 2029. So no start date has been set.

Reducing the GTV

You can reduce it, but in a congestion area you will not easily get the capacity back.

A lower GTV reduces what you pay in kW contract charges. At Liander in the MV category, 100 kW less GTV saves 100 × €2.29 × 12 = €2,748 a year (our calculation, 2026 tariff sheet). Assumptions: the GTV is 100 kW lower for twelve months and the connection stays in the same MV tariff category. We hold the 2026 tariff (excluding VAT) constant for twelve months and are not forecasting next year's tariff.

At medium voltage and MV/LV transformer level, a reduction takes effect at the earliest on the first day of the calendar month after your request. Even then it cannot be sooner than twelve months after the last increase, unless you have reasonable grounds (Systeemcode elektriciteit 2026, art. 7.26(2) and (4)). If you exceed the reduced value within twelve months of your request, the GTV rises to that overrun level. This applies retroactively from the first day of the month in which the reduction took place (para. 3).

At EHV, HV, IV and HV+IV/MV transformer level, you can request an adjustment at most once a year, on reasonable grounds (art. 7.25(3)). At Stedin, the GTV declaration and the choice between Normaal and Reserve for the HV+IV/MV transformer and IV categories must be received in writing by 30 November at the latest for the following calendar year; otherwise Stedin sets the GTV itself and classifies you as Normaal (Tarieven- en vergoedingsregeling, art. 5). Reserve is Stedin's category for an operating time of up to 600 hours.

As a rule, Liander only reduces the GTV if it has not been adjusted upwards in the past 12 months (2026 tariff sheet). Enexis refers to Mijn Enexis Grootzakelijk for the conditions, and invites customers with long-unused GTV and no plans for it to reduce it. Stedin handles a change within connection capacity by email; above that it goes through an upgrade quotation on mijnaansluiting.nl.

In a congestion area a reduction is hard to reverse. An upward adjustment is not permitted there, not even the retroactive adjustment under para. 3 (art. 7.26(5)). Anyone who wants more later has to make a new application: at Liander it is first come, first served, while Stedin uses a queue. Enexis warns that an increase there can "sometimes take up to 10 years".

In a congestion area there is also a limit to leaving capacity unused: "use it in time or lose it" (GOTORK). The grid operator can reduce your GTV if at medium voltage you used no more than 50% of it in the preceding twelve months. It can also do so if 1 MW or more is unused, provided in either case that the unused portion will not be used within a reasonable period (art. 7.29(1)). The same limits apply for HV below 110 kV; for the transmission system, 50% or 10 MW.

The procedure starts with written notice, after which you have two months to consult the grid operator. A report of that consultation follows within 10 working days, and you can respond to it within 10 working days. The new GTV becomes the highest kWmax of the preceding 24 months, or higher if you can make a plausible case from forecasts (paras. 3 and 4). In November 2024 Enexis reported that it had started doing this on a small scale.

If you exceed the lower value after a reduction, in a congestion area that is an ordinary overrun (our reading). So do not base a reduction on one quiet year. Look at your highest quarter-hour per month over 24 months and at your growth plans. Then discuss with your grid operator what a reduction means for your position.

Lower the peak

Lowering the peak starts with your quarter-hourly data.

Enexis recommends quarter-hourly data as the first step: your metering company can supply your metering data per quarter-hour. According to Enexis, this shows you exactly when you consume or feed in (too) much. Compare the highest quarter-hours per month with your operations: which machines or chargers were running at that moment? Look back 24 months, as that is also the period the grid operator uses for a unilateral reduction (art. 7.29).

What comes next depends on your processes. Processes that do not have to start at the same time can be spread over different quarter-hours. Look into whether an energy management system (EMS) can control your charge points and other controllable installations so that total offtake stays below the desired limit. Liander points out that you are free to choose your solution behind the meter, as long as you stay within the GTV.

A battery can flatten the peak (peak shaving) by discharging in the quarter-hours when offtake is highest. At medium voltage, kWmax is set month by month, so if the battery misses the peak in any month, that month is charged at the higher peak. The business case and subsidy rules are in our guide on business batteries.

Metalis, a metalworking company in Drachten, was given 0 kW of available capacity by Liander. At its site an EMS controls 450 solar panels and a 1.2 MWh battery, alongside a capacity restriction contract (CBC-T) with Liander (Metalis case study).

In a congestion area, flexibility can also lead to a contract with the grid operator. Under a capacity restriction contract (CBC), you give up full use of your connection and transport capacity in return for payment (ACM). ACM does not set a fixed price for this.

Since the code decision of 11 December 2025, the grid operator can also agree a voluntary capacity steering contract (CSC) with you. You then limit your grid use or use the grid in the opposite direction. The contract types are covered in our guide solving grid congestion.

A flexibility scan sets your quarter-hourly profile against your business processes and identifies measures. Our Flex-e guide explains the subsidy position on this. For what a scan costs, see our page on the cost of energy advice.

Frequently asked questions

Questions about peak demand and contracted capacity.

Will I get a penalty if I exceed my contracted capacity?

The Systeemcode elektriciteit 2026 (the Dutch electricity system code) governs how your contracted transport capacity is adjusted after an overrun; we found no penalty amount or separate overrun tariff at Liander, Enexis or Stedin. Outside a congestion area for offtake, your contracted offtake capacity goes up at medium voltage and at the medium-to-low voltage (MV/LV) transformer level, from the first day of the month of the overrun. You can request a reduction from the next calendar month at the earliest, but no sooner than twelve months after the last increase, unless you have reasonable grounds. In a congestion area for offtake it does not go up: Liander asks for measures within four weeks, and Enexis mentions disconnection or legal action as a last resort.

Can I reduce my contracted capacity?

Yes, on request. At medium voltage and MV/LV transformer level, the reduction takes effect no earlier than the first day of the calendar month after your request, and no sooner than twelve months after the last increase, unless you have reasonable grounds (Systeemcode elektriciteit 2026, art. 7.26). Outside a congestion area, the GTV goes back up retroactively to the overrun level if you exceed the reduced value within twelve months of your request. In a congestion area the GTV can no longer go up: getting reduced capacity back at Liander, Enexis and Stedin means a new application and joining the queue. Enexis warns that an increase there can sometimes take up to 10 years, so discuss a reduction with your grid operator first.

What is contracted capacity?

Contracted transport capacity (GTV) is the maximum capacity you may use on your connection, set separately for offtake and feed-in (Begrippencode elektriciteit 2026). It is equal to or lower than your connection capacity and is recorded in the connection and transport agreement (Systeemcode elektriciteit 2026, art. 7.24). For offtake GTV you pay the kW contract tariff (Liander, MV category 2026: €2.29 per kW per month), unless you have a variable transport right. At medium voltage, your actual highest load per month is the kWmax, which has its own tariff.

How is the kWmax on my invoice determined?

At medium voltage, kWmax is your highest load of the month, and each month counts separately. With a metering period of 15 minutes or less, the value per clock quarter-hour counts; with any other metering period, the highest value per metering period (Begrippencode elektriciteit 2026). Stedin describes it as the average load over 15 minutes, unless agreed otherwise. The 2026 medium-voltage tariff per kW per month is €3.57 at Liander, €3.66 at Enexis (MV-D) and €3.0966 at Stedin.

How much does a lower peak save on my grid bill?

That depends on your grid operator and grid level. Our calculation for medium voltage, at 2026 tariffs excluding VAT, assumes a monthly peak that is 100 kW lower every month. On kWmax that saves €4,284 a year at Liander, €4,392 at Enexis (MV-D) and €3,715.92 at Stedin. The kW contract charge only falls if the contracted capacity is reduced as well, and that is subject to the conditions of the Systeemcode (art. 7.26).

Can the grid operator reduce my contracted capacity?

In a congestion area it can, if at medium voltage you used no more than 50% of your GTV in the preceding twelve months. It can also do so if 1 MW or more is unused, provided in either case that the unused portion will not be used within a reasonable period (Systeemcode elektriciteit 2026, art. 7.29). You first receive written notice and then have two months to consult the grid operator. The new GTV becomes the highest kWmax of the preceding 24 months, or higher if you can make a plausible case from forecasts.

Are time-dependent grid tariffs coming for businesses?

They have applied to parties connected to TenneT's transmission system since 1 January 2025 (Netbeheer Nederland, 2026). For large consumers on the regional grids, such as those of Liander, Enexis and Stedin, there is a proposal from Netbeheer Nederland dated 13 March 2026. As of 23 September 2026 we found no draft or final decision from ACM, so no start date has been set. Under the proposal your GTV would stay unweighted, but the timing of your peak would also count towards kWmax.

Do I pay for reactive power?

Only for reactive energy above the amount that corresponds to a power factor of 0.85 inductive or 1.0 capacitive (Tarievencode elektriciteit 2026, art. 3.17). Reactive energy you exchange at the grid operator's request does not count. In 2026 Liander charges €0.0000 per kvarh for MV/LV and above, and Stedin €0.0169 for all categories. Enexis charges €0.0184 for MV and above and, according to its own tariff sheet, €0.0188 for LV above 3x80 A (2026 tariff sheets).

Free initial assessment

Have your quarter-hourly data analysed before you change your contract.

An initial assessment is free. We set your highest quarter-hours against your contracted capacity and your grid operator's rules. Then we discuss whether a reduction makes sense, or whether you would do better to tackle the peak first.

Discuss your situation →