Practical guide, updated October 2026

Solving grid congestion: all the options at a glance

Your company cannot get (extra) grid capacity, and the wait for a large-consumer connection can reach 10 years in congestion areas (how the queue works). Waiting is rarely necessary. There are seven proven routes that let you press ahead regardless. This guide sets them side by side: what each option is, when it makes sense, and what lead time and cost to expect.

No transport capacity available or connection refused: what can you do?

If you cannot get (extra) grid capacity, there are seven proven routes: an ANW contract, a capacity restriction contract (CBC-T), battery storage, cable pooling, an energy hub, load management and on-site generation. Which route suits you depends on your consumption profile, location and time horizon. In practice the solution is almost always a combination of two or three options.

The decision framework

Seven routes around a congested grid

Option What it is When to use it Lead time (indicative)
ANW contract
Connection with curtailment
A connection and transport agreement with curtailment, a form of capacity restriction contract: you get capacity faster, but accept that the grid operator curtails you at peak times. You are waiting for a (larger) connection and can absorb peaks with flexibility: a battery, scheduling or controllable processes. 3–6 months. This route gave Raben a connection within 6 months, against a standard wait of 5+ years, with at most 3 hours of curtailment a day.
CBC(-T)
Capacity restriction contract
You commit by contract to using less transport capacity at agreed times, in return for room on the grid. You already have a connection and can control your demand, or you want a faster connection with capped peaks. Metalis combined CBC-T with a battery and solar. 3–6 months for the contract; the flexibility needed on site sets the pace.
Battery storage
Behind-the-meter
A battery that shaves peaks, buffers on-site generation and, where the contract allows, takes part in the balancing market. Your peaks are short and predictable, or you want to make the most of on-site generation. Metalis: 1.2 MWh; Raben: 200 kWh alongside the charging hub. 6–12 months from design to commissioning.
Cable pooling
Sharing a connection
One connection shared between complementary profiles, such as solar and wind, or solar and EV charging. There is a neighbouring company or your own asset with a mirror-image consumption or generation profile. 6–18 months, depending on contracting and technology.
Energy hub
Shared infrastructure
Several companies share a connection, generation and storage, with a joint governance and settlement structure. You are on a business park where several parties are stuck, as at IBF Heerenveen and Azeven-Noord. 1–3 years including governance.
Load management / smart charging
Smart control within the existing contract
Scheduling consumption and charging sessions so that peaks stay within the contracted capacity. Your peak can be scheduled, as in logistics. BAT Tilburg runs 30 charge points rated at 400 kW and keeps total demand under 600 kVA, well within the 800 kVA connection. Often the fastest route: no new connection, but you do need control systems and software within the existing installation.
On-site generation
Solar PV behind the meter
Generating your own power reduces demand on the grid; combined with storage it also covers times without sun. You have roof or site space and a daytime profile that suits solar. Metalis installed 450 panels on the roof, linked to the battery. Depends on roof structure, permit and feed-in capacity; almost always in combination with storage or contractual arrangements.

Lead times based on Energyc projects (2024–2026). Investment costs vary widely by situation and capacity; the advisory work itself costs €4,500 to €40,000 (see the cost guide), of which the Flex-e scheme covered 50% in 2026.

Further reading by situation: upgrading a connection, peak demand and the kW tariff, solar panels under a feed-in limit and electric trucks with too little grid capacity.

The decision tree

Which route suits your situation?

Start with your bottleneck, not the technology. The four situations below cover almost all the grid congestion issues we encounter, each with the logical first route.

1. You are waiting for a new or larger connection

Look first at an ANW contract or CBC(-T): these often secure capacity within 3–6 months instead of years of waiting. The condition is that you can absorb peaks, usually with a battery or schedulable processes. That is how Raben got a connection within 6 months for 4 DC chargers rated at 400 kW, buffered by a 200 kWh battery.

2. You have a connection but are hitting the ceiling

The question then is: can you lower the peak? Load management is the fastest and cheapest step. If that is not enough, battery storage and on-site generation come next. Metalis got 0 kW of extra capacity and still began operating gas-free: 450 solar panels, a 1.2 MWh battery and a CBC-T contract.

3. You are electrifying your fleet or building a charging hub

Charging lends itself particularly well to scheduling. With smart charging, even heavy charging stays within a modest connection: BAT Tilburg controls 30 charge points rated at 400 kW so that total demand stays under 600 kVA, within a single 800 kVA connection. If your operating schedule calls for charging speed the connection cannot provide, a battery fills the gap; see our e-mobility transition advice.

4. You are developing, or based on, a business park where several parties are stuck

Individually there is often nothing to be gained; collectively there is. An energy hub or cable pooling bundles the profiles of several companies behind shared infrastructure. Allow 1–3 years including governance; IBF Heerenveen and Azeven-Noord show that it works. How to set up such a hub, including the group transport agreement (GTO) with the grid operator, is covered in the energy hub & GTO guide.

Rule of thumb: the more individual and contractual the solution (ANW, CBC-T, load management), the faster. The more collective and physical (hub, cable pooling), the longer the lead time, but also the more lasting the result.

How we work

What Energyc does for you

We are an independent advisor, not an installer or a supplier. We analyse your consumption profile and the grid situation at your location, work the promising routes through to a business case and negotiate the contract type with the grid operator. An initial assessment is free; analysis and design start from €4,500; complex projects with implementation support range from €15,000 to €40,000.

01

Initial assessment

Free initial meeting: grid situation at your location, consumption profile, preliminary choice of route. 30–60 minutes on site or online.

02

Flex scan or feasibility study

Flex scan (€5,000 to €10,000) or full feasibility study (€10,000 to €30,000). Flex-e covered 50% of this up to and including 15 October 2026.

03

Contract & design

Negotiating ANW/CBC-T with the grid operator, technical design of battery, generation or hub, subsidy stacking.

04

Delivery

Procurement or tender support, managing execution, completion and operating arrangements.

In 2026 the government paid half the cost of the advice

The Flex-e scheme run by RVO (Netherlands Enterprise Agency) covered 50% of a flexibility scan (a subsidy of up to €10,000) and 50% of a feasibility study (subsidy of €10,000 to €125,000). In 2026 any organisation with a large-consumer connection could apply: the old threshold of 100 kW contracted transport capacity had been dropped. RVO does not require accreditation but refers applicants to qualified advisors in the Netcongestie Register; Energyc is FedEC-accredited and carries out these projects. The 2026 application window closed on 15 October 2026 at 17:00. See the complete Flex-e guide or our broader subsidy overview.

50% Advisory costs covered: scan up to €10,000, study up to €125,000 Source: RVO Flex-e, 2026
Frequently asked questions

Questions about solving grid congestion.

What can you do if the grid operator cannot supply (extra) capacity?

You do not have to wait for grid reinforcement. There are seven routes: an ANW contract (faster connection with curtailment at peak times), a capacity restriction contract (CBC-T), battery storage, cable pooling, an energy hub, load management and on-site generation. In practice the solution is almost always a combination, such as a battery plus CBC-T (as at Metalis) or smart charging within the existing connection (as at BAT Tilburg).

What is the difference between an ANW contract and a CBC(-T)?

They are closely related: an ANW contract is a form of capacity restriction contract. With an ANW contract (a connection and transport agreement with curtailment) you get capacity faster, but the grid operator may curtail you at peak times, in Raben's case for no more than 3 hours a day. With a CBC(-T) you commit to using less transport capacity at agreed times, in return for room on the grid. Both call for flexibility on site, such as a battery or controllable processes.

How quickly can a grid congestion solution be in place?

An ANW or CBC-T contract is often arranged within 3–6 months; this route gave Raben a connection within 6 months, against a standard wait of more than 5 years. A battery system takes 6–12 months from design to commissioning, cable pooling 6–18 months and an energy hub 1–3 years including governance. For comparison: the wait for a large-consumer connection can reach 10 years in congestion areas.

What does it cost to have grid congestion solved?

An initial assessment with Energyc is free. Analysis and design start from €4,500, a flex scan costs €5,000 to €10,000 and a full feasibility study €10,000 to €30,000. Complex projects with implementation support range from €15,000 to €40,000. In 2026 the Flex-e scheme run by RVO (Netherlands Enterprise Agency) covered 50% of advisory costs (the application window closed on 15 October): a subsidy of up to €10,000 for a flexibility scan and €10,000 to €125,000 for a feasibility study.

What subsidy is available for grid congestion advice?

In 2026 the Flex-e scheme run by RVO (Netherlands Enterprise Agency) covered 50% of a flexibility scan (a subsidy of up to €10,000) and 50% of a feasibility study (subsidy of €10,000 to €125,000); flexibility measures such as a battery fell under a separate component (up to 40%, subsidy of €25,000 to €300,000). In 2026 any organisation with a large-consumer connection (above 3x80 A) could apply; the old threshold of 100 kW contracted transport capacity had been dropped. RVO does not require accreditation but refers applicants to qualified advisors in the Netcongestie Register. Energyc is FedEC-accredited and carries out Flex-e projects. The 2026 application window closed on 15 October 2026 at 17:00.

What is blokstroom, or a time-block contract?

Blokstroom is what the grid operators call the time-block transport right: you may draw extra capacity within a fixed time block, on top of your existing contracted capacity. The contract runs indefinitely and stays in force once the congestion has been resolved. What is on offer differs by grid operator. In the first phase Liander offers blokstroom only for consumption in Friesland and the Noordoostpolder, between 00:00 and 06:00. Enexis offers it where the substation has capacity between 00:00 and 06:00, and charges 25% of the blokstroom capacity; the remaining 75% is credited. In the first phase Stedin offers it only in Zeeland, and RENDO offers it between 00:00 and 06:00 while capacity lasts. You need a large-consumer connection above 3x80 A.

What is a non-firm ATO or alternative transport right?

A connection and transport agreement (ATO) normally gives you a 24/7 right to the full contracted capacity. In July 2024 the ACM (the Dutch regulator) gave the green light to alternative transport rights, known in the trade as non-firm ATO or NFA, which grant that right only subject to conditions, at a reduced transport tariff. There are now four forms: the standard ATO, a fully variable agreement (NFA 1.0, only in congestion areas, with a transport right as long as there is residual capacity), the time-duration transport right and the time-block transport right (blokstroom). They are open to new and existing customers with a connection above 3x80 A, inside and outside congestion areas. Outside them, the appeal is precisely the lower tariff. Which form suits you depends on how controllable your consumption is.

Sources & references

Sources

Real-world figures (lead times, system sizes) come from completed Energyc projects: Metalis, Raben Group, BAT Tilburg, IBF Heerenveen and Azeven-Noord.