Practical guide, September 2026

New or upgraded connections in the northern Netherlands: costs and lead times by grid operator

The regional grid operators Liander and Enexis have no fixed price for upgrading an existing large-consumer connection: both charge the actual costs, through a quote. Fixed tariffs do exist for a new connection: €8,883 to €530,091 at Liander in 2026, not including your own transformer. The connection deadline is 26 weeks, 52 weeks or set case by case, plus a regional waiting time. It does not apply where there is congestion (ACM, 2024).

What does upgrading my large-consumer connection cost, and how long does it take?

For upgrades, Liander and Enexis charge the actual costs rather than a fixed tariff; according to Enexis, it often ends up as a new connection at a different grid level. For comparison, a new 630 kVA connection in 2026 costs €35,644 one-off at Liander and €27,366 at Enexis, excluding VAT. Both also require your own transformer, and we did not find its cost in any tariff sheet. The connection deadline is 26 weeks, 52 weeks or set case by case, plus a regional waiting time; it does not apply where there is congestion (ACM, 2024).

Adjusting expectations

Upgrades are bespoke work, and at Enexis often mean a new connection

"Increasing the capacity of a large-consumer connection is possible in only a limited number of situations," Enexis writes. According to Enexis, a new connection at a different grid level is needed in many cases, and each application is assessed individually. "We therefore cannot quote standard amounts" (Enexis, Uw grootzakelijke aansluiting verzwaren).

Grid operatorUpgrade priceNotes
LianderFrieslandNo fixed tariff. Liander makes "a separate calculation" and invoices the actual costs; you request a quote.The fixed one-off tariff applies to a new permanent connection.
Enexislargely Groningen and DrentheNo fixed tariff. The actual costs, "based on an advance cost calculation"; the tariff sheet lists all eight capacity-increase routes as bespoke.Upgrading is possible "in only a limited number of situations". The connection may get a new EAN code, which you pass on to your supplier and metering company.
RENDOsouth Drenthe and north OverijsselAdvance cost calculation: at least the difference between the one-off tariffs for the new and old capacity, and never less than €135.No higher than the price of a new connection including any extra length, plus the removal of a connection. A change to the metering installation is arranged through your own metering company.

Source: Liander, Tarieven voor eenmalige klantdiensten elektriciteit grootverbruik 2026 (version 2026.1.0); Enexis, Eenmalige aansluittarieven elektriciteit grootverbruikers per 1 januari 2026 (v2.0) and Uw grootzakelijke aansluiting verzwaren; RENDO, Tarieven (eenmalige) aansluitdiensten elektriciteit grootverbruikers 2026 (version 1.0). Accessed on 23 September 2026.

Of the tariff sheets we consulted, only RENDO's gives a lower and an upper limit. Worked example (our own calculation from the RENDO tariff sheet): from category 4 (€9,025) to the class above 0.15 up to and including 0.63 MVA (€38,300), the minimum is €29,275. The maximum is the €38,300 for a new connection, plus any extra length and the cost of removing a connection.

For budgeting purposes, our reading is this: you will only have a figure for an upgrade once you have the quote. The one-off tariff for a new connection in the class you need is a benchmark, not a price. So first check whether you really need a larger connection, or just more contracted capacity.

Connection capacity or contract

A larger connection, or just more contracted capacity?

A large-consumer connection has two limits. Connection capacity is what the connection can technically handle. Contracted transport capacity is set out in your connection and transport agreement (ATO): "the maximum capacities you may use on your connection", for offtake and feed-in (Liander, tariff sheet 2026).

The transport capacity you request "cannot be higher than the 'technical' capacity of the connection"; if you want more, you need a larger connection (Liander). Within the existing connection capacity, you request more contracted capacity through Mijn Liander. That is not possible either "if insufficient capacity is available on the grid"; according to Liander, the upstream grid must then be reinforced first (Liander, tariff sheet 2026).

Liander publishes the maximum consumption and feed-in per connection category. In category AC5a, above 160 up to and including 630 kVA, that is 535 kW of consumption and 630 kW of feed-in. In AC5b, above 630 kVA up to and including 1 MVA, it is 850 kW and 1,000 kW (Liander, Soorten grootverbruikaansluitingen). If your new capacity requirement fits within the maximum of your current category, more contracted capacity is the first thing to ask your grid operator about.

Exceeding your contracted capacity is not the same as upgrading. Liander treats an overrun as a request for an increase and normally adjusts the contract automatically for the whole calendar year. That does not happen "in congestion areas for the same direction of energy flow" (Liander, tariff sheet 2026). Enexis emails and calls you if you exceed your contract in a region where transport capacity is scarce; if you keep doing so, "we may disconnect you or take legal action" (Enexis, network costs 2026).

At RENDO, an increased contracted capacity applies "for a period of at least 12 months" before it can be lowered (RENDO, network tariffs 2026). So at RENDO, base an increase on a sustained need, not a single spike.

Moving from a small-consumer to a large-consumer connection means more to arrange. Above 3 x 80 A you choose your own metering company, and no maximum metering tariff applies (ACM, Netbeheerkosten). You enter into an ATO with the grid operator, and Liander requires the contracts with supplier and metering company to be in place at least 20 working days before commissioning. Enexis does not allow you to split a connection to stay under the limit: "You may have a maximum of 1 connection per property (WOZ object)" (Enexis, Nieuwe grootzakelijke aansluiting aanvragen).

2026 tariffs

What a new connection costs at Liander, Enexis and RENDO

Liander, Enexis and RENDO do publish fixed amounts for a new large-consumer connection, by capacity class. You pay a one-off connection tariff and then a periodic fee for the connection service (Liander, tariff sheet 2026). Separately you pay the transport tariff; at Liander this depends on the sub-market, which follows from your contracted transport capacity. The meter is not included: those costs are charged by "your energy supplier and metering company" (Enexis, network costs 2026).

Class (Liander)Max. consumptionOne-offExtra lengthPer month
> 3x80 A up to 100 kVAAC4a, general supply point94 kW€ 8.883€87.60 per m€ 22,09
> 100 up to 160 kVAAC4b, general supply point147 kW€ 9.916€101.30 per m€ 24,79
> 160 up to 630 kVAAC5a, with transformer and LV metering535 kW€ 35.644€202.00 per m€ 88,62
> 630 kVA up to 1 MVAAC5b, with transformer and LV metering850 kW€ 45.237€202.00 per m€ 88,62
> 1 up to 2 MVAAC51,700 kW€ 64.485€219.00 per m€ 162,17
> 2 up to 5 MVAAC6a4,250 kW€ 442.982€236.00 per m€ 1.107,00
> 5 up to 10 MVAAC6b8,500 kW€ 530.091€384.00 per m€ 1.325,00
> 10 MVAAC6cbespokeon request—bespoke

Liander, Tarieven voor eenmalige klantdiensten elektriciteit grootverbruik 2026 (version 2026.1.0) and Tarieven voor aansluiting en transport elektriciteit grootverbruik 2026 (version 2026.1.1); maximum consumption from Liander, Soorten grootverbruik elektriciteitsaansluitingen. Amounts exclude VAT. The one-off tariff includes up to 25 metres of connection cable; the extra-length price includes standard excavation and paving, and Liander charges more for non-standard constructions.

The periodic tariffs for the transformer classes exclude transformer rental, which is a free-market service. For a connection above 3x80A on the LV grid, Liander charges €5.15 per month. For connections from 3 MVA up to and including 10 MVA, €0.29 per metre per month is added per cable for every metre above 25 metres.

Cable length matters. Liander measures from the nearest connection point on the grid to the meter installation, and every metre above 25 is extra length. Worked example (our own calculation from the Liander tariff): if the meter installation is 75 metres from that connection point, the extra length is 50 metres. In the class above 160 up to and including 630 kVA, that adds 50 × €202 = €10,100 on top of the €35,644.

Capacity (Enexis)Grid levelOne-offExtra lengthPer year
3 x 160 AMV/LV, 0.4 kV€ 6.445€98.30 per m€401.00class > 3 x 80 A up to 3 x 250 A
3 x 250 AMV/LV, 0.4 kV€ 8.520€98.30 per m€401.00class > 3 x 80 A up to 3 x 250 A
630 kVAMV-D, 10/20 kV€ 27.366€159.00 per m€1,742.00class > 3 x 250 A up to 1,750 kVA
1,750 kVAMV-D, 10/20 kV€ 61.098€159.00 per m€1,742.00class > 3 x 250 A up to 1,750 kVA
6,000 kVAMV-T, 10/20 kV€ 439.605€372.70 per m€4,804.00class > 3 up to 6 MVA
10,000 kVAHV/MV, 10/20 kV€ 626.698€406.70 per m€5,638.00class > 6 up to 10 MVA
> 10,000 kVA—bespoke—bespoke

Enexis, Eenmalige aansluittarieven elektriciteit grootverbruikers per 1 januari 2026 (v2.0) and Netwerkkosten grootverbruik standaard aansluitingen per 1 juli 2026 (v1.1). Amounts exclude VAT; the one-off tariff includes paving on the public road and up to 25 metres of cable route. The fixed one-off amounts apply to standard new connections; N-0 connections and connections above 10 MVA are bespoke. The periodic fee for above 6 MVA N-0 up to and including 10 MVA N-0 is also bespoke.

The periodic fee has its own classes; the table shows the class each connection capacity falls into. The class above 1,750 kVA up to and including 3 MVA also costs €4,804 per year. The periodic extra-length charge applies at 3 MVA or higher with a cable route longer than 25 metres. It costs €6.29 per metre per year up to and including 6 MVA, and €6.96 above 6 up to and including 10 MVA.

The Enexis tariff assumes a clear, clean route across your own site. Without one, the tariff may be higher, for example because sealed paving has to be broken up and reinstated or the ground improved. Enexis also cites the removal of rubble or contaminated soil and delays caused by the customer (Enexis, one-off connection tariffs 2026). For commissioning a large-consumer connection, Enexis charges €385.87, excluding VAT (Enexis, other tariffs 2026).

Category (RENDO)ClassOne-offExtra lengthPer year
4LV connection> 3x80 A up to 3x225 A€ 9.025€79.45 per m€ 77,25
5transformer MV/LV> 0.15 up to 0.63 MVA, LV metering€ 38.300€211.85 per m€ 340,25
5transformer MV/LV> 0.63 up to 1.2 MVA, LV metering€ 43.200€211.85 per m€ 340,25
6MV Distribution> 1.2 up to 2 MVA, MV metering€ 101.600€211.85 per m€ 1.000,00
7MV Transport or Distribution> 2 up to 5 MVA, MV metering€ 607.200€386.10 per m€1,000.00with MV Distribution
8MV Transport or Distribution> 5 up to 10 MVA, MV metering€ 659.200€497.75 per m€1,000.00with MV Distribution
9MV Transport or Distribution> 10 MVA, MV meteringadvance cost calculation——

RENDO, Tarieven (eenmalige) aansluitdiensten elektriciteit grootverbruikers and Nettarieven elektriciteit grootverbruikers, both as of 1 January 2026 (version 1.0). Amounts exclude VAT. Category 4 has five sub-classes, from > 3x80A up to 3x100A to > 3x200A up to 3x225A, at the same tariff up to and including 25 metres.

Categories 7 to 9 are MV Transport for a direct connection to the 110/10 kV substation, otherwise MV Distribution. The periodic tariff for MV Transport is not in this table. With MV Distribution, €13.55 per metre of extra length per year is added above 3 MVA.

Watch the units: Liander publishes the periodic fee per month, Enexis and RENDO per year. The three grid operators' classes do not line up, so a row in one table does not correspond to a row in another. The transport tariff is not included here; how it is calculated from contracted capacity and the monthly peak is explained in our guide to peak demand and contracted capacity.

Substation and step change

Two thresholds: your own substation and the 2 MVA limit

The first threshold is your own substation. At Enexis, above 173 kVA you "always" need a customer substation: a medium-voltage (MV) substation whose transformer converts at least 10,000 volts to a lower voltage level. Enexis installs the regulated part, such as the MV installation and the connection to the public grid. You have the non-regulated part, including the transformer and housing, installed by one or more accredited metering companies of your choice (Enexis, MS-aansluiting en klantstation aanvragen).

Enexis's Programme of Requirements (PvE) covers compact and walk-in customer substations, up to and including 630 kVA and up to and including 1,750 kVA. Above 1,750 kVA it is a walk-in substation for MV-T or HV-MV (Enexis, PvE version 2.8). The PvE also applies to upgrades, where Enexis's switchgear is replaced or a different intake station is needed. This applies to applications received from 1 October 2025.

At Liander the limit is 160 kVA. For a connection above 160 kVA up to and including 10 MVA, Liander requires a purpose-built room, the intake room (inkoopruimte). Liander installs the regulated part there; your own distribution switchgear and transformer go in a separate room. You may start building only after Liander has approved the production drawing, in line with Programme of Requirements S10505 (indoor) or S10506 (prefab) (Liander, Technische en bouwkundige eisen).

The PvE for an indoor intake room requires at least 1,200 mm of service clearance in front of the switchgear and doors with a clear opening of at least 1,150 mm. The access route must allow a load 3.0 metres wide to pass, with a clear height of at least 4.2 metres (Liander, PvE S10505). Liander asks you to allow now for a transition from the 10 kV to the 20 kV grid. As an example it cites "a switchable transformer and suitable cables" (Liander, Soorten grootverbruikaansluitingen).

At RENDO, above 0.15 up to and including 1.2 MVA is category 5, "Aansluiting trafo MS/LS" (transformer connection, MV/LV). Above 1.2 up to and including 2 MVA is MV Distribution. Above 2 MVA, MV Transport applies for a direct connection to the 110/10 kV substation, otherwise MV Distribution (RENDO, tariff sheet 2026).

We did not find the cost of your own substation in any of the Liander, Enexis or RENDO tariff sheets. On the transformer classes, Liander writes: "Excludes transformer rental, which is a free-market service." We have not verified market prices and therefore give no figure. Our reading: the costs depend on factors including the type of substation, whether it is indoor or prefab, whether the transformer is owned or rented, and the space requirements in the PvE.

The second threshold at Liander and RENDO is 2 MVA. At Liander the class above 1 up to and including 2 MVA costs €64,485 one-off, and the class above it €442,982. At RENDO it is €101,600 against €607,200. At Enexis the jump comes between 1,750 kVA on MV-D (€61,098) and 6,000 kVA on MV-T (€439,605).

Our calculation from the tariff pairs above: the higher class costs roughly six to just over seven times as much. The capacity classes compared differ by grid operator.

The tariff sheets give no explanation. Liander fits connections above 2 MVA that connect directly to one of its substations with an additional DC installation for protection (Liander, PvE S10505).

If your requirement sits just above one of those two thresholds, first work out whether a lower peak keeps you in the class below. How that works is explained in our guide to peak demand and contracted capacity.

Application process

From application to reservation: Liander and Enexis side by side

"An application is not yet a reservation on the electricity grid," writes Liander. Capacity or your place in the queue is definitively reserved only once you have returned the signed ATO and the order form. You have 30 days for this, the validity period of the quote (Liander, step-by-step guide). At Enexis, a signed quote is required to join the queue; a mere notice that no capacity is available does not secure a place (Enexis, Wachtlijst voor transportcapaciteit).

StepLianderEnexis
ApplyingFirst a price indication, which you convert into a quote request. Liander then gets in touch within 2 weeks.Enexis gets in touch within 5 working days of submission. If someone else applies on your behalf, such as an installer or advisor, a power of attorney is required.
QuoteAfter a grid check that there is room for the required capacity, you receive a quote with an ATO, or Liander contacts you first.Within 10 working days "once your application is complete". The quote states whether capacity is available.
Securing your placeOrder form and ATO returned signed within 30 days; capacity or your place in the queue is then definitively reserved.Signing via a link, confirmation by letter. No signed quote, no place in the queue.
PaymentFirst invoice after signing, second before the excavation work; the final invoice settles any additions or omissions.Applications from 1 July 2026, quote above €10,000: 20% deposit, 70% before work starts, 10% after completion.
Completion dateYou are given the final connection deadline "usually within 5 working days" of Liander receiving the signed documents.You receive the latest completion date by email within 5 weeks of accepting the quote. In the planning phase Enexis carries out a quick assessment.
What you arrangeFor AC5 and AC6 (above 160 kVA), a purpose-built room in line with the PvE and a person responsible for the installation. No later than a week before installation, items including an earthing report, a clean soil declaration, an asbestos-free cable route and a building with glazing fitted. Liander arranges permits and the soil report for public land.Soil investigation on your own site and responsibility for the installation. Depending on capacity, also a transformer and switchgear. Enexis arranges permits and soil investigation on public land.
ContractsWith energy supplier and metering company, at least 20 working days before commissioning.With energy supplier and metering company, based on the EAN code you receive from Enexis. With an upgrade, that code may change.
PavingFor AC5 and AC6, you are responsible for the paving at the customer substation. If you lay it yourself, you must do so within 10 working days of commissioning; otherwise Liander does it and charges €1,250 as additional work.The one-off tariff includes paving on the public road.

Source: Liander, Stappenplan aanvragen nieuwe grootverbruik elektriciteitsaansluiting and Nieuwe elektriciteitsaansluiting aanvragen; Enexis, Nieuwe grootzakelijke aansluiting aanvragen and Uw grootzakelijke aansluiting verzwaren (both with the same step-by-step guide), Eenmalige aansluittarieven 2026 and Oplevertermijnen elektriciteitsaansluitingen. Accessed on 22 and 23 September 2026.

The Enexis schedule applies to applications from 1 July 2026. With a quote above €10,000, you therefore pay 90% before work starts (our calculation: 20% plus 70%). For applications before 1 July 2026, a 50% deposit applied above €10,000, and above €250,000 first 10% and then 40% before work started. The deposit invoice follows within 14 days of acceptance, with a payment term of 14 days (Enexis, Nieuwe grootzakelijke aansluiting aanvragen).

At Enexis, what counts for your place in the queue, after the ACM's priority rules, is the moment "the quote request was completed". For more contracted capacity, it is the moment of that application (Enexis, Wachtlijst voor transportcapaciteit). We found no public checklist at Liander or Enexis of the details that make an application complete. You can, however, have ready in advance what the grid operators ask for during the process:

  • The capacity you need, for offtake and any feed-in; those capacities go into the ATO. Liander recommends deciding on the connection together with an accredited installer.
  • A power of attorney, if someone else applies on your behalf, such as an installer or advisor (Enexis).
  • At Liander, above 160 kVA up to and including 10 MVA: a plan for the intake room in line with PvE S10505 (indoor) or S10506 (prefab).
  • A person responsible for the installation, appropriate to the connection: according to Liander, NEN 3140 for low voltage (AC4) and NEN 3840 for medium voltage (AC5).
  • Soil data: a soil investigation on your own site (Enexis), or a clean soil declaration for your own land, preferably in line with the current CROW publication (Liander).
  • Contracts with an energy supplier and a metering company, at Liander at least 20 working days before commissioning.

This is not an official list, but a compilation of what the step-by-step guides ask for. If in doubt, ask your grid operator which details it needs in advance.

Lead time

How long it takes: connection deadline plus regional waiting time

Depending on complexity, the connection deadline for a large connection is 26 weeks, 52 weeks or a reasonable period set by the grid operator (ACM, code decision 2024). On top of that, the grid operator may add extra waiting time per quarter and per region. The 2024 ACM decision sets a maximum of 40 weeks' extra regional waiting time, with that maximum tapering off over the following ten years. Enexis publishes this by regional office: in the third quarter of 2026 it is 38 weeks in Groningen and 36 weeks in Drenthe (Enexis, Oplevertermijnen).

For Friesland, all we found at Liander was an illustrative worked example with 40 weeks' regional waiting time, which according to Liander confers no rights (Liander, Aansluittermijnen grootzakelijk). For large business connections applied for before 1 January 2025, the average lead time at Liander was almost 2 years (Liander, Levertijden onder druk).

The connection deadline does not apply where there is congestion. The ACM cites 3 months after the congestion is resolved; Liander and Enexis cite 13 weeks, each with its own conditions. Enexis counts from the moment transport capacity becomes available to you, "unless force majeure applies". Without capacity your application goes into a queue, and according to Enexis "the waiting time can then run to as much as 10 years" (Enexis, Doorlooptijden).

Liander advises applying for a connection straight away if you already know your plans "a year in advance" (Liander, Nieuwe elektriciteitsaansluiting aanvragen). Through Klant Sluit Zichzelf Aan (KSZA, the customer connects itself), an installer accredited by Liander can build a connection of 160 kVA to 2.0 MVA. This is also possible when moving, replacing or removing a connection, at no extra cost compared with a regular connection. KSZA shortens the construction lead time but "has no influence on the availability of capacity in congestion areas" (Liander, KSZA).

Raben Group secured the connection for a 400 kW DC charging hub for logistics within 6 months instead of 5+ years. The hub has been operational since Q4 2024. How the queue works and when you can apply for priority is covered in our guide to the grid operator's queue. For a truck charging hub there is a separate guide on charging electric trucks on an undersized grid connection.

If it cannot be done

Decision guide: upgrade, flexible contract, battery or peak reduction

Without transport capacity on the grid there is no increase in contracted capacity and no firm capacity on a larger connection; you then join a queue. Some routes work with less firm capacity. The table below helps you choose which to discuss with your grid operator.

SituationRoute to discussNoteRead more
Your connection can technically handle more than your contracted capacityMore contracted capacityAt Liander through Mijn Liander, unless grid capacity is insufficient. At RENDO an increase applies for at least 12 months.Peak demand
You have a sustained need for more than the connection can technically deliver, and grid capacity is availableUpgrade or a new connectionBespoke, through a quote. At Liander, connections above 160 kVA up to and including 10 MVA require an intake room; at Enexis, connections above 173 kVA require a customer substation.The tariffs and application process above
The extra consumption can happen at night or at varying timesAlternative transport rightEnexis: time-block transport (Blokstroom) for offtake between 00:00 and 06:00. Liander: Blokstroom and Reststroom are "in development" according to its own page. Netbeheer Nederland (the grid operators' association) also describes non-firm and duration-limited contracts, with a discount on the transport tariff.Solving grid congestion
You can cut back your demand when the grid is congested, for example with a batteryCongestion product or congestion mitigatorLiander offers CBC-A, CBC-T, CSC and the bid-obligation contract, among others, in return for a fee. A congestion mitigator does not automatically receive transport capacity (Netbeheer Nederland).Business battery
Your peak is brief, or you sit just above a class limitLower the peakNetbeheer Nederland cites saving energy and shifting consumption away from peak times as options for those waiting. At Liander and RENDO the one-off tariff jumps above 2 MVA.Peak demand, flexibility scan
Your neighbours on the business park are in the same situationGroup contract or energy hubEnexis is developing the group transport agreement with 10 business parks and expects to offer it more widely from 2027.Energy hub

Decision guide by Energyc based on the sources in this guide. Whether a route is possible for your connection is for the grid operator to decide.

At Enexis, you have been able to apply for Blokstroom for offtake since 1 April 2025; it is not yet available for feed-in (Enexis, Alternatieve transportrechten). You pay for 6 of the 24 hours, "in other words 25% of the contracted transport capacity (GTV) for Blokstroom; the remaining 75% is credited to you". Enexis sets the tariff category based on your current GTV plus the full Blokstroom GTV (Enexis, Blokstroom).

Blokstroom is available only if the substation you are or will be connected to has capacity between 00:00 and 06:00, in areas with and without congestion. Your existing contracted capacity is retained (Enexis, Blokstroom).

If there is insufficient capacity for Blokstroom, your application at Enexis can go into a separate queue. This does not affect a pending application for firm capacity. If firm capacity is granted later, the Blokstroom capacity is retained (Enexis, Blokstroom).

Enexis reserves the right to adjust the time window "if the grid risks overload". Anyone who routinely takes power outside the window risks suspension or termination of the transport right (Enexis, Blokstroom).

The picture for Friesland is less clear. On its own page, Liander describes Blokstroom and Reststroom (residual-capacity transport) as "in development" and expects to offer them "at the end of 2025". That text was still there on 23 September 2026; the same page also states that Blokstroom is "not yet available everywhere" (Liander, Transportovereenkomsten). You will need to ask Liander whether it is available for your connection.

Liander does describe congestion products, which let you deploy flexible capacity in return for a fee. These are CBC-A (on call), CBC-T (with a fixed time window), the capacity steering contract (CSC), the bid-obligation contract and the group CBC, shared with "grid neighbours". The fee depends on the situation, including for those in the queue who receive capacity through a congestion product (Liander, Congestieproducten).

Metalis, a metalworking company in Drachten, was given zero kilowatts of available capacity by Liander. The company uses 450 solar panels, a 1.2 MWh battery and a CBC-T contract with Liander, controlled by an EMS.

Anyone using flexible capacity to make room for others can apply for congestion mitigator status: category 1, the highest priority. "However, this does not mean that congestion mitigators automatically receive transport capacity," writes Netbeheer Nederland (Stand van de Uitvoering 2025, p. 21). The grid operator first checks whether the application meets the conditions, then whether the solution can actually contribute technically to reducing congestion. What a battery costs and what it earns is covered in our guide to the business battery.

A route for business parks is in development. Enexis is working with 10 business parks on the group transport agreement (GTO): one transport contract for a group of companies sharing an agreed transport capacity. Each company keeps its own connection, and Enexis expects to offer the GTO to a wider group "from 2027". Conditions include a connection above 3 x 80 A, the same voltage level, the same transport distribution station and an energy management system (Enexis, GTO).

We could not establish from Liander's current pages whether it offers a comparable group contract. Whether an energy hub suits your site is discussed in the guide energy hub: is it right for our business park?

Frequently asked questions

Questions about new and upgraded connections.

What does it cost to upgrade a connection with Liander?

Liander has no fixed tariff for upgrades; you request a quote. For changes to a connection above 3x80 amps, Liander calculates the work separately and invoices the actual costs (Liander, one-off tariffs 2026). What is fixed is the tariff for a new connection, such as €35,644 for the class above 160 up to and including 630 kVA (2026, excluding VAT). Connections above 160 kVA up to and including 10 MVA need your own or a rented transformer; those costs are not in the tariff sheet.

What does it cost to upgrade a connection with Enexis?

When connection capacity is increased, Enexis charges the actual costs, based on an advance cost calculation; the 2026 tariff sheet lists all eight capacity-increase routes as bespoke. According to Enexis, upgrading is possible in only a limited number of situations, and in many cases a new connection has to be made at a different grid level. For comparison, a new 630 kVA connection costs a one-off €27,366 excluding VAT, not counting the transformer, which you arrange to have installed. For applications from 1 July 2026 with a quote above €10,000, you pay a 20% deposit, 70% before work starts and 10% after completion.

How long does it take to apply for or upgrade a large-consumer connection?

For a connection above 3 x 80 A the deadline is 26 weeks, 52 weeks or set case by case, depending on complexity (ACM, 2024; Liander and Enexis). The 2024 ACM decision provides for up to 40 weeks' extra regional waiting time, with that maximum tapering off over the following ten years. Enexis gives 38 weeks in Groningen and 36 in Drenthe (third quarter of 2026); for Friesland we found only an illustrative example from Liander. The connection deadline does not apply where there is congestion; without capacity, the wait can run to as much as 10 years, according to Enexis.

When is grid capacity reserved for my application?

At Liander, an application is not yet a reservation on the grid. Capacity or a place in the queue is only definitively reserved once the signed connection and transport agreement (ATO) and the order form have been received; you have 30 days to return them. At Enexis, a signed quote is required to join the queue, and simply being told that no capacity is available does not secure a place. Once the priority rules have been applied, Enexis goes by the moment you applied for a contract increase, or the moment the quote request was completed.

When do I need my own transformer or customer substation?

At Enexis, above 173 kVA you always need a customer substation, a medium-voltage substation whose transformer and housing you arrange to have installed. At Liander, a connection above 160 kVA up to and including 10 MVA requires an intake room, with your own distribution switchgear and transformer. At RENDO, above 0.15 up to and including 1.2 MVA is category 5, "Aansluiting trafo MS/LS" (transformer connection, MV/LV). We did not find the cost of the transformer and the room in any of these three grid operators' tariff sheets.

What is the difference between connection capacity and contracted capacity?

Connection capacity is what the connection can technically handle; contracted transport capacity is the maximum you may use under your connection and transport agreement. According to Liander, the contract cannot exceed the technical capacity: if you want more, you need a larger connection. Within the connection capacity, you can apply to Liander for more contracted capacity through Mijn Liander, unless there is insufficient capacity on the grid. Liander states the maximum per category, for example 535 kW of consumption for a connection above 160 up to and including 630 kVA.

What changes if my connection goes above 3 x 80 A?

Above 3 x 80 A you have a large-consumer connection and choose your own metering company; the ACM (the Dutch regulator) sets no maximum metering tariff for large connections. You enter into a connection and transport agreement (ATO) with the grid operator, setting out the capacities for offtake and feed-in. Large connections are subject to maximum tariffs set per grid operator, including for contracted capacity and the maximum measured capacity per month (ACM). Liander requires you to have a contract with an energy supplier and a metering company at least 20 working days before commissioning.

What can I do if an upgrade is not possible or takes too long?

At Enexis you can apply for time-block transport (Blokstroom): transport capacity for offtake between 00:00 and 06:00, if the substation has capacity during those hours. Liander still describes Blokstroom and Reststroom as "in development" and sets out congestion products such as the capacity restriction contract, under which you deploy flexible capacity in return for a fee. Anyone granted congestion mitigator (congestieverzachter) status moves up the queue but, according to Netbeheer Nederland (the grid operators' association), does not automatically receive transport capacity. Netbeheer Nederland also points to saving energy and shifting consumption away from peak times as options for those waiting.

Free initial assessment

Do you know which connection you really need?

An initial assessment is free. You share your consumption profile and your plans; we work out which capacity class fits and which route to discuss with the grid operator. We are not an installer and have no stake in the choice.

Discuss your situation →
Sources & references

Sources